This solicitation requests proposals for the manufacture of aluminum shipping and storage containers. The Air Force Packaging Technology and Engineering Facility is seeking a firm-fixed price contract for the production of CNU-766/E and CNU-776/E containers from March 2022 to March 2025, including a 12-month base period and two 12-month option periods. The Statement of Work provides production and delivery schedules for 120 CNU-766/E containers and 85 CNU-776/E containers over the three-year period to the specified delivery locations. This is a small business set-aside solicitation issued by the Department of the Air Force Materiel Command Lifecycle Management Center under NAICS code 332439. Questions are due by 10 February 2022 and funds are not presently available, though no award will be made until funding is in place.

View the file

Other files

File Type Posted
Instructions to Offerors and Evaluation Criteria.pdf PDF
DL20191800_CUI.pdf PDF
SP20171300_RevB 2-1-22_CUI.pdf PDF
DL20191700_CUI.pdf PDF
DL20171300_CUI.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR

SHIPPING AND STORAGE CONTAINER, MISCELLANEOUS EQUIPMENT,

CNU-766/E & CNU-776/E

7 JANUARY 2021

1. INTRODUCTION. The Air Force Packaging Technology and Engineering Facility

(AFPTEF) has engineering authority for reusable, long-term shipping and storage containers designed for various Project Cobra assets. The containers will provide physical and environmental protection during worldwide transportation and storage for the various assets.

2. SCOPE. The contractor will be required to:

2.1. Manufacture. The contractor is to manufacture the CNU-766/E and CNU-776/E shipping and storage containers in accordance with:

2.1.1. Prime Item Product Fabrication Specification. SP20171300 with all associated specifications, standards, and documents.

2.1.2. Drawing Package. DL20191700 for CNU-766/E and DL20191800 for CNU-776/E with all associated drawings, parts lists, and documents, respectively.

2.2. Interface. The contractor must provide a point of contact, name, telephone number, email address, and cell phone number if applicable, for interface with AFPTEF. The AFPTEF point of contact will be the program manager. This will insure coordination of actions and requirements shall be accomplished in a timely and productive manner.

3. TASKS.

3.1. General tasks. The contractor shall have in place a management system to provide supplies and services required to fabricate, evaluate, test, produce, and deliver containers in accordance with Prime Item Product Fabrication Specification SP20171300.

3.1.1. First article testing and inspection. The contractor shall prepare for and host the first article testing and inspection meeting. Three complete sets of piece parts and one complete container of each type shall be required for first article testing and inspection to validate the adequacy of the container manufacturing processes and procedures. The contractor shall have all parts laid out in an area of sufficient size to perform the required inspection and measurement. The contractor shall provide measuring instruments sufficient to verify drawing tolerance compliance. These instruments shall be calibrated for accuracy. The contractor shall provide their internal inspection records and material certifications for inspection and comparison of these documents with the items they describe. The contractor shall ensure quality assurance personnel are available during First Article testing and inspection meeting.

3.1.2. Request for Deviation/Waiver and Engineering Change Proposal. No design changes or modifications shall be made without prior approval from the AFPTEF program manager. Proposed changes which effect cost or schedule require formal approval by the government and shall be submitted through the contracting officer. The contractor's request shall state the nature and reasons for the change and the effect of the change on cost and delivery. Engineering change proposals, which have no effect on cost or schedule, may be approved by the AFPTEF program manager/project engineer, and routed through the contracting office.

3.1.3. First article acceptance and inspection. AFPTEF personnel will perform preliminary

(first article) inspection and acceptance of the pre-production units for conformance to the specification, drawings, and contractor inspection records. The contractor shall notify AFPTEF 15 days prior to the date they propose for the inspection, so schedule and travel arrangements may be made.

3.1.4. UN performance oriented packaging (POP) tests. The contractor shall supply a total of two CNU-766/E and two CNU-776/E to AFPTEF for performance testing (one of each in the Base Year and Option Year 2) IAW SP20171300. AFPTEF shall prepare a written report at the completion of testing. These containers will not be returned after testing.

3.1.5. Acceptance and inspection. The contractor will be notified in writing by the

Contracting Officer within 5 days after POP testing acceptance. In the base year, this will signal the start of production. In option year 2, this will signal that the first production lots may be delivered. The Contracting Officer appointed official will perform final inspection and acceptance of production units at the contractor’s facility.

3.1.6. Rejection of containers. Containers failing to pass the acceptance tests, as outlined in the container fabrication specification (SP20171300), may be modified by the contractor and re-tested or another container may be fabricated.

3.1.7. Management and technical meetings. The government or the contractor may call a technical interchange meeting. The location of the meeting will be determined prior to the meeting date or may be accomplished remotely. The contractor shall notify the government 15 days prior to the date they propose for the meeting, so schedule and travel arrangements (if necessary) may be made.

3.2. Detailed Tasks. The contractor shall comply with the following:

3.2.1. Quality assurance. The contractor shall have a quality control plan/system (e.g. IAW

SAE-AS9100 or ISO 9001) in place for ensuring that the containers meet all specifications and drawing requirements. The contractor's quality assurance program shall be approved by the government quality assurance representative.

3.2.2. Minutes. AFPTEF shall provide minutes of all meetings, formal reviews, and inspections held with the contractor.

3.2.3. Program status reporting. If the contractor experiences any issue that will result in a quality of product and/or a delivery schedule slippage, the contractor shall provide the AFPTEF program manager with a report detailing the problem, cause, and recovery actions.

3.3. Government Furnished Property (GFP).

3.3.1. Acceptance of GFP. Generic asset representative items will be sent to the contractors’ facility for a FA fit check. The contractor is responsible for ensuring the items are not lost or damaged during this time frame.

3.3.2. Disposition of GFP. The contractor will ship the asset representative items to the specified address (see section 4.4) after acceptance of FA units.

4. DELIVERY.

4.1. Container First Article/Production Delivery schedule after contract award.

4.1.1. First Article Test and Inspection (Pre-production): Shall be accomplished no later than

12 weeks after contract award. The pre-production CNU-766/E and CNU-776/E will be shipped to AFPTEF within 1 week of First Article Testing (FAT) completion for POP testing.

4.1.2. Performance Oriented Packaging Test (Production Sample): Shall be delivered to AFPTEF in option year (OY) 2 no later than 13 weeks after contract award.

4.1.3. Production. After written authorization to begin production, final delivery shall meet the delivery schedule below.

BY: Delivery (Weeks after FAT/POP Accept.) 14 26 39 52 Total

CNU-766/E 8 8 8 5 29

Delivery West Location 8 8 8 5 29

CNU-776/E 8 8 10 26

Delivery West Location 8 8 10 26

OY1: Delivery (Weeks after contract award)

13 26 39 52 Total

CNU-766/E 9 8 8 8 33

Delivery West Location 9 8 8 8 33

CNU-776/E 9 9 8 8 34

Delivery West Location 9 9 8 8 34

OY2: Delivery (Weeks after POP Acceptance) 1 13 26 39 Total

CNU-766/E 23 23 22 21 89

Delivery West Location 23 23 22 21 89

CNU-776/E 13 13 13 12 51

Delivery West Location 13 13 13 12 51

Accelerated deliveries are possible with the approval of the AFPTEF program manager and shall be routed through the contracting officer.

4.2. Preservation and packing. Containers must be stored in an indoor area prior to delivery.

Containers shall be palletized and shrink wrapped for delivery. All conveyances shall be loaded, blocked and braced to ensure containers are protected during typical handling and transport procedures. It is recommended that the humidity indicator litmus paper (if contract or purchase order specifies replacement of drum plugs with humidity indicators) not be placed in the container until ready for delivery.

4.3. Container Shipping Address. All containers shall be shipped to the following West address as stipulated:

WEST ADDRESS:

7538 5TH STREET

BLDG. 850 BAY E

HILL AFB UT 84056-5706

ATTN: KEITH JACKSON or TIM FASIG (801) 775-4049

4.4. GFP Shipping Address. All GFP shall be shipped to the following address as stipulated:

AFPTEF

5215 THURLOW STREET

SUITE 5, BLDG 70, AREA A

WPAFB, OH 45433-5540

ATTN: LOGAN GUMUCIO (937) 257-7166

STATEMENT OF WORK FOR