Contract Title: SONORAN SUBSTATION COMMUNICATION ADDITIONS Award Date:
Contract No.: NTP:
Contractor: Completion Date:
Location Date Submittal Item In Date Sent to Date
# # Submittal Item Standards CSO DSW Date Due Submitted CSO Approved COMMENTS
STANDARD 1
1 Construction Schedule 1.1.4.1. 3 (see project spec)
2 Survey Plan 1.1.5.2.(1) 3 Prior to survey work
3 Survey Notes 1.1.5.5. & 1.1.5.7. 1 Immed. upon completing
4 Survey Data Collector Dump & Computer Printout 1.1.5.6. 1 Immed. upon completing
5 Survey Field Book 1.1.5.7. 1 Immed. upon completing
6 Breakdown of Contract Prices 1.1.6.1. 1 1 NLT 30-days after NTP
7 Electrical Equipment & Steel Purchase Orders 1.2.3.1. 1 NLT 10-working-days after PO award
8 Cable Location Plan w/Print of Locations 1.3.4.2 & 1.4.5.2 1 1 Prior to starting excavation
9 Acknowledgement When Stringing Over Energized Lines 1.3.5.3. 1 Prior to starting stringing
10 Safety and Health Program 1.4.1.5. 1 NLT 10-days prior to start of construction
11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. 1 Prior to use
12 - Load Performance Tests 1.4.1.10.(1) 1 Prior to use
13 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) 1 Prior to use
14 - Brake Performance Test 1.4.1.10.(3) 1 Prior to use
15 - Test Results of Protective Ground Leads 1.4.1.10.(4) 1 Prior to use
16 - Material Safety Data Sheets 1.4.1.10.(5) 1 Prior to use
17 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) 1 Prior to use
18 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 1 Prior to use
19 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 1 Prior to use
20 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 1 Prior to use
21 Assurance of Competency in Equipment Operation 1.4.3.4. 1 Prior to use
22 Structure Erection Plan 1.4.8.1. 1 Prior to structure erection
23 Protective Ground Lead Test Results & Certification 1.4.14.3. 1 Prior to use
24 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3. 1 NLT 10-working-days prior to starting work
25 Stringing Plan 1.4.17.3. 1 Prior to stringing
26 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) 1 Prior to stringing
STANDARD 2
Submitted To Copies
SUBMITTAL TRACKING SHEET
Location Date Submittal Item In Date Sent to Date
# # Submittal Item Standards CSO DSW Date Due Submitted CSO Approved COMMENTS Submitted To
Copies
27 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 1 20-days prior to compacting
28 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. 1 Immed. after test complete
29 Gravel Surfacing Material Gradation 2.1.1.4 1 Prior to placing
30 Gravel Surfacing Density & Compaction Test Results 2.1.1.4 1 NLT 7-days after test complete
31 Batch Certification 2.1.1.7.(6) 1 NLT 20-days prior to paving
32 Earth Backfill Material 2.3.1.3. & 2.8.1.2.(1) 1 Prior to refill
STANDARD 3
33 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3. 1 NLT 20-days prior to concrete placement
34 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. 1 NLT 10-days prior to use
35 Flyash For Concrete 3.1.1.2.(5) & 3.1.1.4. 1 NLT 20-days prior to use
36 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. 1 NLT 10-days prior to use
37 Batch Certificates 3.1.1.2.(7) 1 Provide at delivery
38 Test Reports 3.1.1.2.(8) 1 Immed. upon completing
39 Void Forming Material 3.1.1.2.(9) & 3.1.1.4. &
3.1.4.2. 2 Prior to use
40 Nonshrink Grout 3.1.1.2.(10) 1 Prior to use
41 Drawings & Data For Electrical Equip. Foundation Design 3.2.1.2. 2 T Prior to installation
42 Approval Drawings For Precast Cable Trench 3.2.1.3. 2 T Prior to precasting
43 Approval Drawings For Precast Concrete Pull Boxes 3.2.1.4. 2 T Prior to precasting
44 Final Drawings For Precast Cable Trench & Pull Boxes 3.2.1.5. 1 & T 2 Prior to material shipment
STANDARD 9
45 Contractor On-site Test Personnel 9.1.2.2.(2) 1 Prior to working on-site
46 Electrical Test Reports & Documents 9.1.2.2.(3) 2 NLT 7 days after testing
47 Continuity & Megohmmeter Testing Personnel 9.1.2.2.(7) 1 Prior to testing
48 Infrared Inspection Tape 9.1.2.2.(15) 1 NLT 48-hours after testing
49 Equipment Installation Drawings Including Seismic Qualification Report Table 9-1 & 9.1.3.2. 3 NLT 60-days after NTP
50 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. 3 NLT 60-days after NTP
51 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) 1 NLT 21-days prior to equip.
installation
52 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) 1 4 NLT 21-days prior to equip.
installation
53 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) 1 4 NLT 21-days prior to equip.
installation
Location Date Submittal Item In Date Sent to Date
# # Submittal Item Standards CSO DSW Date Due Submitted CSO Approved COMMENTS Submitted To
Copies
54 Insulated Conductor Data Table 9-1 & 9.1.3.7. 2 NLT 60-days after NTP
55 Revised Wiring Diagrams Table 9-1 & 9.1.3.9. 3 NLT 60-days after receipt of drawings
56 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) 1 1 NLT 60-days after equip.
checkout
57 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) 1 NLT 60-days after equip.
checkout
58 Test Reports For Ground Tests 9.2.1.3. 3 NLT 15-days after completion of testing
STANDARD 10
59 Catalog Data Sheets of Accessories & Hardware Used In Conductor & Overhead Ground Wire Installation 10.2.2. 3
NLT 40-days prior to material installation
60 Drawings of Insulator & Overhead Groundwire Assemblies and Details 10.2.2. 3
NLT 40 days prior to material installation
61 Complete Material List 10.2.2. 1 NLT 40-days prior to material installation
STANDARD 13
62 Recycled Materials Quantity Report 13.2.1. & 13.7.2. 1
63 Products Containing Recovered Materials Report 13.2.2. & 13.8.3. 1
64 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2. 1
65 Asbestos Licenses or Certificates 13.2.10. & 13.15. 1
66 PCB Test Reports 13.2.13 & 13.18.2 1
67 Cleanup Work Management Plan 13.2.16. & 13.19.2. 1
68 Post Cleanup Report 13.2.17. & 13.19.7. 1
STANDARD 15
69 As-Built Drawings 15.2.6. 1
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable