CN-770000-22282-CO1.pdf
PDF 2 MB Posted
- Contract number
- 22282
- Issued by
- Florida
About this file
This document is a Construction Contract Change Order (CO) between the Florida Fish and Wildlife Conservation Commission (Owner) and Boromei Construction, Inc. (Contractor) for the Hilochee Pole Barn Utilities project in Lake County, Florida. The change order is associated with FWC Contract No. 22282 and Solicitation Number FWC 22/23-93C.
The change order addresses fire protection permitting and additional valve requirements, increasing the contract amount by $14,442.33 to meet NFPA 1142 building code requirements. The modification includes costs for Southern Fire Protection to provide permitting, installation, and inspections for a 9500-gallon water tank, as well as furnishing and installing a solenoid valve. The change order extends the project duration by 30 days, with the original substantial completion date of 2.27.2025 now adjusted to 3.29.2025. The total contract sum increases from $618,110.00 to $632,552.33, with all work to be completed in one phase during regular hours and in accordance with applicable NFPA and local building standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-19158-TA4.pdf | ||
| CN-770000-22282-NTP2.0.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Philip T. Stone
Chief Operating Officer
1/28/2025
P.T. Stone Digitally signed by P.T.
Stone Date: 2025.01.28 16:19:53 -05'00'
File details come from the government source that posted it. Updated .