ABE_ATCT_-_Appendix_B.pdf
PDF 32 KB Posted
- Attached to
- Fuel Storage Tank Replacement-Allentown, PA
- Solicitation number
- DTRT57-14-Q-80078
About this file
Attachment J.4 Site Survey
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage_Determination-Allentown.txt | TXT text file | |
| Project_Plan_Specifications_ABE-ATCT_8-29-14Clean.pdf | ||
| RFQ_No._DTRT57-14-Q-80078.pdf | ||
| Typical_AST_Tank_Layout.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Name:
331 Airport Drive
0 LF
0.3 CY to be installed
(to replace removed asphalt)
0 EA 0
CIVIL INSTALLATION Baseline Quantity Actual Quantity
1 EA 2
Remove conduit/s? NO Remove fuel oil control valve/s? NO
0 EA 0
0 EA
0 EA 0
ELECTRICAL DEMOLITION Baseline Quantity Actual Quantity 0 EA 0Remove DDCP fuel control panel/s? NO
6 LF 0
Tank Replacement
0 EA 0Close in Place Underground Piping? NO
26 LF
Remove vent line/s? NO
2500-gal
0 EA 1
0 EA 1
0 EA 0
MECHANICAL DEMOLITION Baseline Quantity Actual Quantity
0 EA 1
Tank Repair
Remove entire daytank control panel/s? NO Remove Pump motor starter/s? NO
0 EA 0
0 EA 0
Remove Fuel Tank Monitor/s? YES Remove ERMS Connection/s? NO Site Specific Electrical Demolition:
Gravel Removal? YES
Asphalt Trenching Installation? YES
0 CY 10 CY
0 CY 0.5 CY
1-1000 EA
Site Specific Mechanical Demolition:
Mode of transportation to the facility for equipment delivery? Truck
Asphalt Trenching removal? YES
Concrete Trenching removal? YES
Remove submersible pump/s? NO wall and will cut across an asphalt driveway, a concrete sidewalk, underneath radiator water lines, and a water pipe support post.
Asphalt and Concrete removal will be required. Concrete curb repair may also be necessary.
Bollard removal? YES Site Specific Civil Demolition:
0 EA
Baseline Quantity Actual Quantity
0 LF
0.3 CY to be removed
12' X 2' X 4"
Close in Place Underground Tank/s? NO
Remove manway and piping containment/equipment sump/s? YES Remove fill port and spill bucket/s? YES
Remove outside fuel piping - approximately 50 feet - supply and return piping inside a secondary containment plastic pipe. Each line is approx 50-feet Will remove above ground portion of vent line, as requested.
If yes coverage requirements:
Soil Excavation to Remove or Expose Piping? YES
Remove tank/s? YES
Site Specific challenges: AST will be installed in same location after current UST is removed. Piping will be underground from the AST to outside the EG room
Remove fuel lines? YES
GENERAL REQUIREMENTS/LOGISTICS
If yes are they utilizing a local firm? The contractor will contact the State "One Call" utility locator. Also, the contractor will utilize a third party utility locator to conduct GPR and EMI.
Temporary Facilities Required? NO
Surveying & Utility locating required? Yes. GPR and EMI will be conducted prior to construction activities taking place. This will be initiated by the removal/install contractor.
If yes Amount:
SITE WORK
Bond Required by local municipality? NO Specific Insurance required? NO
0 LF
0.12 CY to be removed
68.5" X 2' X 4"
0 CY 2.5 CY
0 CF 1 CYConcrete Support Slab Removal? YES
Soil Excavation to Remove or Expose tank? YES
Latitude Longitude
Remove manway lid/s? YES
Remove Daytanks? NO 0 EA
CIVIL DEMOLITION
AST UST 1-UST 1-AST
SITE SURVEY CHECKLIST Location Identifier Facility Identifier
Address City
State
Date Facility POC
Alan Laird Daytime Phone: 610-264-2220 Type of FST Number of Tanks to be removed Number of tanks to be installed
PA
7/29/2014
ABE
ATCT
Allentown
40.658466 -75.441668
ELECTRICAL DEMOLITION Baseline Quantity Actual Quantity
Install New Permanent Daytank System? NO
Install New Permanent fuel supply/overfill piping from MT to DT? YES
Install Power Conductors? NO 60 LF 0
Install service platform? YES Basic Mechanical
20 LF 75 LF
0 EA 0
Install daytank control panel/s? NO
Install Fuel Tank Monitor/s? YES
0 EA 0
1 1
Tank Repair
Tank Replacement Gallons: 250 250
1 EA 0
26 LF
20 LF
(Total for 1 supply and 1 return hose)
Install Temporary fuel supply system? YES
AST Gallons: 1,000-gallon
Install New Permanent fuel supply/Return piping from DT to EG? YES
0 EA 0
Install Temporary fuel supply Piping? YES
Install New Permanent secondary containment piping from MT to DT? YES 20 LF 66 LF
35 LF 0
0 EA 0
0 EA 0
Baseline Quantity Actual Quantity
Baseline Quantity Actual Quantity
0 LF
0.12 CY to be installed
(to replace removed concrete)
0 EA 0
74 LF
112 LF
(Total for 1 supply and 1 return hose)
8 LF 0
10 TONS 12 TONS
Self-compacting gravel to be used to fill UST excavation. Additional stone to be installed to get AST location level with grade - Approx 2 TONS (added to total above).
Top Soil Installation? NO Gravel Installation? YES
0 LF 0
0 CY
2.5 CY for AST pad
0.5 CY for Stairs/Platform pad
0 EA
MECHANICAL INSTALLATION Baseline Quantity Actual Quantity
0 LF 0
Concrete Support Slab installation? YES
Site Specific Mechanical Installation:
Install manway and piping containment sump/s? NO
Install pump/s? NO
5Bollard Installation? YES Site Specific Civil Installation:
Concrete Trenching Installation? YES Select backfill installation? YES
Paint Bollards? YES
20 LF 20 LF
Install piping Labels? YES Install valve tags? NO
0 EA
Install New Permanent vent piping? NO Install New Permanent Daytank vent piping? YES 0 LF 16 LF
New fuel hoses to be installed from MT to inside EG Room wall at secondary containment termination boot.
Install New fuel cooler? NO
Install Control/Comm wiring? NO
Install actuated fuel oil control valve/s? NO Install conduit/s? YES
Install fuel control panel/s? NO
Install fill port and spill bucket/s? NO Install manway lid/s? NO
Replace supply and return fuel piping inside EG room. Return fuel piping will be sized larger than the diameter of the supply piping.
Paint piping? YES
The overfill alarm will require the installation of a separate electrical circuit breaker inside the electrical panel box.
Site Specific Electrical Installation:
Install a new Veeder-Root TLS 300C monitoring system. Monitor install location will be in current monitoring system location. Vent louver conduit will need to be rerouted to enable Veeder Root installation.
ERMS Connection/s to be Coordinated by FAA. POC for Coordination:
1 EA
No
00 EA
ELECTRICAL INSTALLATION
Install motor starter/s? NO
Install New Permanent Tank? YES Gallons: GPM Rating: 0
Sheet1
File details come from the government source that posted it. Updated .