EMG Alteration (45 Days) (5).pdf

PDF 112 KB Posted

Attached to
Emergency Commercial Demolition: 6911 E Lafayette
Solicitation number
300000152308649
Issued by
Michigan

About this file

This is an Emergency Commercial Alteration Timeline document related to a Michigan commercial project located at 6911 E Lafayette. The document outlines a 45-day alteration schedule with critical project milestones measured in calendar days from the Notice to Proceed (NTP). The alteration work begins immediately, with the open hole approval occurring at day 3, followed by Certificate of Approval at day 30, site finalization at day 40, and pre-invoice approval at day 45. The timeline extends to day 105 for final completion or closeout procedures. The project represents emergency commercial alteration services required to address immediate facility needs at the specified Lafayette Avenue location.

No pricing terms, set-asides, incumbent information, or funding details are specified in this timeline document. The file serves primarily as a scheduling framework to ensure coordinated progression through approval stages and project completion within the established 105-calendar-day window. Contractors responding to this opportunity should be prepared to meet aggressive timelines, particularly the initial 3-day approval window for the open hole phase and the overall 45-day completion target for primary alteration work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Emergency Commercial

Alteration Timeline

Begin Alteration

Open Hole Approved

Certificate of Approval

Site Finalization

Pre-Invoice Approved

Number of Calendar Days from

NTP

3 30 40 45 105