AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A003 04/25/2018 N/A See Block 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
DTFH7017B00023
9B. DATED (SEE ITEM 11)
04/02/2018
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
N/A
D OTHER (Specify type of modification and authority) N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
ID PFH 21(7), Warren Wagon Road
See Page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A003, dated 04/25/2018 Solicitation No. DTFH7017B00023
REVISIONS ARE AS FOLLOWS:
BID SCHEDULE
Page A-14. Revises, Fixed Unit Price for Item 63509-100 TEMPORARY TRAFFIC
CONTROL, FLAGGER.
Page A-21. Revises, Fixed Unit Price for Item 63509-100 TEMPORARY TRAFFIC
Page A-28. Revises, Fixed Unit Price for Item 63509-100 TEMPORARY TRAFFIC
CONTROL, FLAGGER.
Page A-35. Revises, Fixed Unit Price for Item 63509-100 TEMPORARY TRAFFIC
CONTRACT CLAUSES
ENCLOSURES
Pages:
A-7 through A-35
Notice to Bidders: Please submit revised pages A-7 through A-35 with your bid.
A-7
Bid Schedule
Project: ID PFH 21(7) Warren Wagon Road
Bidders please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit bid price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the Amount Bid for the item will be based on the Unit Bid Price.
When a “LPSM” (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total the amounts bid for all pay items and insert the total bid amount.
BRAND NAME OR EQUAL NOTIFICATION
If providing other than the listed brand name products, complete the following (See FAR Provision 52.211-6, Brand Name or Equal):
A. For Item 65101-1000, Draped Rockfall Protection, Wire Mesh (anchored) in Schedules A, B C, and D, in lieu of the brand name Geobrugg Tecco® G65 wire mesh specified in Subsection 710.12 High-Tensile Strength Steel Wire Mesh, our firm offers:
Brand: __________________________________________
Manufacturer’s Name: _____________________________
B. For Item 65101-1000, Draped Rockfall Protection, Wire Mesh (anchored) in Schedules A, B C, and D, in lieu of the brand name Geobrugg Tecco® system spike plate specified in Subsection 717.01(g) Diamond-shaped spike plates, our firm offers:
Brand: __________________________________________
Manufacturer’s Name: _____________________________
Revised by Amendment A003
A-7a
C. For Section 563 - PAINTING in Schedules A, B C, and D, in lieu of the brand name Natina® galvanized metal colorant specified in Subsection 725.19 Weathering Agent, our firm offers:
Brand: __________________________________________
Manufacturer’s Name: _____________________________
Include with your bid all documents needed by the Government to determine if the proposed product meets the requirements listed in the appropriate Section. The determination as to the equality of the product offered is the responsibility of the Government and will be based on the information furnished by the bidder as well as other information reasonably available to the contracting office. If proposed “equal” is determined by the government to be “not equal”, bid will be considered nonresponsive.
A-8
B I D S C H E D U L E Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
15101-0000
Line A0020 ALL LPSM $
15201-0000
Line A0040 ALL LPSM $
15301-0000
Line A0060 ALL LPSM $
15401-0000
Line A0080 ALL LPSM $
15501-0000
Line A0100 ALL LPSM $
15704-1000
Line A0120 1,000 SQYD $ $
15705-0100
Line A0140 3,200 LNFT $ $
15705-0500
Line A0160 300 LNFT $ $
15705-0800
Line A0180 130 LNFT $ $
15705-1300
Line A0200 425 LNFT $ $
15705-1400
Line A0220 29,250 LNFT $ $
15705-1800
Line A0240 200 LNFT $ $
15706-0300
Line A0260 300 EACH $ $
15801-0000
Line A0280 10,000 MGAL $ $
20101-0000
Line A0300 15.5 ACRE (CQ) $ $
20301-0700
Line A0320 85 EACH $ $
20301-1200
Line A0340 11 EACH $ $
Schedule Total: ________________________
Submitted by: _________________________
REMOVAL OF DELINEATOR
REMOVAL OF HEADWALL
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR QUALITY CONTROL
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, PLASTIC LINING
SOIL EROSION CONTROL, SANDBAG
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, TEMPORARY CULVERT PIPE (18-inch)
SOIL EROSION CONTROL, TEMPORARY 36-INCH CULVERT PIPE
SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM
Revised by Amendment A003 david.l.mariman Rectangle
A-9
Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
20301-1400
Line A0360 1 EACH $ $
20301-1700
Line A0380 2 EACH $ $
20301-1900
Line A0400 7 EACH $ $
20301-2300
Line A0420 35 EACH $ $
20301-3700
Line A0440 2 EACH $ $
20303-3000
Line A0460 200 SQYD $ $
20401-0000
Line A0480 25,820 CUYD $ $
20402-0000
Line A0500 4,780 CUYD $ $
20411-0000
Line A0520 9,450 TON $ $
20465-0000
Line A0540 50 EACH $ $
20701-0300
Line A0560 125,960 SQYD $ $
20720-0300
Line A0580 23,870 SQYD $ $
25101-0200
Line A0600 180 CUYD $ $
25101-2000
Line A0620 85 CUYD $ $
25101-2200
Line A0640 70 CUYD $ $
25120-2000
Line A0660 90 LNFT $ $
30101-2000
Line A0680 43,320 TON $ $
AGGREGATE BASE GRADING D
SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C
REINFORCEMENT GEOSYNTHETIC, TYPE 3 (biaxial)
PLACED RIPRAP, METHOD A, CLASS 2
REMOVAL OF TERMINAL SECTION
REMOVAL OF SIDEWALK, ASPHALT
ROADWAY EXCAVATION
REMOVAL OF INLET (salvage for reset)
PLACED RIPRAP, METHOD B (headwall)
PLACED RIPRAP, METHOD B, CLASS 2
RIPRAP DITCH, METHOD B (Class 1 or 2)
REMOVAL OF MANHOLE (monitoring well)
REMOVAL OF PIPE CULVERT
REMOVAL OF SIGN/MARKER
SUBEXCAVATION
SELECT BORROW
CONSERVE AND PLACE BOULDER
Revised by Amendment A003
A-10
Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
30302-1000
Line A0700 125 LNFT $ $
30801-0000
Line A0720 77,500 SQYD (CQ) $ $
40101-5600
Line A0740 11,650 TON $ $
40105-3000
Line A0760 120 TON $ $
40601-0000
Line A0780 38 TON $ $
40605-0000
Line A0800 506 TON $ $
40801-0000
Line A0820 17,000 TON $ $
41201-0000
Line A0840 47 TON $ $
60103-0000
Line A0860 2 EACH $ $
60103-0440
Line A0880 2 EACH $ $
60201-0200
Line A0900 70 LNFT $ $
60201-0400
Line A0920 80 LNFT $ $
60201-0500
Line A0940 55 LNFT $ $
60201-0600
Line A0960 750 LNFT $ $
60201-0800
Line A0980 400 LNFT $ $
60201-2400
Line A1000 78 LNFT $ $
60201-2500
Line A1020 68 LNFT $ $
24-INCH PIPE CULVERT
132-INCH PIPE CULVERT
144-INCH PIPE CULVERT
CONCRETE, HEADWALL (132-inch pipe culvert)
CONCRETE, HEADWALL FOR 144-INCH PIPE CULVERT
6-INCH PIPE CULVERT
12-INCH PIPE CULVERT
15-INCH PIPE CULVERT
18-INCH PIPE CULVERT
ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
ANTISTRIP ADDITIVE, TYPE 3
FOG SEAL (CSS-1 or CSS-1h)
BLOTTER
COLD RECYCLED ASPHALT BASE COURSE
TACK COAT (grade CSS-1)
DITCH RECONDITIONING
RECYCLED AGGREGATE BASE (pavement)
Revised by Amendment A003
A-11
Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
60202-0800
Line A1040 50 LNFT $ $
60401-0000
Line A1060 2 EACH $ $
60403-0000
Line A1080 1 EACH $ $
60501-0000
Line A1100 170 LNFT $ $
60510-0700
Line A1120 1,220 LNFT $ $
60510-0800
Line A1140 170 LNFT $ $
60704-0000
Line A1160 23 EACH $ $
61203-0000
Line A1180 6 EACH $ $
61203-0000
Line A1200 1 EACH $ $
61501-1100
Line A1220 235 SQYD $ $
61701-2300
Line A1240 25 LNFT $ $
61702-0800
Line A1260 3 EACH $ $
61702-1200
Line A1280 1 EACH $ $
61708-1000
Line A1300 88 LNFT $ $
62201-0250
Line A1320 200 HOUR $ $
62201-0900
Line A1340 100 HOUR $ $
62201-1400
Line A1360 100 HOUR $ $
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
BULLDOZER, 250HP MINIMUM FLYWHEEL POWER
SIDEWALK, ASPHALT
GUARDRAIL SYSTEM G9, TYPE 2, CLASS B WOOD POSTS
TERMINAL SECTION TYPE TANGENT
TERMINAL SECTION, TYPE LST
REMOVE AND RESET, GUARDRAIL
DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
STANDARD UNDERDRAIN SYSTEM
6-INCH COLLECTOR PIPE
6-INCH OUTLET PIPE
CLEANING CULVERT IN PLACE
MANHOLE, SANITARY SEWER (adjustment)
MANHOLE, SANITARY SEWER (air valve adjustment)
48-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
MANHOLE (monitoring well manhole reset)
INLET (reset)
Revised by Amendment A003
A-12
Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
62201-2850
Line A1380 100 HOUR $ $
62201-3000
Line A1400 50 HOUR $ $
62201-3000
Line A1420 50 HOUR $ $
62201-3400
Line A1440 100 HOUR $ $
62201-3750
Line A1460 80 HOUR $ $
62301-0000
Line A1480 200 HOUR $ $
62302-0100
Line A1500 1,550 HOUR $ $
62403-0000
Line A1520 3,100 CUYD $ $
62406-0100
Line A1540 11.5 ACRE (CQ) $ $
62501-0000
Line A1560 11.5 ACRE (CQ) $ $
62901-1400
Line A1580 375 SQYD $ $
63302-0000
Line A1600 345 SQFT $ $
63308-3000
Line A1620 2 EACH $ $
63309-0000
Line A1640 520 EACH $ $
63310-0000
Line A1660 6 EACH $ $
63316-1000
Line A1680 35 EACH $ $
63316-2000
Line A1700 4 EACH $ $
REMOVE AND RESET DELINEATOR (bollard type)
ROLLED EROSION CONTROL PRODUCT, TYPE 5.C
SIGN SYSTEM
OBJECT MARKER, TYPE 3
DELINEATOR (Idaho Type 4F-B)
CHANNELIZING DEVICE
REMOVE AND RESET SIGN
CHAIN SAW
GENERAL LABOR
SPECIAL LABOR, SLOPE SCALING
FURNISHING AND PLACING TOPSOIL
PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
TURF ESTABLISHMENT
MOTOR GRADER, 12 FOOT MINIMUM BLADE
HYDRAULIC EXCAVATOR (140HP minimum with 50 foot minimum reach)
HYDRAULIC EXCAVATOR (mini, 23.1HP to 40.2HP, with 5 foot minimum dozer blade)
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT
Revised by Amendment A003
A-13
Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63401-0300
Line A1720 84,450 LNFT (CQ) $ $
63401-0300
Line A1740 224,040 LNFT (CQ) $ $
63401-0400
Line A1760 21,530 LNFT (CQ) $ $
63401-0450
Line A1780 3,950 LNFT $ $
63405-0050
Line A1800 24 EACH $ $
63502-0400
Line A1820 50 EACH $ $
63502-0600
Line A1840 20 EACH $ $
63502-1250
Line A1860 760 EACH $ $
63502-1300
Line A1880 510 EACH $ $
63502-1500
Line A1900 65 EACH $ $
63502-1600
Line A1920 95 EACH $ $
63502-1700
Line A1940 230 EACH $ $
63502-3700
Line A1960 50 EACH $ $
63503-0700
Line A1980 29,000 LNFT $ $
63503-1000
Line A2000 2,315 LNFT $ $
63504-1000
Line A2020 1,219 SQFT $ $
63506-0600
Line A2040 225 HOUR $ $
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
TEMPORARY TRAFFIC CONTROL, SNOW POLE
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 1
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
PAVEMENT MARKINGS, TYPE B, SOLID (yellow)
PAVEMENT MARKINGS, TYPE B, SOLID (white)
PAVEMENT MARKINGS, TYPE B, BROKEN (yellow)
PAVEMENT MARKINGS, TYPE B, DOTTED (white)
PAVEMENT MARKINGS, SYMBOLS (type B yield triangle)
Revised by Amendment A003
A-14
Schedule A Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63507-0700
Line A2060 315 DAY $ $
63509-1000
Line A2080 7,200 FXHR $ 360,000.00 50.00 $
64702-1000
Line A2100 900 LNFT $ $
64703-6000
Line A2120 120 EACH $ $
64704-1000
Line A2140 740 CUYD $ $
65101-1000
Line A2160 375 SQYD $ $
TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
TEMPORARY TRAFFIC CONTROL, FLAGGER
MITIGATION, LANDSCAPING LOG
MITIGATION, FISH PASSAGE BOULDER
MITIGATION, STREAMBED MATERIAL
DRAPED ROCKFALL PROTECTION, WIRE MESH (anchored)
A003
A-15
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
15101-0000
Line B0020 ALL LPSM $
15201-0000
Line B0040 ALL LPSM $
15301-0000
Line B0060 ALL LPSM $
15401-0000
Line B0080 ALL LPSM $
15501-0000
Line B0100 ALL LPSM $
15704-1000
Line B0120 1,000 SQYD $ $
15705-0100
Line B0140 3,200 LNFT $ $
15705-0500
Line B0160 300 LNFT $ $
15705-0800
Line B0180 130 LNFT $ $
15705-1300
Line B0200 425 LNFT $ $
15705-1400
Line B0220 29,250 LNFT $ $
15705-1800
Line B0240 200 LNFT $ $
15706-0300
Line B0260 300 EACH $ $
15801-0000
Line B0280 10,000 MGAL $ $
20101-0000
Line B0300 15.5 ACRE (CQ) $ $
20301-0700
Line B0320 85 EACH $ $
20301-1200
Line B0340 11 EACH $ $
Schedule Total: ________________________
Submitted by: _________________________
REMOVAL OF DELINEATOR
REMOVAL OF HEADWALL
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR QUALITY CONTROL
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, PLASTIC LINING
SOIL EROSION CONTROL, SANDBAG
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, TEMPORARY CULVERT PIPE (18-inch)
SOIL EROSION CONTROL, TEMPORARY 36-INCH CULVERT PIPE
SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM
Revised by Amendment A003
A-16
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
20301-1400
Line B0360 1 EACH $ $
20301-1700
Line B0380 2 EACH $ $
20301-1900
Line B0400 7 EACH $ $
20301-2300
Line B0420 35 EACH $ $
20301-3700
Line B0440 2 EACH $ $
20303-3000
Line B0460 200 SQYD $ $
20401-0000
Line B0480 25,820 CUYD $ $
20402-0000
Line B0500 4,780 CUYD $ $
20411-0000
Line B0520 9,450 TON $ $
20465-0000
Line B0540 50 EACH $ $
20701-0300
Line B0560 125,960 SQYD $ $
20720-0300
Line B0580 23,870 SQYD $ $
25101-0200
Line B0600 180 CUYD $ $
25101-2000
Line B0620 85 CUYD $ $
25101-2200
Line B0640 70 CUYD $ $
25120-2000
Line B0660 90 LNFT $ $
26001-0000
Line B0680 530 LNFT $ $
ROCK BOLT (25 kip)
SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C
REINFORCEMENT GEOSYNTHETIC, TYPE 3 (biaxial)
PLACED RIPRAP, METHOD A, CLASS 2
REMOVAL OF TERMINAL SECTION
REMOVAL OF SIDEWALK, ASPHALT
ROADWAY EXCAVATION
REMOVAL OF INLET (salvage for reset)
PLACED RIPRAP, METHOD B (headwall)
PLACED RIPRAP, METHOD B, CLASS 2
RIPRAP DITCH, METHOD B (Class 1 or 2)
REMOVAL OF MANHOLE (monitoring well)
REMOVAL OF PIPE CULVERT
REMOVAL OF SIGN/MARKER
SUBEXCAVATION
SELECT BORROW
CONSERVE AND PLACE BOULDER
Revised by Amendment A003
A-17
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
26001-0000
Line B0700 1,090 LNFT $ $
26002-0000
Line B0720 100 LNFT $ $
30101-2000
Line B0740 43,320 TON $ $
30302-1000
Line B0760 125 LNFT $ $
30801-0000
Line B0780 77,500 SQYD (CQ) $ $
40101-5600
Line B0800 11,650 TON $ $
40105-3000
Line B0820 120 TON $ $
40601-0000
Line B0840 38 TON $ $
40605-0000
Line B0860 506 TON $ $
40801-0000
Line B0880 17,000 TON $ $
41201-0000
Line B0900 47 TON $ $
60103-0000
Line B0920 2 EACH $ $
60103-0440
Line B0940 2 EACH $ $
60201-0200
Line B0960 70 LNFT $ $
60201-0400
Line B0980 80 LNFT $ $
60201-0500
Line B1000 55 LNFT $ $
60201-0600
Line B1020 750 LNFT $ $
12-INCH PIPE CULVERT
15-INCH PIPE CULVERT
18-INCH PIPE CULVERT
BLOTTER
COLD RECYCLED ASPHALT BASE COURSE
TACK COAT (grade CSS-1)
CONCRETE, HEADWALL (132-inch pipe culvert)
CONCRETE, HEADWALL FOR 144-INCH PIPE CULVERT
6-INCH PIPE CULVERT
AGGREGATE BASE GRADING D
DITCH RECONDITIONING
RECYCLED AGGREGATE BASE (pavement)
ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
ANTISTRIP ADDITIVE, TYPE 3
FOG SEAL (CSS-1 or CSS-1h)
ROCK BOLT (50 kip)
ROCK DOWEL
Revised by Amendment A003
A-18
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
60201-0800
Line B1040 400 LNFT $ $
60201-2400
Line B1060 78 LNFT $ $
60201-2500
Line B1080 68 LNFT $ $
60202-0800
Line B1100 50 LNFT $ $
60401-0000
Line B1120 2 EACH $ $
60403-0000
Line B1140 1 EACH $ $
60501-0000
Line B1160 170 LNFT $ $
60510-0700
Line B1180 1,220 LNFT $ $
60510-0800
Line B1200 170 LNFT $ $
60704-0000
Line B1220 23 EACH $ $
61203-0000
Line B1240 6 EACH $ $
61203-0000
Line B1260 1 EACH $ $
61501-1100
Line B1280 235 SQYD $ $
61701-2300
Line B1300 25 LNFT $ $
61702-0800
Line B1320 3 EACH $ $
61702-1200
Line B1340 1 EACH $ $
61708-1000
Line B1360 88 LNFT $ $
TERMINAL SECTION, TYPE LST
REMOVE AND RESET, GUARDRAIL
CLEANING CULVERT IN PLACE
MANHOLE, SANITARY SEWER (adjustment)
MANHOLE, SANITARY SEWER (air valve adjustment)
SIDEWALK, ASPHALT
GUARDRAIL SYSTEM G9, TYPE 2, CLASS B WOOD POSTS
TERMINAL SECTION TYPE TANGENT
48-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
MANHOLE (monitoring well manhole reset)
INLET (reset)
STANDARD UNDERDRAIN SYSTEM
6-INCH COLLECTOR PIPE
6-INCH OUTLET PIPE
24-INCH PIPE CULVERT
132-INCH PIPE CULVERT
144-INCH PIPE CULVERT
Revised by Amendment A003
A-19
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
62201-0250
Line B1380 200 HOUR $ $
62201-0900
Line B1400 100 HOUR $ $
62201-1400
Line B1420 100 HOUR $ $
62201-2850
Line B1440 100 HOUR $ $
62201-3000
Line B1460 50 HOUR $ $
62201-3000
Line B1480 50 HOUR $ $
62201-3400
Line B1500 100 HOUR $ $
62201-3750
Line B1520 80 HOUR $ $
62301-0000
Line B1540 200 HOUR $ $
62302-0100
Line B1560 1,550 HOUR $ $
62403-0000
Line B1580 3,100 CUYD $ $
62406-0100
Line B1600 11.5 ACRE (CQ) $ $
62501-0000
Line B1620 11.5 ACRE (CQ) $ $
62901-1400
Line B1640 375 SQYD $ $
63302-0000
Line B1660 345 SQFT $ $
63308-3000
Line B1680 2 EACH $ $
63309-0000
Line B1700 520 EACH $ $
DELINEATOR (Idaho Type 4F-B)
FURNISHING AND PLACING TOPSOIL
PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
TURF ESTABLISHMENT
ROLLED EROSION CONTROL PRODUCT, TYPE 5.C
SIGN SYSTEM
OBJECT MARKER, TYPE 3
HYDRAULIC EXCAVATOR (140HP minimum with 50 foot minimum reach)
HYDRAULIC EXCAVATOR (mini, 23.1HP to 40.2HP, with 5 foot minimum dozer blade)
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT
CHAIN SAW
GENERAL LABOR
SPECIAL LABOR, SLOPE SCALING
DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
BULLDOZER, 250HP MINIMUM FLYWHEEL POWER
MOTOR GRADER, 12 FOOT MINIMUM BLADE
Revised by Amendment A003
A-20
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63310-0000
Line B1720 6 EACH $ $
63316-1000
Line B1740 35 EACH $ $
63316-2000
Line B1760 4 EACH $ $
63401-0300
Line B1780 84,450 LNFT (CQ) $ $
63401-0300
Line B1800 224,040 LNFT (CQ) $ $
63401-0400
Line B1820 21,530 LNFT (CQ) $ $
63401-0450
Line B1840 3,950 LNFT $ $
63405-0050
Line B1860 24 EACH $ $
63502-0400
Line B1880 50 EACH $ $
63502-0600
Line B1900 20 EACH $ $
63502-1250
Line B1920 760 EACH $ $
63502-1300
Line B1940 510 EACH $ $
63502-1500
Line B1960 65 EACH $ $
63502-1600
Line B1980 95 EACH $ $
63502-1700
Line B2000 230 EACH $ $
63502-3700
Line B2020 50 EACH $ $
63503-0700
Line B2040 29,000 LNFT $ $
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
TEMPORARY TRAFFIC CONTROL, SNOW POLE
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
PAVEMENT MARKINGS, TYPE B, BROKEN (yellow)
PAVEMENT MARKINGS, TYPE B, DOTTED (white)
PAVEMENT MARKINGS, SYMBOLS (type B yield triangle)
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 1
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
CHANNELIZING DEVICE
REMOVE AND RESET SIGN
REMOVE AND RESET DELINEATOR (bollard type)
PAVEMENT MARKINGS, TYPE B, SOLID (yellow)
PAVEMENT MARKINGS, TYPE B, SOLID (white)
Revised by Amendment A003
A-21
Schedule B Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63503-1000
Line B2060 2,315 LNFT $ $
63504-1000
Line B2080 1,219 SQFT $ $
63506-0600
Line B2100 225 HOUR $ $
63507-0700
Line B2120 315 DAY $ $
63509-1000
Line B2140 7,200 FXHR $ 360,000.00 50.00 $
64702-1000
Line B2160 900 LNFT $ $
64703-6000
Line B2180 120 EACH $ $
64704-1000
Line B2200 740 CUYD $ $
65101-1000
Line B2220 375 SQYD $ $
MITIGATION, FISH PASSAGE BOULDER
MITIGATION, STREAMBED MATERIAL
DRAPED ROCKFALL PROTECTION, WIRE MESH (anchored)
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
TEMPORARY TRAFFIC CONTROL, FLAGGER
MITIGATION, LANDSCAPING LOG
A-22
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
15101-0000
Line C0020 ALL LPSM $
15201-0000
Line C0040 ALL LPSM $
15301-0000
Line C0060 ALL LPSM $
15401-0000
Line C0080 ALL LPSM $
15501-0000
Line C0100 ALL LPSM $
15704-1000
Line C0120 1,000 SQYD $ $
15705-0100
Line C0140 3,200 LNFT $ $
15705-0500
Line C0160 300 LNFT $ $
15705-0800
Line C0180 130 LNFT $ $
15705-1300
Line C0200 425 LNFT $ $
15705-1400
Line C0220 29,250 LNFT $ $
15705-1800
Line C0240 200 LNFT $ $
15706-0300
Line C0260 300 EACH $ $
15801-0000
Line C0280 10,000 MGAL $ $
20101-0000
Line C0300 15.5 ACRE (CQ) $ $
20301-0700
Line C0320 85 EACH $ $
20301-1200
Line C0340 11 EACH $ $
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR QUALITY CONTROL
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, PLASTIC LINING
SOIL EROSION CONTROL, SANDBAG
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, TEMPORARY CULVERT PIPE (18-inch)
SOIL EROSION CONTROL, TEMPORARY 36-INCH CULVERT PIPE
SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM
REMOVAL OF DELINEATOR
REMOVAL OF HEADWALL
Schedule Total: ________________________
Submitted by: _________________________
Revised by Amendment A003
A-23
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
20301-1400
Line C0360 1 EACH $ $
20301-1700
Line C0380 2 EACH $ $
20301-1900
Line C0400 7 EACH $ $
20301-2300
Line C0420 35 EACH $ $
20301-3700
Line C0440 2 EACH $ $
20303-3000
Line C0460 200 SQYD $ $
20401-0000
Line C0480 25,820 CUYD $ $
20402-0000
Line C0500 4,780 CUYD $ $
20411-0000
Line C0520 9,450 TON $ $
20465-0000
Line C0540 50 EACH $ $
20701-0300
Line C0560 125,960 SQYD $ $
20720-0300
Line C0580 23,870 SQYD $ $
25101-0200
Line C0600 180 CUYD $ $
25101-2000
Line C0620 85 CUYD $ $
25101-2200
Line C0640 70 CUYD $ $
25120-2000
Line C0660 90 LNFT $ $
26001-0000
Line C0680 1,195 LNFT $ $
PLACED RIPRAP, METHOD B (headwall)
PLACED RIPRAP, METHOD B, CLASS 2
RIPRAP DITCH, METHOD B (Class 1 or 2)
REMOVAL OF MANHOLE (monitoring well)
REMOVAL OF PIPE CULVERT
REMOVAL OF SIGN/MARKER
SUBEXCAVATION
SELECT BORROW
CONSERVE AND PLACE BOULDER
SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C
REINFORCEMENT GEOSYNTHETIC, TYPE 3 (biaxial)
PLACED RIPRAP, METHOD A, CLASS 2
REMOVAL OF TERMINAL SECTION
REMOVAL OF SIDEWALK, ASPHALT
ROADWAY EXCAVATION
REMOVAL OF INLET (salvage for reset)
ROCK BOLT (25 kip)
Revised by Amendment A003
A-24
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
26001-0000
Line C0700 1,090 LNFT $ $
26002-0000
Line C0720 220 LNFT $ $
30101-2000
Line C0740 43,320 TON $ $
30302-1000
Line C0760 125 LNFT $ $
30801-0000
Line C0780 77,500 SQYD (CQ) $ $
40101-5600
Line C0800 11,650 TON $ $
40105-3000
Line C0820 120 TON $ $
40601-0000
Line C0840 38 TON $ $
40605-0000
Line C0860 506 TON $ $
40801-0000
Line C0880 17,000 TON $ $
41201-0000
Line C0900 47 TON $ $
60103-0000
Line C0920 2 EACH $ $
60103-0440
Line C0940 2 EACH $ $
60201-0200
Line C0960 70 LNFT $ $
60201-0400
Line C0980 80 LNFT $ $
60201-0500
Line C1000 55 LNFT $ $
60201-0600
Line C1020 750 LNFT $ $
AGGREGATE BASE GRADING D
DITCH RECONDITIONING
RECYCLED AGGREGATE BASE (pavement)
ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
ANTISTRIP ADDITIVE, TYPE 3
FOG SEAL (CSS-1 or CSS-1h)
ROCK BOLT (50 kip)
ROCK DOWEL
12-INCH PIPE CULVERT
15-INCH PIPE CULVERT
18-INCH PIPE CULVERT
BLOTTER
COLD RECYCLED ASPHALT BASE COURSE
TACK COAT (grade CSS-1)
CONCRETE, HEADWALL (132-inch pipe culvert)
CONCRETE, HEADWALL FOR 144-INCH PIPE CULVERT
6-INCH PIPE CULVERT
Revised by Amendment A003
A-25
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
60201-0800
Line C1040 400 LNFT $ $
60201-2400
Line C1060 78 LNFT $ $
60201-2500
Line C1080 68 LNFT $ $
60202-0800
Line C1100 50 LNFT $ $
60401-0000
Line C1120 2 EACH $ $
60403-0000
Line C1140 1 EACH $ $
60501-0000
Line C1160 170 LNFT $ $
60510-0700
Line C1180 1,220 LNFT $ $
60510-0800
Line C1200 170 LNFT $ $
60704-0000
Line C1220 23 EACH $ $
61203-0000
Line C1240 6 EACH $ $
61203-0000
Line C1260 1 EACH $ $
61501-1100
Line C1280 235 SQYD $ $
61701-2300
Line C1300 25 LNFT $ $
61702-0800
Line C1320 3 EACH $ $
61702-1200
Line C1340 1 EACH $ $
61708-1000
Line C1360 88 LNFT $ $
24-INCH PIPE CULVERT
132-INCH PIPE CULVERT
144-INCH PIPE CULVERT
CLEANING CULVERT IN PLACE
MANHOLE, SANITARY SEWER (adjustment)
MANHOLE, SANITARY SEWER (air valve adjustment)
SIDEWALK, ASPHALT
GUARDRAIL SYSTEM G9, TYPE 2, CLASS B WOOD POSTS
TERMINAL SECTION TYPE TANGENT
48-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
MANHOLE (monitoring well manhole reset)
INLET (reset)
STANDARD UNDERDRAIN SYSTEM
6-INCH COLLECTOR PIPE
6-INCH OUTLET PIPE
TERMINAL SECTION, TYPE LST
REMOVE AND RESET, GUARDRAIL
Revised by Amendment A003
A-26
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
62201-0250
Line C1380 200 HOUR $ $
62201-0900
Line C1400 100 HOUR $ $
62201-1400
Line C1420 100 HOUR $ $
62201-2850
Line C1440 100 HOUR $ $
62201-3000
Line C1460 50 HOUR $ $
62201-3000
Line C1480 50 HOUR $ $
62201-3400
Line C1500 100 HOUR $ $
62201-3750
Line C1520 80 HOUR $ $
62301-0000
Line C1540 200 HOUR $ $
62302-0100
Line C1560 1,550 HOUR $ $
62403-0000
Line C1580 3,100 CUYD $ $
62406-0100
Line C1600 11.5 ACRE (CQ) $ $
62501-0000
Line C1620 11.5 ACRE (CQ) $ $
62901-1400
Line C1640 375 SQYD $ $
63302-0000
Line C1660 345 SQFT $ $
63308-3000
Line C1680 2 EACH $ $
63309-0000
Line C1700 520 EACH $ $
HYDRAULIC EXCAVATOR (140HP minimum with 50 foot minimum reach)
HYDRAULIC EXCAVATOR (mini, 23.1HP to 40.2HP, with 5 foot minimum dozer blade)
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT
CHAIN SAW
GENERAL LABOR
SPECIAL LABOR, SLOPE SCALING
DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
BULLDOZER, 250HP MINIMUM FLYWHEEL POWER
MOTOR GRADER, 12 FOOT MINIMUM BLADE
DELINEATOR (Idaho Type 4F-B)
FURNISHING AND PLACING TOPSOIL
PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
TURF ESTABLISHMENT
ROLLED EROSION CONTROL PRODUCT, TYPE 5.C
SIGN SYSTEM
OBJECT MARKER, TYPE 3
Revised by Amendment A003
A-27
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63310-0000
Line C1720 6 EACH $ $
63316-1000
Line C1740 35 EACH $ $
63316-2000
Line C1760 4 EACH $ $
63401-0300
Line C1780 84,450 LNFT (CQ) $ $
63401-0300
Line C1800 224,040 LNFT (CQ) $ $
63401-0400
Line C1820 21,530 LNFT (CQ) $ $
63401-0450
Line C1840 3,950 LNFT $ $
63405-0050
Line C1860 24 EACH $ $
63502-0400
Line C1880 50 EACH $ $
63502-0600
Line C1900 20 EACH $ $
63502-1250
Line C1920 760 EACH $ $
63502-1300
Line C1940 510 EACH $ $
63502-1500
Line C1960 65 EACH $ $
63502-1600
Line C1980 95 EACH $ $
63502-1700
Line C2000 230 EACH $ $
63502-3700
Line C2020 50 EACH $ $
63503-0700
Line C2040 29,000 LNFT $ $
CHANNELIZING DEVICE
REMOVE AND RESET SIGN
REMOVE AND RESET DELINEATOR (bollard type)
PAVEMENT MARKINGS, TYPE B, SOLID (yellow)
PAVEMENT MARKINGS, TYPE B, SOLID (white)
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
TEMPORARY TRAFFIC CONTROL, SNOW POLE
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
PAVEMENT MARKINGS, TYPE B, BROKEN (yellow)
PAVEMENT MARKINGS, TYPE B, DOTTED (white)
PAVEMENT MARKINGS, SYMBOLS (type B yield triangle)
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 1
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
Revised by Amendment A003
A-28
Schedule C Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63503-1000
Line C2060 2,315 LNFT $ $
63504-1000
Line C2080 1,219 SQFT $ $
63506-0600
Line C2100 225 HOUR $ $
63507-0700
Line C2120 315 DAY $ $
63509-1000
Line C2140 7,200 FXHR $ 360,000.00 50.00 $
64702-1000
Line C2160 900 LNFT $ $
64703-6000
Line C2180 120 EACH $ $
64704-1000
Line C2200 740 CUYD $ $
65101-1000
Line C2220 375 SQYD $ $
MITIGATION, FISH PASSAGE BOULDER
MITIGATION, STREAMBED MATERIAL
DRAPED ROCKFALL PROTECTION, WIRE MESH (anchored)
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
TEMPORARY TRAFFIC CONTROL, FLAGGER
MITIGATION, LANDSCAPING LOG
A-29
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
15101-0000
Line D0020 ALL LPSM $
15201-0000
Line D0040 ALL LPSM $
15301-0000
Line D0060 ALL LPSM $
15401-0000
Line D0080 ALL LPSM $
15501-0000
Line D0100 ALL LPSM $
15704-1000
Line D0120 1,000 SQYD $ $
15705-0100
Line D0140 3,200 LNFT $ $
15705-0500
Line D0160 300 LNFT $ $
15705-0800
Line D0180 130 LNFT $ $
15705-1300
Line D0200 425 LNFT $ $
15705-1400
Line D0220 29,250 LNFT $ $
15705-1800
Line D0240 200 LNFT $ $
15706-0300
Line D0260 300 EACH $ $
15801-0000
Line D0280 10,000 MGAL $ $
20101-0000
Line D0300 15.5 ACRE (CQ) $ $
20301-0700
Line D0320 85 EACH $ $
20301-1200
Line D0340 11 EACH $ $
Schedule Total: ________________________
Submitted by: _________________________
REMOVAL OF DELINEATOR
REMOVAL OF HEADWALL
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR QUALITY CONTROL
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, PLASTIC LINING
SOIL EROSION CONTROL, SANDBAG
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, TEMPORARY CULVERT PIPE (18-inch)
SOIL EROSION CONTROL, TEMPORARY 36-INCH CULVERT PIPE
SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM
Revised by Amendment A003
A-30
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
20301-1400
Line D0360 1 EACH $ $
20301-1700
Line D0380 2 EACH $ $
20301-1900
Line D0400 7 EACH $ $
20301-2300
Line D0420 35 EACH $ $
20301-3700
Line D0440 2 EACH $ $
20303-3000
Line D0460 200 SQYD $ $
20401-0000
Line D0480 25,820 CUYD $ $
20402-0000
Line D0500 4,780 CUYD $ $
20411-0000
Line D0520 9,450 TON $ $
20465-0000
Line D0540 50 EACH $ $
20701-0300
Line D0560 125,960 SQYD $ $
20720-0300
Line D0580 23,870 SQYD $ $
25101-0200
Line D0600 180 CUYD $ $
25101-2000
Line D0620 85 CUYD $ $
25101-2200
Line D0640 70 CUYD $ $
25120-2000
Line D0660 90 LNFT $ $
26001-0000
Line D0680 1,410 LNFT $ $
ROCK BOLT (25 kip)
SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C
REINFORCEMENT GEOSYNTHETIC, TYPE 3 (biaxial)
PLACED RIPRAP, METHOD A, CLASS 2
REMOVAL OF TERMINAL SECTION
REMOVAL OF SIDEWALK, ASPHALT
ROADWAY EXCAVATION
REMOVAL OF INLET (salvage for reset)
PLACED RIPRAP, METHOD B (headwall)
PLACED RIPRAP, METHOD B, CLASS 2
RIPRAP DITCH, METHOD B (Class 1 or 2)
REMOVAL OF MANHOLE (monitoring well)
REMOVAL OF PIPE CULVERT
REMOVAL OF SIGN/MARKER
SUBEXCAVATION
SELECT BORROW
CONSERVE AND PLACE BOULDER
Revised by Amendment A003
A-31
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
26001-0000
Line D0700 2,105 LNFT $ $
26002-0000
Line D0720 400 LNFT $ $
30101-2000
Line D0740 43,320 TON $ $
30302-1000
Line D0760 125 LNFT $ $
30801-0000
Line D0780 77,500 SQYD (CQ) $ $
40101-5600
Line D0800 11,650 TON $ $
40105-3000
Line D0820 120 TON $ $
40601-0000
Line D0840 38 TON $ $
40605-0000
Line D0860 506 TON $ $
40801-0000
Line D0880 17,000 TON $ $
41201-0000
Line D0900 47 TON $ $
60103-0000
Line D0920 2 EACH $ $
60103-0440
Line D0940 2 EACH $ $
60201-0200
Line D0960 70 LNFT $ $
60201-0400
Line D0980 80 LNFT $ $
60201-0500
Line D1000 55 LNFT $ $
60201-0600
Line D1020 750 LNFT $ $
12-INCH PIPE CULVERT
15-INCH PIPE CULVERT
18-INCH PIPE CULVERT
BLOTTER
COLD RECYCLED ASPHALT BASE COURSE
TACK COAT (grade CSS-1)
CONCRETE, HEADWALL (132-inch pipe culvert)
CONCRETE, HEADWALL FOR 144-INCH PIPE CULVERT
6-INCH PIPE CULVERT
AGGREGATE BASE GRADING D
DITCH RECONDITIONING
RECYCLED AGGREGATE BASE (pavement)
ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
ANTISTRIP ADDITIVE, TYPE 3
FOG SEAL (CSS-1 or CSS-1h)
ROCK BOLT (50 kip)
ROCK DOWEL
Revised by Amendment A003
A-32
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
60201-0800
Line D1040 400 LNFT $ $
60201-2400
Line D1060 78 LNFT $ $
60201-2500
Line D1080 68 LNFT $ $
60202-0800
Line D1100 50 LNFT $ $
60401-0000
Line D1120 2 EACH $ $
60403-0000
Line D1140 1 EACH $ $
60501-0000
Line D1160 170 LNFT $ $
60510-0700
Line D1180 1,220 LNFT $ $
60510-0800
Line D1200 170 LNFT $ $
60704-0000
Line D1220 23 EACH $ $
61203-0000
Line D1240 6 EACH $ $
61203-0000
Line D1260 1 EACH $ $
61501-1100
Line D1280 235 SQYD $ $
61701-2300
Line D1300 25 LNFT $ $
61702-0800
Line D1320 3 EACH $ $
61702-1200
Line D1340 1 EACH $ $
61708-1000
Line D1360 88 LNFT $ $
TERMINAL SECTION, TYPE LST
REMOVE AND RESET, GUARDRAIL
CLEANING CULVERT IN PLACE
MANHOLE, SANITARY SEWER (adjustment)
MANHOLE, SANITARY SEWER (air valve adjustment)
SIDEWALK, ASPHALT
GUARDRAIL SYSTEM G9, TYPE 2, CLASS B WOOD POSTS
TERMINAL SECTION TYPE TANGENT
48-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
MANHOLE (monitoring well manhole reset)
INLET (reset)
STANDARD UNDERDRAIN SYSTEM
6-INCH COLLECTOR PIPE
6-INCH OUTLET PIPE
24-INCH PIPE CULVERT
132-INCH PIPE CULVERT
144-INCH PIPE CULVERT
Revised by Amendment A003
A-33
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
62201-0250
Line D1380 200 HOUR $ $
62201-0900
Line D1400 100 HOUR $ $
62201-1400
Line D1420 100 HOUR $ $
62201-2850
Line D1440 100 HOUR $ $
62201-3000
Line D1460 50 HOUR $ $
62201-3000
Line D1480 50 HOUR $ $
62201-3400
Line D1500 100 HOUR $ $
62201-3750
Line D1520 80 HOUR $ $
62301-0000
Line D1540 200 HOUR $ $
62302-0100
Line D1560 1,550 HOUR $ $
62403-0000
Line D1580 3,100 CUYD $ $
62406-0100
Line D1600 11.5 ACRE (CQ) $ $
62501-0000
Line D1620 11.5 ACRE (CQ) $ $
62901-1400
Line D1640 375 SQYD $ $
63302-0000
Line D1660 345 SQFT $ $
63308-3000
Line D1680 2 EACH $ $
63309-0000
Line D1700 520 EACH $ $
DELINEATOR (Idaho Type 4F-B)
FURNISHING AND PLACING TOPSOIL
PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
TURF ESTABLISHMENT
ROLLED EROSION CONTROL PRODUCT, TYPE 5.C
SIGN SYSTEM
OBJECT MARKER, TYPE 3
HYDRAULIC EXCAVATOR (140HP minimum with 50 foot minimum reach)
HYDRAULIC EXCAVATOR (mini, 23.1HP to 40.2HP, with 5 foot minimum dozer blade)
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT
CHAIN SAW
GENERAL LABOR
SPECIAL LABOR, SLOPE SCALING
DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
BULLDOZER, 250HP MINIMUM FLYWHEEL POWER
MOTOR GRADER, 12 FOOT MINIMUM BLADE
Revised by Amendment A003
A-34
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63310-0000
Line D1720 6 EACH $ $
63316-1000
Line D1740 35 EACH $ $
63316-2000
Line D1760 4 EACH $ $
63401-0300
Line D1780 84,450 LNFT (CQ) $ $
63401-0300
Line D1800 224,040 LNFT (CQ) $ $
63401-0400
Line D1820 21,530 LNFT (CQ) $ $
63401-0450
Line D1840 3,950 LNFT $ $
63405-0050
Line D1860 24 EACH $ $
63502-0400
Line D1880 50 EACH $ $
63502-0600
Line D1900 20 EACH $ $
63502-1250
Line D1920 760 EACH $ $
63502-1300
Line D1940 510 EACH $ $
63502-1500
Line D1960 65 EACH $ $
63502-1600
Line D1980 95 EACH $ $
63502-1700
Line D2000 230 EACH $ $
63502-3700
Line D2020 50 EACH $ $
63503-0700
Line D2040 29,000 LNFT $ $
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
TEMPORARY TRAFFIC CONTROL, SNOW POLE
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
PAVEMENT MARKINGS, TYPE B, BROKEN (yellow)
PAVEMENT MARKINGS, TYPE B, DOTTED (white)
PAVEMENT MARKINGS, SYMBOLS (type B yield triangle)
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 1
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
CHANNELIZING DEVICE
REMOVE AND RESET SIGN
REMOVE AND RESET DELINEATOR (bollard type)
PAVEMENT MARKINGS, TYPE B, SOLID (yellow)
PAVEMENT MARKINGS, TYPE B, SOLID (white)
Revised by Amendment A003
A-35
Schedule D Account: ALL
Project No: ID PFH 21(7)
Name: Warren Wagon Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63503-1000
Line D2060 2,315 LNFT $ $
63504-1000
Line D2080 1,219 SQFT $ $
63506-0600
Line D2100 225 HOUR $ $
63507-0700
Line D2120 315 DAY $ $
63509-1000
Line D2140 7,200 FXHR $ 360,000.00 50.00 $
64702-1000
Line D2160 900 LNFT $ $
64703-6000
Line D2180 120 EACH $ $
64704-1000
Line D2200 740 CUYD $ $
65101-1000
Line D2220 375 SQYD $ $
MITIGATION, FISH PASSAGE BOULDER
MITIGATION, STREAMBED MATERIAL
DRAPED ROCKFALL PROTECTION, WIRE MESH (anchored)
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
TEMPORARY TRAFFIC CONTROL, FLAGGER
MITIGATION, LANDSCAPING LOG
| SF30amd_WORD |
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT |
| A003 |
| Amd_Page_2_Master |
| BID SCHEDULE |
| CONTRACT CLAUSES |
| Bid Schedule |
| A003A-7 |
| A003Bid Schedule A-D |
File details come from the government source that posted it.