This document is a Task Work Order for Professional Services issued by the State of Florida Department of Transportation (FDOT) to DRMP, Inc., a consulting firm located in Jacksonville, FL. The task work order is part of Contract No. CAW60 and specifically relates to Task Work Order No. 3 for a Right-of-Way Monumentation Survey and Mapping Project on State Road 100 in Bradford County.

The task work order authorizes DRMP to perform survey and mapping services for a segment of State Road 100 from US 301 to East of CSX Railroad Crossing, with a total compensation limit of $100,618.00. The project involves conducting a right-of-way monumentation survey, creating a monumentation map, and preparing required documentation according to District Two Right Of Way Monumentation Survey Map Check List. The work is to be completed by 3/2/2030, with all services subject to review by the District Survey Manager and compliance with current FDOT guidelines and handbooks.

View the file

Other files

File Type Posted
CN-550000-CAW60-W0010000.pdf PDF
CN-550000-CAW60-W0020000.pdf PDF
CN-550000-CAW60-W0040000.pdf PDF
CN-550000-CAW60-00010000.pdf PDF
CN-550000-CAW60.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

3/2/2030

*Limiting or Estimating/Budgeted Amount.

Distribution:

Task Work Order No.:

Contract No.: Payment FM No.:

CAW60 436558-1-62-08

$546,141.00

(name) (title) Signature

Clay Driggers, PSM PLS Supervisor II

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

(LA4) Units worked at loaded billing rates in Table 6

Page 1 Total

Page 2 thru 6 Subtotal

Total

Survey/Mapping Services

DRMP, INC.

8001 Belfort Parkway, Suite 200 Jacksonville, FL 32256

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$100,618.00

$100,618.00 Limit

SR100 Monumentation Map at Starke Railroad Overpass

Signature

DRMP

$100,618.00

$0.00

(name) (title)

C. William Faust III, PSM

$100,618.00

Total authorizations to date (including this one):

Departmental Approval:

Consultant Acceptance:

Digitally signed by: Clay Driggers

DN: CN = Clay Driggers email = clay.

driggers@dot.state.fl.us C = AD O = FDOT

OU = Location Survey

Date: 2025.04.30 10:38:12 -04'00'

Clay Driggers

Docusign Envelope ID: 8DFE3628-F82A-4BD7-826F-3D4F46D91CA9

05/01/2025 | 2:57 PM EDT

A - 1

Stage III (4/16/2025)

SCOPE OF SERVICES

A. DESCRIPTION

Authorization Financial Project ID Number 436558-1-62-08, State Road 100 from US301 to East of CSX Railroad Cossing. This is for a Right-of-Way Monumentation Survey and Mapping Project on SR100 in Bradford County.

B. Project Limits

1. The project is a portion of State Road Number 100. The limits should match the existing current R/W map for this project.

C. Survey: Right-of-Way Monumentation

Perform all necessary field work according to the current District Two Right Of Way Monumentation Survey Map Check List. (See Section 1 of checklist for requirements)

D. Map: Right-of-Way Monumentation Map

Complete all mapping requirements according to the current District Two Right Of Way Monumentation Survey Map Check List. (See Section 2 of checklist for requirements)

E. Survey: General

The following items apply to the entire project.

1. A Surveyor’s Report shall be prepared and submitted according to the current District Two

Right Of Way Monumentation Survey Map Check List. (See Section 3 of checklist for requirements)

2. All submittals shall comply with the current District Two Right Of Way Monumentation Survey Map Check List. (See Section 4 of checklist for requirements)

I. PROVISIONS OF WORK

All work shall be coordinated and subject to the review of the District Survey Manager. Refer to all current guidelines and handbooks for compliance.

J. DEPARTMENT'S RESPONSIBILITIES

The DOT will furnish existing information for the project.

Docusign Envelope ID: 8DFE3628-F82A-4BD7-826F-3D4F46D91CA9

SCOPE OF SERVICES
A. DESCRIPTION
B. Project Limits
J. DEPARTMENT'S RESPONSIBILITIES