SONORA SUBSTATION COMMUNICATION ADDITION

ARIZONA

SECTION C

DESCRIPTION/SPECIFICATION

Amendment 002 April 27, 2016

PROJECT DRAWINGS

SONORA SUBSTATION COMMUNICATION ADDITION PROJECT DRAWINGS

A. GENERAL:

CONSTRUCTION STANDARD DRAWINGS: A complete set of standard drawings are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx. Construction drawings are the specification drawings and any additional drawings required for use in construction. The construction drawings will be issued after contract award and may include amendment changes and other details, which make the drawings suitable to use for construction purposes.

PROJECT DRAWINGS: Project drawings included herein are reduced reproductions and are not to scale.

Some project drawings show details of fabrication and other information not a part of the work. Disregard information and details, which are not applicable.

STANDARD DRAWINGS: Where details shown on standard drawings included herein differ from project drawings or text, the details of project drawings or text shall govern.

INFORMATIONAL DRAWINGS: Some project drawings have the words “FOR INFORMATION ONLY” appearing above the title block. These drawings show some information, which may be required for bidding purposes. These drawings do not show items to be furnished or work to be performed.

EXISTING INSTALLATION DRAWINGS: Some project drawings have the words “EXISTING INSTALLATION” appearing above the title block. These drawings show the existing installations prior to modifications and may show some new work to be performed.

REFERENCE DRAWINGS: Reference drawings referred to on project drawings and not included herein, are not necessary for bidding purposes.

CONTRACTOR'S RESPONSIBILITY: Check all drawings and advise Western of any errors or omissions.

B.

LIST OF DRAWINGS:

LOCATION MAPS:

1. SON 0015 Rev. B – Topography Map

2. SON 0016 – Location Map

3. TEL 0015 – Location and Vicinity Map

WORKING DRAWINGS:

4. TEL 2875 Rev. D – 100’ Self-Supporting Tower Tower

5. 43-30MW 2204 Rev. A – Monopole Foundation Drilled Auger Type

6. 43-30MW 2203 Rev. A – 30’ Heavy Monopole Outline

7. SON 0010 Rev. C – General Plot Plan

8. TEL T3000 Rev. B – Communication Building Architectural Floor Plan & Details

9. TEL 7050 Rev. A – Rack Layouts THA1-THA5 Arrangement

10. SON 7051 – Rack Layouts THC & THD Arrangement

11. SON 3000 – Service Building Architectural Overhead Cable Tray Plan

12. SON 4000 – Control Room Arrangement

13. SON 2875 - Self-Supporting Tower Layout

14. SON 2876 – STD 30’ Heavy Monopole Bridge Channel and Monopole

15. SON 1005 Rev. F. – 69-kV Area Grounding and Buried Cable Plan https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx

SON 0015
SON 0016
TEL 0015
TEL 2875D
43-30MW 2204
43-30MW 2203
SON 0010
SON 2876
SON 7051
TEL T3000B
SON 4000
SON 3000
SON 2875
SON 2876
TEL 7050A
TEL 2875

File details come from the government source that posted it. Updated .