CN-770000-22282-NTP2.0.pdf
PDF 95 KB Posted
- Contract number
- 22282
- Issued by
- Florida
About this file
This document is a Notice to Proceed with Construction issued by the Florida Wildlife Commission (FWC) to Boromei Construction, located in Okeechobee, Florida. The notice pertains to FWC Contract #22282 7207.008 for the Hilochee Utilities and Office replacement project. The original Notice to Proceed was dated January 29, 2024, but was subsequently revised due to extraordinary delays in county permitting.
The construction project involves replacing utilities and offices, with the revised timeline now setting the Notice to Proceed date as August 26, 2024. The project is scheduled for 185 calendar days of construction, with Substantial Completion set for February 27, 2025, and Final Completion to occur 15 calendar days later on March 14, 2025. The contract is managed by Michael Cottingham from FWC, and despite best efforts from the contractor, FWC, and input from the state fire marshal, the county delayed project approval until the revised date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-19158-TA4.pdf | ||
| CN-770000-22282-CO1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice to Proceed with Construction January 29, 2024
Boromei Construction 420B NW 3rd Street Okeechobee, Fla 34972
RE: FWC Contract #22282 7207.008 Hilochee Utilities and Office replacement
Notice to Proceed with Construction
Dear Mr. Boromei:
Please consider this as your formal NOTICE TO PROCEED WITH CONSTRUCTION. You may now mobilize on site and proceed with construction subject to the conditions of the contract.
The official commencement date for this project will be the date of this Notice to Proceed (NTP) and subsequent Substantial Completion and Final Completion dates will be as established in the contract documents.
Notice to Proceed-Mobilize and begin Construction 01/29/24 Substantial Completion –185 calendar days 08/01/24
Final Completion –15 calendar days after substantial completion 08/16/24
This NTP has been revised. This is due to an extraordinary delay in permitting with the county. Despite the contractors best efforts, FWC support, and input from the state fire marshal, the county would not approve this project to begin work until 08/26/24.
These are the new dates:
Notice to Proceed-Mobilize and begin Construction 08/26/24 Substantial Completion –185 calendar days 02/27/25 Final Completion –15 calendar days after substantial completion 03/14/25