PROJECT_DESCRIPTION_WA_NPS_OLYM_2015(4)_.docx
DOCX document 36 KB Posted
- Attached to
- WA NPS OLYM 2015(4), Spruce Railroad Trail Segment C Federal contract opportunity
- Solicitation number
- DTFH70-16-B-00011
About this file
Project Description WA NPS OLYM 2015(4)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidSum_Spruce_RR.pdf | ||
| A003_Spruce.pdf | ||
| Q A_7-28.pdf | ||
| A002.pdf | ||
| Q A_7-20.pdf | ||
| A001_Spruce.pdf | ||
| XS_May2016.pdf | ||
| 2016-01-15_Illumination_Memo.pdf | ||
| Spruce_Tunnel-Portal_Structure_Technical_Memorandum_3-30-16.pdf | ||
| Helgeson_Asbestos_Disposal_Record.pdf | ||
| Plan_Request_form_SpruceRR.pdf | ||
| Helgeson_Hazardous_Materials_Survey.pdf | ||
| SWPPP_WA_NPS_OLYM_2015(4)_Spruce_Railroad_Trail_Segment_C.pdf | ||
| Spruce_Tunnels_-_GRR_02.02.2016_rev2_text_and_pictures.pdf | ||
| IFB__SpruceRR.pdf | ||
| Plans_SpruceRR.pdf | ||
| GM03-16_Spruce_RR_Trail_Segment_C_WA_NPS_OLYM_2015(4)__Geotech_Recomm_8Jan2016.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WA NPS OLYM 2015(4), Spruce Railroad Trail Segment C, Clallam County, Washington
The work consists of grading, excavation, parking area construction, tunnel work, culvert portals, clearing and other small items of work.
Project length: .56 Miles
Tentative Fixed Completion Date: Spring 2017 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $1 million to $2 million
Location: 20 Miles West of Port Angeles, Washington
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
One Schedule Base
DIVISION 150 – Project Requirements
| 152 Construction Survey & Staking (yes/no) |
| Yes |
| 153 Contractor Quality Control and Assurance |
(yes/no)
| Yes |
| 154 Contractor Sampling & Testing (yes/no) |
| Yes |
| 155 Schedules for Construction Contracts (construction schedules) (yes/no) |
| Yes |
| 157 Soil Erosion & Sediment Control (erosion control devices) |
Silt Fence Fiber Roll
DIVISION 200 – Earthwork
201 Clearing & Grubbing
2.4 AC
202 Additional Clearing & Grubbing (clearing & grubbing) Removal, Individual Tree
33 EA
203 Removal of Structures & Obstructions (structures, demolition) Structure Concrete
2 EA
55 SY
204 Excavation Unclassified borrow Granular Backfill Select borrow Rock Excavation
430CY
4541 CY
170 CY
935 CY
50 CY
207 Geotextile Geogrid
6450 SY
1750 SY
| 208 Structure Excavation |
| 20 CY |
DIVISION 250 – Slope Reinforcement and Retaining Walls
| 251 Riprap |
| 15 CY |
| 255 Mechanically Stabilized Earth Wall |
| 745 SF |
| 257 Contactor-Designed Retaining Walls (contractor completed designs) |
| LS |
| 260 Rock Bolts |
| 400 lf |
DIVISION 300 – Aggregate and Base Courses
| 302 Minor Crushed Aggregate |
| 2500 T |
DIVISION 400 – Asphalt Pavements & Surface Treatments
| 403 Asphalt Concrete |
| 225 T |
DIVISION 500 – Rigid Pavement
| 552 Structural Concrete |
| 34 CY |
| 557 Timber Structures (structures, timber) |
| 300 LF |
| 566 Shotcrete |
| 150 CY |
DIVISION 600 – Incidental Construction
602 Culverts 18” Culverts 30”
89 LF
34 LF
| 603 Structural Arch Plate |
| 75 LF |
605 Underdrains Geocomposite Sheet Drains 60 lf
145 SY
| 609 Wheelstop, Concrete |
| 20 EA |
| 619 Fence, Type Cedar, 6’ |
| 220 LF |
| 622 Rental Equipment (yes/no) |
| Yes |
| 623 General Labor (yes/no) |
| Yes |
| 624 Topsoil (landscaping & related items) |
| 5460 SY |
625 Mulching, Dry Method Mulching, Hydraulic Method
1.1 AC
0.2 AC
633 Sign System Delineator Remove and reset sign
6 SF
18 EA
1 EA
| 634 Permanent Pavement Markings (traffic pavement markings) |
| 850 LF |
| 635 Temporary Traffic Control |
| LS |
| 647 Landscape Logs |
| 35 EA |