This document is a Task Work Order (TWO) #1 for professional services issued by the Florida Department of Transportation (FDOT) to Stantec Consulting Services, Inc., with two subconsultants: AIM Engineering & Surveying, Inc. and Kisinger-Campo & Associates, Inc. The contract (CAX36) is for Statewide Environmental Review and Analysis Consultant Support, procured through a Request for Proposal method, with a total contract budgetary ceiling of $5,000,000.00.
The Task Work Order authorizes Stantec to provide program support services for the Office of Environmental Management, including tasks such as reviewing federal and state laws, assisting with procedure development, supporting strategic initiatives, conducting technical document reviews, managing data and file repositories, and providing project coordination and management. The total compensation for this Task Work Order is $293,818.78, broken down as $269,648.73 for Stantec, $14,038.50 for AIM Engineering, and $10,131.55 for Kisinger-Campo & Associates. The contract period runs from 06/04/2025 to 06/03/2030, with monthly invoicing based on staff hours and job classifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAX36-00010000.pdf | ||
| CN-550000-CAX36.pdf | ||
| CN-550000-CAX36-W0020000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
6/3/2030
*Limiting or Estimating/Budgeted Amount.
Distribution:
Consultant Acceptance:
Signature
PROCUREMENT, CONSULTANT, FILE
Principal
$293,818.78
$0.00
(name) (title)
Nicole Carter
$293,818.78
Total authorizations to date (including this one):
Departmental Approval:
$269,648.73 Estimate
AIM ENGR., INC,
$14,038.50 Estimate
Program Support
Stantec Consulting Services, Inc.
901 Ponce De Leon Blvd. Suite 900, Coral Gables, FL 33134
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$293,818.78
(LA4) Units worked at loaded billing rates in Table 6
(LA4) Units worked at loaded billing rates in Table 6
Page 1 Total
Page 2 thru 6 Subtotal
Total
(LA4) Units worked at loaded billing rates in Table 6KCA
STANTEC
Estimate$10,131.55
$293,818.78
(name) (title) Signature
Katasha Cornwell Contract Manager
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
Task Work Order No.:
Contract No.: Payment FM No.:
CAX36 407085-1-32-04
Docusign Envelope ID: D1642ED6-5B50-42CB-B72E-CC4FD673B658
07/07/2025 | 1:18 PM EDT
Contract CAX36: Task Work Order #1 Program Support
ATTACHMENT A
SCOPE OF SERVICES
Office of Environmental Management (OEM)
Department Project Manager: Katasha Cornwell Stantec Contract Manager: Nicole Carter Stantec Task Manager: Ted Devens Project Description: Statewide Environmental Review and Analysis Support Contract: CAX36
FIN#: 407085-1-32-04
Task Work Order #1: Program Support
The purpose of this Task Work Order (TWO) is for the Consultant to provide professional services that support Office of Environmental Management Program Needs and Production efforts, including normal contract and data management activities related to Contract CAX36 and its subordinate task work orders. As directed by OEM – the Consultant will also provide responsive support for unforeseen or immediate needs that arise. Tasks are assigned by the Department’s Project Manager, or designee, according to program priorities as funding allows.
Task 1: Program Support
The Consultant will provide responsive support to overall contract management and production activities, which can include assistance with statewide initiatives, process and procedure development, concept development, and project delivery support. The services to be provided may include activities such as:
Research, review, and preparation of comments and/or recommendations of new or proposed federal and state laws, rules, and regulations affecting programs and projects, and provide technical support when needed. Assist OEM to identify potential challenges and opportunities.
Assist OEM to update, revise or develop Department related procedures, guidelines, manuals, or other documents to support project development and project documentation.
Assist with initial brainstorming and innovations for new process concepts. Submit draft and final versions, including responses to comments, for newly developed deliverables.
Provide responsive support to OEM when establishing strategic visions or concepts. Assist with research, develop ideas, assess risks, and evaluate other decision-making parameters.
Collaborate with OEM staff to "define the problem" and consider alternative approaches.
Conduct coordination meetings to confer on recommended approaches. As warranted, convene Stantec’s “Innovation Team” which consists of senior discipline leaders and subject-matter-experts - to consider the issues at hand, identify considerations, and then provide recommendations or guidance.
Support OEM with assessment, preparation, and modification of existing Memorandums of Understanding (MOU), Memorandums of Agreement (MOA), Programmatic Agreements, and other documents that signify understandings or agreement.
Assist OEM with conducting self-assessment reviews and/or preparing for NEPA Assignment monitoring and auditing events.
Deliverables
Review comments and/or recommendations of federal and state laws, rules and regulations affecting programs and projects. Comments will be provided within the PDF, unless otherwise requested.
Provide comments and/or recommendations on existing or proposed Department procedures, guidelines, manuals, or other documents as requested. Comments will be provided within the PDF, unless otherwise requested.
Recommendations and risk analyses relative to new strategic visions or initiatives in requested format (i.e. memo, report and/or word document, pdf).
Draft and final versions, including progressive electronic “tracked changes” to ensure responses to comments for each iteration of review, for newly developed items under this TWO (i.e. procedures, guidelines, manuals, or other documents or statewide initiatives).
Meeting notes will be provided for coordination meetings.
Task 2: Production Support
Participate in the technical and procedural review of technical reports/analyses or documents such as: Categorical Exclusions, Environmental Assessments, Finding of No Significant Impacts, Draft and Final Environmental Impact Statement, Alternative Corridor Evaluation Reports (ACER) and Methodology Memorandums and other planning documents, as well as Re-evaluations and associated environmental and engineering technical reports. Prepare a list of review comments and/or recommendations for each document. Provide supplemental environmental or engineering support as directed.
Support internal FDOT and external process development initiatives and programmatic support, as well as organization or systems-management tasks deemed necessary by OEM.
Assist OEM to develop a working Business Operations Management (BOM) dashboard with varying levels of controlled access, which tracks multiple tasks, reviews and deliverables for
OEM.
Schedule and monitor production work assigned under this Task Work Order and keep OEM advised of the status of individual assignments.
Provide support to develop Executive Briefings, FDOT presentations, industry forums and conferences, intra-office FDOT briefings and coordination, and District/FTE-level collaboration. Produce training materials. Prepare or facilitate Virtual Meetings, and Teleconferences with various FDOT and external participants (such as agencies, MPOs, and local governments) on various initiatives or topics.
Provide administrative support for such services as: document formats, consolidate and manage files, distribute files and products, develop graphics and handouts, create and send surveys, and receive/collate comments.
Assist OEM to identify, evaluate, and apply new technologies (such as Artificial Intelligence) which can streamline FDOT processes and/or enhance FDOT and consultant/subconsultant or contractor efficiency. Collaborate with OEM to consider alternative approaches.
Provide responsive support for unforeseen or immediate production needs that arise, and which have not been previously scoped in another Task Work Order.
Coordination meetings for any individual assignment as requested.
Assist OEM Administrators and Project Delivery Coordinators (PDCs) by providing Backup PDC support with activities including, but not limited to: track document reviews, technical reports, and planning & NEPA documents. review pre-screening activities, planning studies and Methodology Memorandums, environmental (e.g., NEPA) and other technical documents, and attend meetings as requested by OEM.
Deliverables
Review comments and/or recommendations for each document review. Comments will be provided within the PDF, unless otherwise requested.
Process development documents, manual updates, flowcharts, handbooks, and other guidance materials as appropriate to the task.
BOM Dashboard with varying levels of controlled access – to track and manage multiple tasks, reviews, and deliverables for OEM – including internal actions, status reporting, and other defined needs.
Task production schedule updates, as appropriate.
Scheduling and polling services, agendas, handouts, and meeting notes. Training materials as requested, including PowerPoint slides and notes and Script, videos, and presentation support.
Administrative file management and delivery of final publishable documents
Research, reports, evaluations, examples, pilot studies or models of applied technologies.
Meeting notes for coordination meetings (for PDC support activities, additional meeting notes beyond those normally provided by others (e.g., Districts often provide meeting notes from monthly OEM coordination meetings) are not required).
Task 3: Data Management and Access
The Consultant will provide reliable electronic file management services:
Sharepoint Site – create, maintain and update a SharePoint central file repository for completed contract Deliverables for all Task Work Orders assigned under this contract and pre-final draft versions of the same. Provide updated access to specified FDOT personnel.
Perform periodic QC to ensure deliverables are saved appropriately.
Deliverables
OEM-accessible, SharePoint site that consolidates contract Deliverable files and pre-final Electronic “tracked” changes version of recommended chapter changes and other documents.
Task 4: Coordination
The Consultant will:
Prepare for, attend, and provide notes at monthly OEM Coordination meetings. Seek/obtain status from subcontractors, task managers, and supporting staff. Develop an updated Contract Status Report and provide meeting follow-up actions. Provide monthly contract financial tracking reports and trendline analysis.
Attend virtual or in-person meetings on OEM’s behalf as requested. This activity includes travel, setup, logistics, attendance and note preparation.
Deliverables
Scheduling, Virtual Meeting and Telecon setup, agendas, handouts, and meeting notes.
Task 5: Project Management and Quality Control
The Consultant will:
Conduct project management activities in support of overall contract management. This will include internal staff coordination, monthly progress reports, and appropriate schedule updates.
Coordinate and perform Quality Control and Quality Assurance reviews of work.
Deliverables
Monthly progress reports on activities performed in the previous 30 days.
Staffing
Consultant and Subconsultant staff classifications are authorized to work on this TWO, at the home rates identified in Table 6 of the contract. Fee estimates may not reflect all classifications. Should additional classifications not identified in the fee estimate be used, the Consultant shall not go over the total fee for the TWO.
Schedule, Resources and Compensation
The duration of this task work order will continue until 6/3/2030.
Compensation for the TWO authorization shall be the Maximum Limiting Amount Fee Method in accordance with the contract and is not to exceed $293,818.78, as shown in Attachment B (Fee
Estimate). Fees for the assigned tasks will be at the rates prescribed in the contract. Invoices will be submitted monthly for services performed and supported by progress reports, already received deliverables, and update meetings or calls, based upon staff hours and job classifications for staff hours worked on an activity/task.
Contract #: CAX36 OEM Contract Manager: Katasha Cornwell Consultant Name: Stantec Consultant Contract Manager: Nicole Carter Consultant Task Manager: Ted Devens Sub Consultant Name: AIM Engineering & Surveying, Inc.
Sub Consultant Task Manager: Brittany Bianco Sub Consultant Name: Kisinger-Campo & Associates, Inc.
Sub Consultant Task Manager: Nicole Selly
Date: June 2025
Prime Consultant (Stantec) TOTAL FEE $269,648.73
Sub Consultant (AIM Engr., Inc.) TOTAL FEE $14,038.50
Sub Consultant (KCA, Inc.) TOTAL FEE $10,131.55
TOTAL TASK WORK ORDER TOTAL FEE $293,818.78
ATTACHMENT B: STAFF HOUR AND FEE ESTIMATE
Task Work Order 1 - Program Support
Consultant Name: Stantec Consultant Contract Manager: Nicole Carter Consultant Task Manager: Ted Devens
TASK Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
$398.01 $299.20 $288.21 $290.43 $265.15 $209.71
Task 1 - Program Support $0.00 64.00 $19,148.80 64.00 $18,445.44 24.00 $6,970.32 16.00 $4,242.40 30.00 $6,291.30
Task 2 - Production Support $0.00 12.00 $3,590.40 12.00 $3,458.52 $0.00 14.00 $3,712.10 240.00 $50,330.40
Task 3 - Data Management and Access $0.00 $0.00 8.00 $2,305.68 $0.00 $0.00 $0.00
Task 4 - Coordination $0.00 70.00 $20,944.00 114.00 $32,855.94 $0.00 $0.00 $0.00
Task 5 - Project Management and Quality Control 4.00 $1,592.04 16.00 $4,787.20 16.00 $4,611.36 $0.00 $0.00 $0.00
TOTAL MAN-HOURS AND COST 4.00 $1,592.04 162.00 $48,470.40 214.00 $61,676.94 24.00 $6,970.32 30.00 $7,954.50 270.00 $56,621.70
(continued)
TASK Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
$160.73 $160.05 $131.56 $88.59
Task 1 - Program Support 30.00 $4,821.90 $0.00 $0.00 16.00 $1,417.44 244.00 $61,337.60
Task 2 - Production Support 185.00 $29,735.05 190.00 $30,409.50 32.00 $4,209.92 104.00 $9,213.36 789.00 $134,659.25
Task 3 - Data Management and Access $0.00 $0.00 $0.00 32.00 $2,834.88 40.00 $5,140.56
Task 4 - Coordination $0.00 $0.00 $0.00 38.00 $3,366.42 222.00 $57,166.36
Task 5 - Project Management and Quality Control $0.00 $0.00 $0.00 4.00 $354.36 40.00 $11,344.96
TOTAL MAN-HOURS AND COST 215.00 $34,556.95 190.00 $30,409.50 32.00 $4,209.92 194.00 $17,186.46 1,335.00 $269,648.73
Crosscheck 1,335.00 $269,648.73
TOTAL FEE (Rounded) $269,648.73
Man Hours
Man Hours
$170.67
$201.98
Total Man Hours Salary Cost
$251.38
$283.62
$128.51
$257.51
ATTACHMENT B: STAFF HOUR AND FEE ESTIMATE
Task Work Order 1 - Program Support
Man HoursMan Hours
Senior Scientist Home
Com. Outreach Specialist Home
Graphic Designer Home
Chief Engineer 2 Home
Senior Planner Home
Senior Env. Specialist Home
Secretary/Clerical Home
Man Hours
Average Hourly Rate
Man Hours Man Hours
Principal Engineer Home
Project Manager 3 Home
Man Hours Man Hours
Senior Engineer 1 Home
Man Hours
SubConsultant Name: AIM Engineering & Surveying, Inc.
SubConsultant Task Manager: Brittany Bianco
TASK Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
$143.25
Task 1 - Program Support 12.00 $1,719.00 $0.00 $0.00 $0.00 $0.00
Task 2 - Production Support 86.00 $12,319.50 $0.00 $0.00 $0.00 $0.00 TOTAL MAN-HOURS AND COST 98.00 $14,038.50 0.00 $0.00 0.00 $0.00 0.00 $0.00 0.00 $0.00
TASK Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
$0.00
Task 1 - Program Support $0.00 $0.00 $0.00 12.00 $1,719.00
Task 2 - Production Support $0.00 $0.00 $0.00 86.00 $12,319.50
TOTAL MAN-HOURS AND COST 0.00 $0.00 0.00 $0.00 0.00 $0.00 98.00 $14,038.50
TOTAL FEE (Rounded) $14,038.50
$143.25 $143.25 $143.25
Man Hours Man Hours Man Hours Man Hours
Total Man
Hours Salary Cost
Man Hours
ATTACHMENT B: STAFF HOUR AND FEE ESTIMATE
Task Work Order 1 - Program Support
Average Hourly Rate Man
Hours Man Hours Man Hours
Senior Environmental Specialist Home
SubConsultant Name: Kisinger-Campo & Associates, Inc.
SubConsultant Task Manager: Nicole Selly
TASK Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
$184.21
Task 1 - Program Support 12.00 $2,210.52 $0.00 $0.00 $0.00 $0.00
Task 2 - Production Support 43.00 $7,921.03 $0.00 $0.00 $0.00 $0.00 TOTAL MAN-HOURS AND COST 55.00 $10,131.55 0.00 $0.00 0.00 $0.00 0.00 $0.00 0.00 $0.00
TASK Loaded Hourly Rate
Loaded Hourly Rate
Loaded Hourly Rate
$0.00
Task 1 - Program Support $0.00 $0.00 $0.00 12.00 $2,210.52
Task 2 - Production Support $0.00 $0.00 $0.00 43.00 $7,921.03
TOTAL MAN-HOURS AND COST 0.00 $0.00 0.00 $0.00 0.00 $0.00 55.00 $10,131.55
TOTAL FEE (Rounded) $10,131.55
$184.21
Average Hourly Rate Man
Hours Man Hours Man Hours
$184.21 $184.21
Total Man
Hours Salary Cost
Man Hours Man Hours Man Hours Man Hours Man Hours
ATTACHMENT B: STAFF HOUR AND FEE ESTIMATE
Task Work Order 1 - Program Support
Senior Environmental Specialist Home
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
CAX36
7/2/2025
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR JASON ADANK, CPA, COMPTROLLER ON 7/2/2025
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55210000985
Expansion Option: N2
Object Code: 131545
Amount: $293,818.78
Financial Project: 40708513204
Work Activity (FCT): 011
CFDA:
Fiscal Year: 2026
Budget Entity: 55100100
Category/Category Year: 088849/26
Amendment ID: W001
Sequence: 00
User Assigned ID: TWO 1
Enc Line (6s)/Status: 0001/04
Total Amount: $293,818.78
Contract: CAX36
Contract Type: CA - ENGINEERING (ENGINEER)
Vendor Name: STANTEC CONSULTING SERVICES INC
Vendor ID: F112167170012
Beginning Date of This Agreement: 06/04/2025
Ending Date of This Agreement: 06/03/2030
Contract Total/Budgetary Ceiling: bc = $5,000,000.00
Method of Procurement: C - REQUEST FOR PROPOSAL (287.55,F. S.)
Description: Statewide Environmental Review & Analysis Consultant Support
Page1 of 1
To: Terri.Cook@dot.state.fl.us
Florida Department of Transportation
RON DESANTIS
GOVERNOR
605 Suwannee Street
Tallahassee, FL 32399-0450
JARED W. PERDUE, P.E.
SECRETARY
Improve Safety, Enhance Mobility, Inspire Innovation www.fdot.gov
MEMORANDUM
DATE: May 12,2025
TO: Catherine Bradley, State Environmental Development Engineer
Thu-Huong Clark, State Environmental Programs Administrator Jonathon Bennett, State Environmental Quality and Performance Administrator
FROM: Katasha Cornwell, Interim Director Office of Environmental Management
SUBJECT: Delegation of Authority
During my absence from the office, you have delegated signature and approval authority. This authority will be in your name "for Interim Director". This authority is valid May 12, 2025, through July 31, 2025.
Please ensure I receive a reading file copy of all correspondence you sign for me.
KC/tc
Docusign Envelope ID: 718C86D2-06BC-4EDB-8A5B-984288A8F05BDocusign Envelope ID: D1642ED6-5B50-42CB-B72E-CC4FD673B658
File details come from the government source that posted it. Updated .