Attachment_7_-_Interim_Progress_Review_Content.docx
DOCX document 12 KB Posted
- Solicitation number
- DJF-16-1200-Q-0000022
About this file
Interim Progress Review Content
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_9_-_List_of_Government_Furnished_Equipment.docx | DOCX document | |
| Attachment_2_-_Project_Test_and_Safety_Plan_Contents.docx | DOCX document | |
| Attachment_6_-_Technical_Presentation_Content.docx | DOCX document | |
| Attachment_4_-_Monthly_Quad_Chart_Template.pptx | PPTX presentation | |
| RFQ_DJF-16-1200-Q-0000022.pdf | ||
| Attachment_1_-_Project_Management_Plan_Contents.docx | DOCX document | |
| Attachment_3_-_Monthly_Status_Report_Template.docx | DOCX document | |
| Appendix_1_-_Task_Order_Pricing_Template.xlsx | XLSX spreadsheet | |
| Attachment_5_-_Technical_Report_Content.docx | DOCX document | |
| Attachment_8_-_Final_Technical_Briefing_Content.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 7
Interim Progress Reviews
The Contractor shall provide an interim status and financial briefing to the Government. The reviews will be held at a location to be specified by the Government, or may be done telephonically. This briefing shall include the following information:
· The technical, schedule status of the project.
· The prior quarter’s accomplishments and the coming period’s projected activities, as well as the status of the project relative to all deliverables and milestones.
· The financial status of the project, including expenditures, outstanding commitments, and invoice status.
· All technical, contractual, schedule changes.
· Any potential risks/issues encountered or anticipated and appropriate mitigation schemes.
· A brief discussion of the testing and analysis performed during the prior period.