21._Attachment_A_-_Revised_Specifications.pdf
PDF 553 KB Posted
- Attached to
- Poudre Substation Stage 05 Federal contract opportunity
- Solicitation number
- DE-SOL-0008557
About this file
REVISED Attachment A - Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 21._Attachment_A_-_Revised_Specifications_09-11-15.pdf | ||
| 21._DE-SOL-0008557_AMD_000004.pdf | ||
| 21._DE-SOL-0008557_AMD_000003.pdf | ||
| 21._DE-SOL-0008557_AMD_000002.pdf | ||
| 21._Transformer_outline.pdf | ||
| 21._DE-SOL-0008557_AMD_000001.pdf | ||
| 21._Serial_Number_of_Transformer.pdf | ||
| 21._Attachment_G_-_Poudre_Substation_Q As_and_Attendance.pdf | ||
| 21._Attachment_C_-_Wage_Determinations.pdf | ||
| 21._Attachment_A_-_Specifications.pdf | ||
| 21._DE-SOL-0008557.pdf | ||
| 21._IFB_Letter-signed.pdf | ||
| 21._Attachment_F_-_Bid _Performance _Payment_Bonds_-_Cover_Page.pdf | ||
| 21._Attachment_B_-_Drawings.pdf | ||
| 21._Attachment_D_-_CRD_DPO.pdf | ||
| 21._Attachment_E_-_Form_W3000-72.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A
POUDRE SUBSTATION
STAGE 05 - Specifications 05/04/2015
DE- SOL-0008557
POUDRE SUBSTATION
STAGE 05
Spec No. 830
SECTION C
DESCRIPTION/SPECIFICATIONS
COLORADO
SECTION C
DESCRIPTION/SPECIFICATIONS
POUDRE SUBSTATION STAGE 05
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT
B. DESCRIPTION OF WORK
1. Demolition
2. Sitework
3. Substation Concrete
4. Substation Metalwork
5. Substation Electrical
C. DESCRIPTION OF BIDDING SCHEDULE ITEM
1. Bidding Schedule item “Mobilization and preparatory work”
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
1. Commencement and Completion
2. Submittal Approval Time
3. Commencement of Control Work
4. Outage Restrictions
5. Construction Schedule Restrictions ............................................... Error! Bookmark not defined.
6. Maximum Available Fault Current
7. Typical Foundations for Contractor and Government-Furnished Electrical Equipment and
Oil Detention Structures
E. CONSTRUCTION PROGRAM
1. Submittal Time
2. Format and Detail
F. MATERIAL
1. Points-of-Delivery
G. GEOLOGIC INVESTIGATIONS
H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES
I. WATER FOR CONSTRUCTION PURPOSES
J. EXPLOSIVES AND BLASTING
K. SUBMITTALS
1. General
2. Hard Copy Submittal Exception
3. Approval Time
4. Transmittal ...................................................................................... Error! Bookmark not defined.
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEM
1. Bidding Schedule item “Miscellaneous sitework”
2. Bidding Schedule item “Demolition”
3. Bidding Schedule Item “Oil Containment”
4. Bidding Schedule does not contain separate items
DIVISION 3 – CONCRETE
A. GENERAL
1. Material
2. Test for Potential Reactivity of Sand and Coarse Aggregate
3. Curing
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Concrete foundations”
DIVISION 4 – SUBSTATION METAL WORK
A. GENERAL
1. Government-Furnished Drawings
2. Measurement
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Steel structures, welded (galvanized)”
2. Bidding Schedule item “Modifying steel structures”
DIVISION 9 – SUBSTATION – ELECTRICAL
A. GENERAL
1. Bidding Schedule for Government-furnished items
2. Bidding Schedule for items (not furnished by the Government)
3. Associated Support Structures Provided for Each Electrical Equipment Rated Above 7-kV
4. Installation and Painting of Electrical Equipment and Material
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Power transformer, 115/12.47-kV, 7.5/9.3 MVA, three-phase
(Relocated)”
2. Bidding Schedule items “Power circuit breaker, 115-kV, 3000 amps (Government-furnished)” and “Power circuit breaker, 72.5-kV, 2000 amps (Government-furnished)”
3. Bidding Schedule items “Disconnecting switch,115-kV, 3000 amps” and “Disconnecting switch, 12.47-kV, 2000 amps”
4. Bidding Schedule item “Single-pole fuse disconnecting switch, 12.47-kV”
5. Bidding Schedule items “Current transformer, 115-kV, single-phase”
6. Bidding Schedule items “Coupling capacitor voltage transformer (CCVT), 115-kV, single-phase”
7. Bidding Schedule item “Station service transformer, 7.2/12.47-kV, 75-kVA”
8. Bidding Schedule item “4/0 AWG, 15-kV, insulated copper cable”
9. Bidding Schedule item “Associated electrical equipment and material”
10. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable”, “Furnishing 12/c
No. 10 AWG control cable”, “Furnishing 25/c No. 18 AWG control cable”, and “Furnishing 3/c No. 18 AWG control cable”
11. Bidding Schedule items “Installing 5/c No. 10 AWG control cable”, “Installing 12/c No. 10 AWG control cable”, “Installing 25/c No. 18 AWG control cable”, and “Installing 3/c No. 18 AWG control cable”
12. Bidding Schedule item “Duplex switchboard section (1) CHA2 (Government-furnished)”
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
Construct and complete Poudre Substation Stage 05, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western’s Construction Standards, including Standard 1 – General Requirements (September 2013), Standard 2 – Sitework (September 2013), Standard 3 – Concrete (September 2013), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2013), Standard 9 – Substation – Electrical (September 2013), Standard 13 – Environmental Quality Protection (September 2013), Standard 15 – Drawings (September 2013); Standard Drawings; and these Project Specifications and Drawings.
If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.
Western’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at http://ww2.wapa.gov/sites/western/business/selling/Pages/buys.aspx .
Western Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.
B. DESCRIPTION OF WORK:
The principal components of work at the Poudre Substation include the following:
1. DEMOLITION:
a. Remove and dispose of 115/69-kV transformer, 12.47-kV transformer, 115-kV circuit breaker, disconnect switches, coupling capacitor voltage transformer, and all 69-kV equipment.
b. Remove and dispose of foundations and steel structures as shown on the Drawings.
c. Remove electrical conduit, entire length of cable, bus work, and related items.
2. SITEWORK:
a. Furnish and install compact backfill, gravel fill, gravel surfacing, oil containment, and herbicide for the substation, and where additional material is required.
b. Excavate, remove, and dispose of all material not suitable of needed for compacted fills and repairing berms.
3. SUBSTATION CONCRETE:
a. Furnish and install foundations for substation steel structures, electrical equipment, and materials.
4. SUBSTATION METALWORK:
a. Furnish and install galvanized, steel structures as shown on Drawings.
http://ww2.wapa.gov/sites/western/business/selling/Pages/buys.aspx
5. SUBSTATION ELECTRICAL:
a. Install Tristate furnished transformer with LTC. (Relocated).
b. Install Government-furnished equipment (GFE) power circuit breakers.
c. Furnish and install electrical equipment per drawings and specifications including but not limited to disconnecting switches, coupling capacitor voltage transformers, current transformers, station power voltage transformer, high voltage bus, grounding system, conduit, insulated cables, terminal boxes, and safety switches.
d. Removing existing control boards and installing Government-furnished switchboard.
Paragraphs “Description of Bidding Schedule Items” in Divisions – 1, 2, 3, 4, 9, and 13 describe the work to be performed.
The work is located in Larimer County near Fort Collins, Colorado. As shown on Drawing
PD 0015.
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.
b. Providing a Construction Program and Safety and Health Program.
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT AND COMPLETION: Begin work within 10-calendar days after date of receipt of Notice to Proceed, and complete all work within 270-calendar days from the date of receipt of such notice by “NTP”.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 20-calendar days for review of drawings or data submitted for approval.
3. COMMENCEMENT OF CONTROL WORK: Do not perform any control board or outdoor equipment wiring until receipt of Government-furnished wiring diagrams. Western will furnish outdoor wiring and schematic diagrams no sooner than two weeks after switchboard delivery.
Include these restrictions in the Construction Program.
4. CONSTRUCTION SCHEDULE AND OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following construction schedule and outage restrictions shall apply:
a. Limit outages for Poudre 115KV main bus to 8 to 10 hours at any given time.
b. No concurrent main and transfer bus outages will be issued.
5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized to carry the maximum available fault current in accordance with the Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:
a. The maximum available fault current in the 115-kV area is 12,020 amps and the X/R ratio is 7.9 prior to completing construction and 12,020 amps and the X/R ratio is 7.9 after completing construction.
b. A minimum of one (1) 1/0 ground shall be used in the 115-kV area.
c. The maximum available fault current in the 12.47-kV area is 28,750 amps and the X/R ratio is 33.5 prior to completing construction and 28,750 amps and the X/R ratio is
33.5 after completing construction.
d. A minimum of one 2/0 ground shall be used in the 12.47-kV area.
e. No protective ground leads shall be longer than 36-feet in length, unless approved by the Contracting Office Representative (COR). Resistance values given in Personal Protective Ground Test Reports shall be less than or equal to those allowed is ASTM F 2249.
6. TYPICAL FOUNDATIONS FOR CONTRACTOR AND GOVERNMENT-FURNISHED
ELECTRICAL EQUIPMENT AND OIL DETENTION STRUCTURES: Typical foundations are shown in Drawings PD 2302 and PD 2303. Western will design these foundations after receipt of the seismic report and informational drawings and data, including the seismic report from the equipment manufacturer. Western will forward the revised Construction Drawings for these foundations no later than 45-days prior to the “NLT” delivery date listed in the, “Material” section. If the “NLT” delivery date is adjusted by Western, forwarding of revised Foundation Construction Drawings will be automatically adjusted in a like manner.
E. CONSTRUCTION PROGRAM:
1. SUBMITTAL TIME: Submit a Construction Program to the COR within 15-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by Western as listed below:
ITEM
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
1. One (1) 3-phase, 115/12.47-kV, 7.5/9.3 MVA, transformer 79,000
2. One (1) 3-phase, power circuit breaker, 115-kV, 3,000 amp
NST 05-04-15
NLT 05-21-15
3. One (1) 3-phase, power circuit breaker, 12.47-kV, 2,000 amp
NST 05-04-15
NLT 05-21-15
4. (1) Duplex switchboard section, CHA2 1,500 NST 03-12-15
NLT 03-25-15
NST – No sooner than.
NLT – No later than.
1. POINTS-OF-DELIVERY: Material furnished by Western will be delivered to Poudre Substation.
The Contractor is responsible for unloading of Western-furnished material. The Contractor shall inspect the equipment and report any damages to the COR.
G. GEOLOGIC INVESTIGATIONS:
Geologic logs of subsurface explorations included in the “Drawings” Division constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown on the Drawings.
Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant.
Western does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.
The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations, and doing other work affected by geology and ground water elevations at the worksite.
H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
The Contractor shall provide electricity needed for construction purposes. Several 120 VAC receptacles are available. Coordinate with the COR for establishing electric power service.
I. WATER FOR CONSTRUCTION PURPOSES:
Furnish water for construction purposes. Make arrangements for obtaining the water, and provide for conveying the water to the points of use.
J. EXPLOSIVES AND BLASTING:
Explosives shall not be used.
K. SUBMITTALS:
1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification. Submittals via email shall be in standard PDF or Electronic CAD “*.dwg” (AutoCAD 2010) formats. All submittals shall include the Western contract number (DE-WA000XXXX), Western project title, and Bidding Schedule Contract Line Item Number (CLIN) and applicable division number. Multiple CLIN’s on a single submittal are not permitted. A cover transmittal letter in Microsoft Word or PDF format shall be included with each email. Email submittals shall be delivered to: RMR-J5600-CS@wapa.gov .
2. SUBMITTAL RESPONSE: Western will return all submittals electronically with an “Approved” or “Not Approved” status with comments as appropriate to the email address where the submittal originated.
3. APPROVAL TIME: Approval time for submittals shall be in accordance with the "Commencement, Prosecution, and Completion of Work" paragraph.
mailto:RMR-J5600-CS@wapa.gov
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Miscellaneous sitework” includes the following:
a. Replacing and protecting existing gravel surfacing.
2. Bidding Schedule item “Demolition” includes the following:
a. Completely removing concrete foundations designated on Existing Installation Drawings PD 2008, PD 2028, and PD 2029.
b. Removing the following structures:
(1) 115-kV Coupling Capacitor Support on Drawing PD 2016.
(2) 115-kV Switch Supports on Drawing PD 2014.
(3) Lightening arrestors
(4) Fencing around lightening arrestors.
Drawings are included showing typical structure details.
c. Removing and disposing of existing switchboard sections, CHA1 and CHA2. Existing end trim must be retained and reinstalled on new switchboard section, CHA2.
3. Bidding Schedule Item “Oil Containment” includes furnishing and installing oil containment system for the transformer shown on Drawings PD 2301, completely with SorbWeb Plus absorptive liner system or equal, sump pump pit, and other accessories. SorbWeb Plus or equal is to be installed per manufacturer’s instructions.
4. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.
a. Excavations for foundations, structures, and trenches.
b. Placing and compacting earth material and backfill.
c. Providing gravelfills under concrete foundations as shown on the Drawings.
d. Disposing of excavated material. The Contractor shall make arrangements required for disposal of waste material in an approved landfill.
DIVISION 3 – CONCRETE
A. GENERAL:
1. MATERIAL:
a. Cement: Type IIA cement in accordance with ASTM C 150 and ACI 318.
b. Compressive Strength: 4000 psi at 28-days for substation concrete.
c. Water-Cement Ratio: Net water-cement ratio, exclusive of water absorbed by the aggregates, shall not exceed 0.45 by weight.
d. Type A and D water-reducing and retarding admixtures may be used if approved by the
COR.
e. Use of fly ash is required in concrete, if readily available.
2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: Perform test for each source used. Perform tests for potential reactivity for the sand and coarse aggregate to be used by the Contractor. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source will be obtained by the Contractor.
3. CURING: Exposed, formed surfaces of concrete foundations shall be cured with water, resin-base curing compound without fugitive dye, or by covering with polyethylene film.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Concrete foundations” includes the following:
a. Earthwork, formwork, reinforcement, material used in concrete, void forming material, drilling and grouting anchor bars, anchor bolts, curing, finishing, joints, and other related work and material needed to complete the concrete construction.
b. Concrete foundations for steel structures.
c. Concrete foundations for electrical equipment.
d. Unwatering foundation excavations, if required.
Measurement for quantities for concrete foundations will be made on the basis of concrete quantities shown on Drawing PD 2008. If separate quantities of formed and auger concrete for each type of foundation are shown on the Drawing, the concrete quantity shall be the total of the formed and auger concrete quantities. Regardless of the concrete quantities actually placed, payment will be based on the quantities of concrete shown on the Drawing.
DIVISION 4 – SUBSTATION METAL WORK
A. GENERAL:
1. GOVERNMENT-FURNISHED DRAWINGS: Except as listed below, existing shop drawings for steel structures are not available.
2. MEASUREMENT: Measurement for quantities for Bidding Schedule items “Steel structures, welded (galvanized) and “Relocating and Modifying Steel Structures” will be made on the basis of weights calculated in accordance with LRFD, “AISC Code of Standard Practice for Steel Buildings and Bridges”, except that weights for nonrectangular shapes and plates are to be based on actual detailed dimensions.
a. Steel structure weights, calculated as noted above, are shown on the Government-furnished shop drawings and shall be shown on the Contractor-furnished final shop drawings, and payment will be based thereon. Steel estimated weights are shown on the specifications drawings for the structures requiring approval drawings as noted in the Bidding Schedule items “Steel structures, welded (galvanized)” and “Relocating and Modifying steel structures”.
b. Exposed surfaces of galvanized steel aluminum shall be dulled. The reflectance shall not be greater than 20 percent.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Steel structures, welded (galvanized)” includes providing the following:
a. One (1) Type III Equipment Support.*
b. Two (2) Type I Bus Frames.*
c. One (1) Type I Tee Bus Pole.*
d. Seven (7) single-switch operating platforms, including grating (31 2045).
e. Equipment cabinet platforms as follows, including gratings:
(1) One (1) – Type I for the 115-kV Transformer (KY1A) (31 2044).
(2) Two (2) – Type II for the 115-kV and 72.5-kV Circuit Breakers (JY1A and JW1A) (31 2044).
*Denotes structures requiring approval drawings.
The above material including connection bolts, nuts, washers, and lock nuts shall be galvanized and dulled.
2. Bidding Schedule item “Modifying steel structures” includes performing the following:
a. Modifying Steel Structures:
(1) Field modify top beam B-1 of the 69-kV Switch and Take-Off Structure as shown on Drawing PD 2018 for disconnecting switches XW1A to be mounted on the underside of the beam as shown on PD 1116.
(2) Field modify lower beam B-2 of the 69-kV Switch and Take-Off Structure as shown on Drawing PD 2018 for disconnecting switches YW1A and YW1B to be mounted on either side of the beam as shown on PD 1113.
b. In order to use the existing “69-kV Switch and Take-Off Structure” to go overhead connecting to PVREA’s future structure, these design limitations must be met of the original structure (PD 2018):
(1) Approach Span: 200-feet, 10 degree line angle.
(2) Vertical loads:
(a) Conductor 300 pounds.
(b) Ground wires 200 pounds.
(3) Maximum horizontal tension at 3/4-inches ice, 6 pound wind, negative 30 degrees Fahrenheit.
(a) Conductors 2,600 pounds.
(b) Ground wires 2,400 pounds.
DIVISION 9 – SUBSTATION – ELECTRICAL
A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES” Standard Equipment Specifications, as shown on Project Drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal Specifications and Standards as applicable. Applicable requirements shall be met under the following service conditions:
Ambient Temperatures:
Maximum ........................................................................................... +40°C Maximum 24-Hour Average .............................................................. +30°C Minimum ............................................................................................. -40°C
Elevation:
Above Mean Sea Level .............................................................. 4,960-Feet
*ASCE-7 Wind Load:
Miniumum Basic Wind Speed ........................................................ 90 MPH Importance Factor ................................................................................ 1.15
*IEEE Seismic Qualification:
As specified in bidding schedule item descriptions.
*Wind and seismic loads are nonsimultaneous.
1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:
a. Unless otherwise indicated, unloading and inspecting Government-furnished items.
b. Installing Government-furnished items as shown on drawings.
c. Furnishing equipment and material not furnished by Western.
2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the Contractor and shall include the following:
a. Providing (furnishing and installing) bidding schedule items.
b. Furnishing equipment and material not furnished by Western.
c. Installing bidding schedule items as shown on drawings.
3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel. Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.
4. Installation and painting of electrical equipment and material shall be provided in accordance with Standards 9 and 12 respectively.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Power transformer, 115/12.47-kV, 7.5/9.3 MVA, three-phase (Relocated)” includes furnishing all equipment and material not furnished by Western and installing the Government-furnished power transformer, including the assembly of the transformer and filling it with oil.
DESIGNATION (SINGLE-PHASE) KY1A
Manufacturer Kuhlman
Voltage Rating (kV) 115/12.47
Rating (MVA) 7.5/9.3
Oil (LBS) 30,673
Total Weight (including oil) (LBS) 79,270
a. The Contractor will move and unload the power transformer located at 7649 REA Parkway, Fort Collins, CO 80528. Contractor personnel shall inspect the power transformer for possible damage during shipment or transportation and report any damage to Western’s COR.
b. The Contractor shall install the transformer in accordance with the equipment manufacturer’s instruction books, the oil purification instruction book and manufacturer’s erection engineer. The manufacturer is Kuhlman. The Contractor is responsible for contacting the transformer manufacturer and complying with all their requirements for completing the vacuum filling process.
c. Spare parts furnished with each transformer bank may include but not be limited to the following:
(1) Spare bushings.
(2) One (1) complete set of gaskets.
(3) One (1) complete extra relay and contactor of each type and size.
(4) One (1) air cell, if a constant pressure system is used.
(5) One (1) cooling fan and motor assembly for cooling unit (if transformers with forced-air cooling are furnished).
(6) One (1) complete oil pump and motor assembly for one (1) cooling unit (if transformers with forced-oil cooling are furnished).
The Contractor shall deliver the spare parts listed above to Western’s onsite representative.
2. Bidding Schedule items “Power circuit breaker, 115-kV, 3000 amps (Government-furnished)” and “Power circuit breaker, 72.5-kV, 2000 amps (Government-furnished)”:
DESIGNATION JY1A JW1A
Manufacturer MEPPI MEPP1
Type SF6 gas SF6 gas
DESIGNATION JY1A JW1A
Nominal Voltage Rating (kV) 115 69
Maximum Voltage Rating (kV) 123 72.5
Continuous Current (Amps) 3000 2000
Rated Short Circuit Current (kA) 40 40
Rated interrupting time (Cycles) 3 3
Estimated Weight of 3-pole Breaker 6353 LBS 4850 LBS
Multi-ratio Current Transformers, each bushing (Amps)
2-1200:5 2-1200:5
The equipment supplier will unload the power circuit breakers from the truck, and Contractor personnel shall inspect the power circuit breakers for possible damage during shipment or transportation and report any damage to Western’s COR.
a. One (1) set of spare parts furnished with each voltage class of power circuit breaker will include two (2) trip coils and two (2) close coils.
b. Special tools and appliances will be furnished with each power circuit breaker. Included are one (1) SF6 gas breaker filling connection assembly (i.e., including hose, pressure gauge, and the hose connections to the breaker and SF6 gas cylinder).
The Contractor shall deliver the spare parts and special tools to Western’s onsite representative.
3. Bidding Schedule items “Disconnecting switch,115-kV, 3000 amps” and “Disconnecting switch, 12.47-kV, 2000 amps” includes providing switches in accordance with WAPA ES 8.1 Equipment Standard and providing associated support structures:
DESIGNATION WY1A,YY1A,
YY1B YW1A,YW1B XW1A
Type
3-pole, single-throw, outdoor, group operated, vertical break, rotating insulator
3-pole, single-throw, outdoor, group operated, vertical break, rotating insulator
3-pole, single-throw, outdoor, group operated, vertical break, rotating insulator
System Nominal Voltage Rating (kV) 115 12.47 12.47
Rated Maximum Voltage (kV) 123 15 15
DESIGNATION WY1A,YY1A,
YY1B YW1A,YW1B XW1A
Basic Impulse Insulation Level (kV) 550 110 110
Continuous Current Rating (Amps) 3,000 2,000 2,000
Momentary Current Rating (kA)
Grounding Blades None None None
Standard Arcing Horns Yes Yes Yes
Switch Operator Type Manual Worm Gear Operator
Manual Worm Gear Operator
Manual Worm Gear Operator
Phase Spacing (FT) 7’-0” 5’-0” 5’-0”
Height of Support Structure (FT) 8’-6” 20’-0” 20’-0”
Mounting Position Horizontal Vertical Horizontal
Insulator Technical Reference No. TR286 TR205 TR205
Control Circuit Voltage Not Required Not Required Not Required Auxiliary Switch Not Required Not Required Not Required Key Interlock No No No
* Approximate mounting height.
a. Seismic Qualification: Each disconnecting switch and its associated support structure shall be qualified for the moderate seismic qualification level according to the requirements of IEEE Standard 693-2005 and shall have a seismic identification plate attached. Time history shake-table testing is required for the moderate seismic qualification level and seismic qualification reports shall be submitted in accordance with Standard 9.
4. Bidding Schedule item “Single-pole fuse disconnecting switch, 12.47-kV” includes providing single-pole fuse disconnecting switch in accordance with WAPA ES 8.3 Equipment Specifications:
a. Equipment Type: Outdoor, single-pole, hook-operated, low noise fuses S&C Electric Company SMD drop out indicating type or equivalent.
DESIGNATION FW1A
Nominal Voltage Rating (kV) 12.47 Maximum Rated Voltage (kV) 17 Basic Impulse Level (kV) 110 Mounting Position Vertical
DESIGNATION FW1A
Approximate Mounting Height
(FT) 18’-0”
Phase Spacing (FT) 5’-0” Insulator Technical Reference No. 205
Fuse Symmetrical Interrupting Rating (RMS Amps) 12,500
Approximate Fuse E Rating* 7E
*Exact E rating will be furnished after the Contractor has submitted the time current curves of proposed fuse units.
b. Fuse Units: Each fuse disconnecting switch shall be furnished complete with one (1) fuse unit and one (1) spare fuse unit. Each fuse unit shall be of a type that can be refused readily in the field.
c. Switch-Operating Hook and Fuse Remover: Furnish 15-foot combination switch-operating hook and fuse remover.
5. Bidding Schedule items “Current transformer, 115-kV, single-phase” includes providing the current transformers and associated support structures.
The current transformers shall be 60 Hz, single-phase, outdoor, wound type in accordance with WAPA ES 6.2 Equipment Specifications, ANSI C 57.13, and the following specific requirements:
DESIGNATION QY1A1,QY1A2,QY1A3
Nominal System Voltage (kV) 115
Maximum Voltage Rating (kV) 123
Basic Impulse Level (kV) 550
Primary to Secondary Ratios 50:5A
Accuracy/Burden 0.15B1.8
Accuracy Range 1% to 200% Irated
Rating Factor 2.0
a. Seismic Qualification: Each current transformer and its associated support structure shall be qualified for the moderate seismic qualification level according to the requirements of IEEE Standard 693-2005 and shall have a seismic identification plate attached. Time history shake-table testing is required for the moderate seismic qualification level and seismic qualification reports shall be submitted in accordance with Standard 9.
6. Bidding Schedule items “Coupling capacitor voltage transformer (CCVT), 115-kV, single-phase” includes providing coupling capacitor voltage transformers in accordance with WAPA ES 6.3 equipment standard and associated support structures.
DESIGNATION VY1A1, VY1A2, VY1A3
Nominal System Voltage (kV) 115 Maximum System Voltage (kV) 123
Basic Impulse Insulation Level (kV) 550
Performance Reference Voltage (kV) 69
Primary to Secondary Ratios 600/1000:1 600/1000:1
ANSI Accuracy Rating 0.3% at W,X,Y,Z and ZZ
Thermal Burden Rating 400 VA at 55°C rise
Mounting Base
a. Seismic Qualification: Each coupling capacitor voltage transformer and its associated support structure shall be qualified for the moderate seismic qualification level according to the requirements of IEEE Standard 693-2005 and shall have a seismic identification plate attached. Time history shake-table testing is required for the moderate seismic qualification level and seismic qualification reports shall be submitted in accordance with Standard 9.
7. Bidding Schedule item “Station service transformer, 7.2/12.47-kV, 75-kVA” includes providing station service transformer in accordance with WAPA ES 2.1 equipment standard:
DESIGNATION KW1A
Type Pad mounted, single-phase, 60 Hz, outdoor, self-cooled, oil filled, dead front
Voltage Rating 7.2/12.47-kV – 240/120 V
Capacity (kVA) 75 Number of High-Voltage Bushing Wells 2
Number of Low-Voltage Bushings with NEMA Pads 3
Low-Voltage BIL (kV) 30
High-Voltage BIL (kV) 95
8. Bidding Schedule item “1/0 AWG, 15-kV, insulated copper cable” includes providing 1/0 AWG, 15-kV, insulated copper power cable type MV-105, 133 percent insulation level as shown on the Drawings. Cables shall run between FW1A and KW1A as shown on drawings.
Cable runs are 1 phase.
9. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material, and services required to complete the following substation installations as shown on the Drawings:
a. Substation Grounding System: Complete and test the substation grounding system.
Unless otherwise specified on Drawings, splices, connections, and other fittings shall be compression type (DMC Power’s Swage or equal). Due to the ongoing copper theft problems, all new exposed ground wire shall be copper clad steel. NOTE: That the included drawings and standards have not been revised to show this new requirement.
b. Electrical Conduit System: Electrical conduit system including embedded and exposed conduit shall be as shown on Drawing 31 1006. All conduits shall have sealing compound installed at both ends.
c. Outdoor Bus System: Outdoor strain and jumper buses, rigid buses, and overhead ground wires. Unless otherwise specified on the Drawings, splices, elbows, pad type terminal connectors, and other fittings used on rigid or cable buses – shall be compression type (DMC Power’s Bus and Cable Connectors and Swage System or equal). Post insulators for new structures shall use industry standard 3-, 5-, or 7-inch base cap bolt circles in lieu of WAPA Standard 9.3.1.1.3.2 and Drawing 31 1081. Replacement insulators shall match existing bolt circles. Insulators shall be ANSI 70 gray.
d. Insulated Conductors: Insulated conductors and cables except 5/c and 12/c No. 10 AWG control cables which are covered under separate bid item.
e. Terminal Boxes: Terminal boxes’ internal components arrangements shown on Drawings 31 1085 and 31 1086 are typical and the Contractor shall provide internal components for Option 1 Type A, F, and J terminal box configuration. Actual internal arrangements will be determined by the COR.
f. Providing gas cart receptacles with switched enclosure similar to Hubbell Switched Twist-Lock enclosure, catalog number SETL3 with NEMA L10-30R locking receptacle, 30 amp, 3-pole, 125/250 V, 3-wire without ground.
g. Phase Identification Signs (31 1000):
(1) One (1) on each phase at both ends of main and transfer buses, at each high voltage circuit terminating structure, and on each phase of an instrument transformer or single-phase transformer:
(a) Phase A – 5 required.
(b) Phase B – 5 required.
(c) Phase C – 5 required.
h. Equipment Identification Signs (31 1000) – Total required – 19. Sign material shall adhere to Division 13. Lettering on the signs shall be as follows:
(1) POUDRE VALLEY REA LINE
PD 125
DISC SW YW1A 12.47-KV
(2) POUDRE VALLEY REA LINE
PD 123
DISC SW YW1B 12.47-KV
(3) PCB 124 BYPASS
PD 129
DISC SW XW1A 12.47-KV
(4) POUDRE VALLEY REA LINE
PD 124
PCB JW1A
(5) STATION SERVICE
FW1A
FUSE DISC 12.47-KV
(6) STATION SERVICE
KW1A
TRANSFORMER
(7) TRANSFORMER
KY1A
(8) TRANSFORMER BUS
QY1A1
CURRENT XFMR 115-KV
(9) TRANSFORMER BUS
QY1A2
CURRENT XFMR 115-KV
(10) TRANSFORMER BUS
QY1A3
CURRENT XFMR 115-KV
(11) TERMINAL BOX CT
EY1B
SHORTING BLOCKS
(12) MAIN BUS
VY1A1
CCVT 115-KV
(13) MAIN BUS
VY1A2
CCVT 115-KV
(14) MAIN BUS
VY1A3
CCVT 115-KV
(15) TERMINAL BOX CCVT
EY1A
SECONDARY FUSES
(16) TRANSFORMER BUS
PD 162
PCB JY1A
(17) TRANSFORMER BUS
PD 161
DISC SW YY1A 115-KV
(18) TRANSFORMER BUS
PD 163
DISC SW WY1A 115-KV
(19) TRANSFORMER BUS
PD 165
DISC SW YY1B 115-KV
10. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable”, “Furnishing 12/c No. 10 AWG control cable”, “Furnishing 25/c No. 18 AWG control cable”, and “Furnishing 3/c No. 18 AWG control cable” include furnishing 5/c No. 10, 12/c No. 10, 25/c No. 18, and 3/c No. 18 AWG control cable, respectively.
11. Bidding Schedule items “Installing 5/c No. 10 AWG control cable”, “Installing 12/c No. 10 AWG control cable”, “Installing 25/c No. 18 AWG control cable”, and “Installing 3/c No. 18 AWG control cable” include installing 5/c No. 10, 12/c No. 10, 25/c No. 18, and 3/c No. 18 AWG control cable, respectively. The Contractor shall install the cables in the duct bank and cable trench between the outdoor equipment and the control panels according to Drawings PD T600, PD 0010, and PD 4004. All control cables shall be labeled according to Drawing PD T600 and Standard 9 – Substation Electrical, paragraph 9.2.3.4.(10), shall reach the farthest point in the control room, and shall be left coiled in the trench. At the outdoor equipment cabinets, the control cables shall reach the farthest point in the cabinet. The Contractor shall terminate at the outdoor equipment only.
12. Bidding Schedule item “Duplex switchboard section (1) CHA2 (Government-furnished)” includes furnishing material not furnished by Western and performing work required to pick up, load, transport, unload, and install the Government-furnished duplex switchboard section CHA2 in the Service Building in the location shown on Drawing PD 4004. The Contractor shall pick up the switchboard from Western’s Loveland warehouse located at 5555 East Crossroads Blvd., Loveland, CO 80538-8986. The Contractor shall remove the existing end trim from existing switchboard section, CHA1, install the new switchboard section, CHA2, and reinstall the end trim.
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. DESCRIPTION:
1. Environmental Quality Protection. The Bidding Schedule does not contain separate items for the following. Include these items in the applicable Bidding Schedule items.
a. Contractor Furnished Data (See Section 13.1 of Standard).
b. Environmental Requirements (See Section 13.2 of Standard).
c. Landscape preservation (See Section 13.3 of Standard).
d. Preservation of Cultural Resources (See Section 13.4 of Standard).
e. Noxious Weed Control (See Section 13.5 of Standard).
f. Recycled Material Quantities (See Section 13.6 of Standard).
g. Use of Products Containing Recovered Materials (See Section 13.7 of Standard).
h. Disposal of Waste Material (See Section 13.8 of Standard).
i. Contractor's Liability for Regulated Material Incidents (See Section 13.9 of Standard).
j. Pollutant Spill Prevention, Notification, and Cleanup (See Section 13.10 of Standard).
k. Pesticides (See Section 13.11 of Standard).
l. Treated Wood Poles and Members Recycling or Disposal (See Section 13.12 of Standard).
m. Prevention of Air Pollution (See Section 13.13 of Standard).
n. Handling and Management of Asbestos Containing Material (See Section 13.14 of Standard).
o. Materials with Lead-based Paint (See Section 13.15 of Standard).
p. Prevention of Water Pollution (See Section 13.16 of Standard).
q. Testing, Draining, Removal, and Disposal of Oil-filled Electrical Equipment (See Section
13.17 of Standard).
r. Removal of Oil-contaminated Materials (See Section 13.18 of Standard).
2. Bidding Schedule item “Disposing of oil-filled electrical equipment” includes the following:
a. Sample, test, drain, remove, transport, and dispose of the following oil-filled equipment:
(1) Transformers KY1A, KW1A, and power circuit breaker JY1A. List equipment name and designations. Coordinate with the electrical engineer for electrical designations and to make sure they are not including this cost under one of electrical substation bid items.
b. Sample and test the oil of each equipment designation for PCB content, using one of the laboratories listed below:
c. Use one of the following companies for transportation, disposal, recycling, or reprocessing of the oil and/or oil-filled electrical equipment depending on the PCB content:
(1) For oil containing 2 parts per million (ppm) or less of PCBs:
(2) For oil containing more than 2 ppm of PCBs but less than 50 ppm:
(3) For oil containing 50 ppm or more of PCBs:
3. Bidding Schedule item “Removal of oil-contaminated material” includes the following:
a. Removing material as shown on drawing PD 0001, page.
b. Sample and test the oil-contaminated material, using one of the audited and approved laboratories listed below:
c. Use one of the following companies audited and approved by Western for transporting and disposing of the oil-contaminated material depending on the PCB content:
(1) For oil containing 2 parts per million (ppm) or less of PCBs:
(2) For oil containing more than 2 ppm of PCBs:
d. Western will be responsible for the transportation and disposal of PCB-contaminated soil and debris.
Message from the Administrator At Western, we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to Western. In performing work for Western, all contractors must make the right decisions to ensure that the work environment is as safe as possible.
Our safety program is based on four points:
Safety procedures or common sense must be applied by each Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.
Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.
Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.
Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.
By integrating these principles into every task we take, together we can ensure Western is a safe place to work.
Mark A. Gabriel Administrator
| DIVISION 1 – GENERAL REQUIREMENTS |
| A. CONTRACT REQUIREMENT: |
| B. DESCRIPTION OF WORK: |
| C. DESCRIPTION OF BID ITEM: |
| 1. Bidding Schedule item “Mobilization and preparatory work” includes the following: |
| D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: |
| 1. COMMENCEMENT AND COMPLETION: Begin work within 10-calendar days after date of receipt of Notice to Proceed, and complete all work within 365-calendar days from the date of receipt of such notice. |
| 2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 21-calendar days for review of drawings or data submitted for approval. |
| 3. OUTAGE RESTRICTIONS: In addition to the restrictions listed in the standard specifications, the following outage restrictions shall apply: |
| Outages for all transmission line sections will be issued between February 1, 2015 and May 30, 2015 only. All work requiring any transmission line outage shall be completed during this time. |
| 4. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized to carry the maximum available fault current in accordance with the Standard 1 – General Requirements, Section 1.4 “Safety and H... |
| E. CONSTRUCTION PROGRAM: |
| 1. SUBMITTAL TIME: Submit a Construction Program to the COR within 30-calendar days after date of Notice to Proceed. |
| F. RIGHTS-OF-WAY: |
| 1. GENERAL: Transmission lines right-of-way is 125-feet wide for the Currecanti (CCI) – MID 230-kV transmission line and 75-feet wide for the BPT – SD and BPT – GS 115-kV transmission lines, except at locations where guys and anchors require addition... |
| 2. ACCESS EASEMENTS: Western has acquired access easements from existing public roads to the transmission line and some off right-of-way access along the transmission line. This off right-of-way access route is to provide access to the transmission ... |
| 3. WORK ON THE RIGHT-OF-WAY: |
| G. GEOLOGIC INVESTIGATIONS: |
| H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES: |
| I. WATER FOR CONSTRUCTION PURPOSES: |
| J. CONTRACTOR COMMUNICATIONS: |
| K. EXPLOSIVES AND BLASTING: |
| L. SUBMITTALS: |
| 1. GENERAL: The Contractor shall furnish submittals as specified in Construction Standards and Project Specifications. |
| 2. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph. |
| 3. ADDRESSES: The Contractor shall transmit submittals to the following addresses: |
| DIVISION 2 – SITEWORK |
| A. DESCRIPTION OF BID ITEMS: |
| 1. Bidding Schedule item “Removing existing transmission line” includes the following: |
| 2. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items. |
| DIVISION 4 – TRANSMISSION LINE LATTICE STRUCTURES |
| A. DESCRIPTION OF BID ITEM: |
| 1. Bidding Schedule item “Modifying steel structures” includes providing the following: |
| DIVISION 7 – WOOD POLE STRUCTURES |
| A. DESCRIPTION OF BID ITEM: |
| 1. Bidding Schedule item “Modifying wood structures” includes providing the following: |
| DIVISION 9 – SUBSTATION – ELECTRICAL |
| A. GENERAL: Electrical equipment and material shall be as specified in Western’s Electrical Equipment Standards (WAPA ES), as shown on project drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal specifications an... |
| 1. Bidding Schedule items shall be furnished by the Contractor and shall include the following: |
| 2. Installation and painting of electrical equipment and material shall be provided in accordance with Standards 9 and 12 respectively. |
| B. DESCRIPTION OF BID ITEM: |
| 1. Bidding Schedule item “Furnish and install fiber optics” includes determining lengths, furnishing and installing conduit, fiber optic distribution cable (FODC), inner-duct, and patch panels, terminating the FODC and connecting it to the installed p... |
| 1) CAUTION. |
| 2) BURIED COMMUNICATION CABLE. |
| 3) WESTERN AREA POWER ADMINISTRATION. |
| 1) For BPT: |
| FIBER OPTIC |
| SPLICE ENCLOSURE |
| OY6A |
| FIBER OPTIC |
| SPLICE ENCLOSURE |
| OY5A |
| 2) For GS: |
| FIBER OPTIC |
| SPLICE ENCLOSURE |
| OY6A |
| 3) For MID: |
| FIBER OPTIC |
| SPLICE ENCLOSURE |
| OV2A |
| 4) For CCW: |
| FIBER OPTIC |
| SPLICE ENCLOSURE |
| OV1A |
| FIBER OPTIC |
| SPLICE ENCLOSURE |
| OV3A |
| 5) For PON: |
| DIVISION 10 – TRANSMISSION LINE ELECTRICAL |
| A. DESCRIPTION OF BID ITEMS: |
| 1. Bidding Schedule items for “Furnishing and installing optical overhead ground wire assemblies, complete with suspension clamp or bolted deadend, suitable for 0.465-inch and 0.472-inch diameter optical overhead ground wire with armor rods” includes ... |
| 2. Bidding Schedule item “Furnish and install 0.465-inch diameter, 48-fiber optical overhead ground wire” includes furnishing and stringing, sagging, clipping in and deadending the OPGW and furnishing and installing material to complete the optical ov... |
| 3. Bidding Schedule item “Furnish and install 0.472-inch diameter, 48-fiber optical overhead ground wire” includes furnishing and stringing, sagging, clipping in, and deadending the OPGW and furnishing and installing material to complete the OPGW inst... |
| 4. Bidding Schedule item “Furnish and install optical splice enclosures” includes determining the number and location of optical splice enclosures along the transmission line based on reel lengths and set-ups, furnishing material, and performing work ... |
| 5. Bidding Schedule item “Furnish and install spiral-type vibration dampers for 0.465-inch and 0.472-inch diameter optical overhead ground wire” includes determining the number of vibration dampers needed, furnishing material, and performing all work,... |
| 6. Bidding Schedule item for “Furnishing and installing line marking devices” includes furnishing and installing markers on the overhead ground wires. The line marking devices shall be installed in the spans ahead and back of Structure numbers 277, 2... |
| 7. Bidding Schedule item “Spare parts” includes furnishing the following material: |
| DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION |
| A. DESCRIPTION: |
| 1. The Bidding Schedule does not contain separate items for Environmental Quality Protection. Include this work in applicable Bidding Schedule items. |
| B. SPECIAL REQUIREMENTS: |
| 1. The following requirements must be observed for the Gering-Sidney and Midway-Poncha OPGW Installation project. |
| Attachment A 12 2 14.pdf |
| DIVISION 1 – GENERAL REQUIREMENTS |
| A. CONTRACT REQUIREMENT: |
| B. DESCRIPTION OF WORK: |
| C. DESCRIPTION OF BID ITEM: |
| 1. Bidding Schedule item “Mobilization and preparatory work” includes the following: |
| D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: |
| 1. COMMENCEMENT AND COMPLETION: Begin work within 30-calendar days after date of receipt of Notice to Proceed, and complete all work within 400-calendar days from date of receipt of such notice. |
| 2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 20-calendar days for review of drawings or data submitted for approval. |
| 3. OUTAGE AND CONSTRUCTION SCHEDULE RESTRICTIONS: In addition to the restrictions listed in the standard specifications, the following outage and construction schedule restrictions shall apply: |
| 4. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the f... |
| E. CONSTRUCTION PROGRAM: |
| 1. SUBMITTAL TIME: Submit a construction program to the COR within 45-calendar days after date of Notice to Proceed. |
| 2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph. |
| F. MATERIAL: Furnish all material for completing the work. |
| G. RIGHTS-OF-WAY: |
| 1. GENERAL: Typical transmission line right-of-way for 115-kV transmission lines is 75-feet-wide. Western does not represent that the Contractor can gain access to every structure site or travel continuously along the transmission line. Orient cons... |
| 2. ACCESS EASEMENTS: Western has acquired access easements from existing public roads to the transmission line and some off right-of-way access along the transmission line. This off right-of-way access route is to provide access to the transmission ... |
| 3. WORK ON THE RIGHT-OF-WAY: |
| H. GEOLOGIC INVESTIGATIONS: |
| I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES: |
| J. WATER FOR CONSTRUCTION PURPOSES: |
| K. EXPLOSIVES AND BLASTING: |
| L. SUBMITTALS: |
| 1. GENERAL: The Contractor shall furnish submittals as specified in the construction standards and the project specifications. |
| 2. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph. |
| 3. ADDRESSES: The Contractor shall transmit submittals to the following addresses: |
| DIVISION 2 – SITEWORK |
| A. DESCRIPTION OF BID ITEMS: |
| 1. Bidding Schedule item “Removing existing single-circuit 115-kV wood transmission line structure 12/7” includes the following: |
| 2. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items. |
| DIVISION 3 – CONCRETE |
| A. GENERAL: |
| 1. MATERIAL: |
| 2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: Perform test for each source used. |
| B. DESCRIPTION OF BID ITEMS: |
| 1. Bidding Schedule item “Concrete foundations” includes the following: |
| DIVISION 4 – SUBSTATION METALWORK |
| A. GENERAL: |
| 1. GOVERNMENT-FURNISHED DRAWINGS: Existing shop drawings for steel structures are not available. |
| 2. MEASUREMENT: Measurement for quantities for Bidding Schedule item “Steel structures, welded (galvanized)” will be made on the basis of weights calculated in accordance with LRFD, “AISC Code of Standard Practice for Steel Buildings and Bridges”, ex... |
| B. DESCRIPTION OF BID ITEMS: |