La Tuna Factory Roof RFI.docx

DOCX document 15 KB Posted

Attached to
Factory Roof
Solicitation number
EP2958-23
Issued by

View the file

Other files

File Type Posted
Roof pictures 2.pdf PDF
SF30 Factory EP2958-23 MOD 3.pdf PDF
SF30 Factory EP2958-23 MOD 2.pdf PDF
FCI.pdf PDF
SF30 Factory EP2958-23.pdf PDF
1620000090 Factory Roof.pdf PDF
La Tuna Wage Determination.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Does the DOJ prefer a specific flat roof system if replacement is recommended? For example: single ply, BUR, SBS modified Three ply hot mop system

Does the DOJ prefer a specific metal roof system if replacement is recommended? For example: standing seam, exposed fastener

NO

To make the bidding more comparable between bidders, can the DOJ quantify the amount of roof repair per roof deck? For example: roof area repair to cover 500 square feet, with any additional repair to be addressed through unit cost.

The Factory roof is 44,445 sq ft Is there any risk of the roof areas containing Asbestos? If unknown or yes, is it the responsibility of the contractor to determine if there is Asbestos containing roof material?

To our knowledge there is no asbestos on the roof, you may do an asbestos test.

Will photography be provided of existing work areas and job site conditions?

Photos posted on sam.gov.

What is the intended life expectancy of repairs or work provided with this contract?

The life expectancy of repairs will constitute on material used and their workmanship Contractor will give time frame.

Is manufacturer warranty required for work performed with this contract? If so, what duration?

The company will give the manufacture warranty on what material they will use.

Please confirm that if once on site and additional repairs are discovered outside the amount specified in the contractor’s proposal, change orders will be issued for the additional work.

Change orders may be issued for any additional work discovered.

Can the agency provide a set square footage of repairs they want quoted for the roof? This will allow us to establish a set unit price for repairs once onsite.

Inside Unicor = 44,445 sqft View Attachments

Does the DOJ have a preferred roof coating system? For example: silicone, acrylic, elastomeric NO with the new roof everything is added to the roof

Do you have the SCOPE OF WORK for each of the Buildings available, and do you have any details on the time frame of Project completion, any additional information of the project and expectations will be appreciated.

Expectations are;

Dispose of all debris (loose gravel and single ply material) Remove existing single ply system and fanfold Install new plumbing vents Reseal goosenecks, ducts, and replace pitch pans as needed Reseal JV and stack vents Remove and replace roof jacks Remove and replace metal scupper Detach and replace edge metal New drain baskets for all Any additional work needed to complete the job.

File details come from the government source that posted it. Updated .