Bidders_Questions_6-22-16.pdf
PDF 8 KB Posted
- Attached to
- CA FTNP/NPS YOSE 500(1) & 16(7) Federal contract opportunity
- Solicitation number
- DTFH6816B00014
About this file
Questions and Answers for the project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_tabs_1.pdf | ||
| 00_CA_FTNP_YOSE_500(2)_ _16(7)_EE_ _SOQ.pdf | ||
| CA_FTNPNPS_YOSE_500(2)_Bid_Opening_Summary.pdf | ||
| Amendment_A001.pdf | ||
| Bidders_Questions_7-8-16.pdf | ||
| CA_YOSE_500(2)_16(7)_100__Final_Hydraulics_Tech_Memo.pdf | ||
| Bidders_Questions_6-24-16.pdf | ||
| DTFH6816B00014_CA_FTNP-NPS_YOSE_500(2)_ _16(7).pdf | ||
| PLANS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidders Questions & Answers
CA FTNP/NPS YOSE 500(2) & 16(7)
6/22/16
1) Q: Under 636.04A #4 you specify a minimum LED display at least 24” wide and 20” tall. Does that refer to the total sign dimensions? Or specifically to the LED display itself? If the latter, that would be a very large sign for a road posted at 25 MPH.
A: As per 636.04A the LED display panel must be at least 24 inches wide and 20 inches tall.
2) Q: If our radar signs are already painted another color, must they be repainted in Yosemite brown? Or are you just referring to the posts and assorted hardware?
A: Response: As per 636.04A all exposed metal areas are to be painted “Yosemite Brown”.
To Be Answered Still:
3) I have a question about Road Striping Paint type D for this project. SECTION 634 PERMANNT PAVEMENT MARKING. Type D Paint IS NOT LONGER USED IN CALIFORNIA and I want see if We can used a Type A instead. Please advise.
A:
4) Specifications mention attendance by the TCS (Traffic Control Supervisor) is required at certain meetings; however, there is no bid item for TCS included with this project. Is a TCS required for this project?
A:
5) Does each phase need to be completed before starting another or can they, or portions of phases, be under construction at the same time?
A: