Bidders_Questions_6-22-16.pdf

PDF 8 KB Posted

Attached to
CA FTNP/NPS YOSE 500(1) & 16(7) Federal contract opportunity
Solicitation number
DTFH6816B00014
Issued by
Department of Transportation Federal Highway Administration

About this file

Questions and Answers for the project.

View the file

Other files for this federal contract opportunity

Other files attached to CA FTNP/NPS YOSE 500(1) & 16(7), newest first.
File Type Posted
Bid_tabs_1.pdf PDF
00_CA_FTNP_YOSE_500(2)_ _16(7)_EE_ _SOQ.pdf PDF
CA_FTNPNPS_YOSE_500(2)_Bid_Opening_Summary.pdf PDF
Amendment_A001.pdf PDF
Bidders_Questions_7-8-16.pdf PDF
CA_YOSE_500(2)_16(7)_100__Final_Hydraulics_Tech_Memo.pdf PDF
Bidders_Questions_6-24-16.pdf PDF
DTFH6816B00014_CA_FTNP-NPS_YOSE_500(2)_ _16(7).pdf PDF
PLANS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidders Questions & Answers

CA FTNP/NPS YOSE 500(2) & 16(7)

6/22/16

1) Q: Under 636.04A #4 you specify a minimum LED display at least 24” wide and 20” tall. Does that refer to the total sign dimensions? Or specifically to the LED display itself? If the latter, that would be a very large sign for a road posted at 25 MPH.

A: As per 636.04A the LED display panel must be at least 24 inches wide and 20 inches tall.

2) Q: If our radar signs are already painted another color, must they be repainted in Yosemite brown? Or are you just referring to the posts and assorted hardware?

A: Response: As per 636.04A all exposed metal areas are to be painted “Yosemite Brown”.

To Be Answered Still:

3) I have a question about Road Striping Paint type D for this project. SECTION 634 PERMANNT PAVEMENT MARKING. Type D Paint IS NOT LONGER USED IN CALIFORNIA and I want see if We can used a Type A instead. Please advise.

A:

4) Specifications mention attendance by the TCS (Traffic Control Supervisor) is required at certain meetings; however, there is no bid item for TCS included with this project. Is a TCS required for this project?

A:

5) Does each phase need to be completed before starting another or can they, or portions of phases, be under construction at the same time?

A: