This document is a Task Work Order Amendment Form for Professional Services issued by the State of Florida Department of Transportation. The amendment involves SRD, INC, located in Tampa, Florida, with contract number CAW 25. The document includes several sub-consultants: Bentley, Burgess & Niple, Harbor Coordination, Oz-Matic, and Stantec. The amendment is specifically Amendment No. 2 to Task Work Order No. 1, with a payment FIN number of 241085-1-32-25.
The amendment adds $22,698.90 in funds for Basic Support Services for SRD, increasing the total task work order amount to $171,140.45. The compensation method is based on (LA4) Units worked at loaded billing rates in Table 6, with the increase applied to the Basic Services Prime Consultant (SRD) compensation element. The total authorizations to date, including this amendment, are $407,585.86. An independent assessment of staff hours and quantities has been performed and found to be fair, reasonable, and competitive. The document is signed by Jason Smith, Vice President of SRD, INC, and Staci Nester, District Utility Administrator.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER AMENDMENT FORM
FOR PROFESSIONAL SERVICES
375-030-26
PROCUREMENT
08/21 recovered is $ .
22,698.90 .
Subtotal Estimate/L imit
$98,361.90 Limit
$8,566.55 Limit
$13,224.44 Limit
$15,425.92 Limit
$14,470.32 Limit
$9,104.76 Limit
$159,153.89
$11,986.56
$171,140.45
Attachments:
Distribution:
Burgess & Niple (Sub-Consultant)
Harbor Coordination (Sub-Consultant)
Stantec (Sub-Consultant)
Oz-Matic(Sub-Consultant)
$0.00
$13,224.44
$15,425.92
$14,470.32
$9,104.76
$22,698.90
$0.00
$22,698.90
Departmental Approval:
Total authorizations to date (including this one):
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
Page 1 subtotal
Page 2 thru 6 Subtotal
Total authorized against this task work order beyond the date of execution of this amendment. The following amount is the remaining work order balance to be recovered
The time for completion of services for the subject task work order is extended thru
The total amount for services performed under this task work order is increased by $
The total amount for services performed under this task work order is decreased by $
The decrease in funds will be allocated to the following compensation elements described below.
elements are described below.
from this task work order $ . Note: for Prof. Serv. Task Work Order Amendments, the encumbrance line should never be closed
The subject task work order is hereby closed. Final payment for the task work order has been set to PAID status in CITS. No additional services or charges are
(Status 50) by Financial Services staff based on this selection. Additional Note: Please be sure you want to close out before marking. Premature close outs that must
The subject task work order is hereby canceled (no work has been performed and no payment is due). The total amount of the task work order which is
The additional funds will be allocated to the following compensation elements described below.
There is no increase/decrease in the task work order amount, funds are only redistributed between compensation elements. Revised compensation be corrected in CITS may require programmer time and costs borne by the program office.
(LA4) Units worked at loaded billing rates in
Table 6
(LA4) Units worked at loaded billing rates in
Table 6
(LA4) Units worked at loaded billing rates in
Table 6
(LA4) Units worked at loaded billing rates in
Table 6
(LA4) Units worked at loaded billing rates in
Table 6
$0.00
Compensation Element
Description
This Amendment
Amount
Basic Services Prime Consultant
(SRD) $22,698.90
$0.00
Bentley (Sub-Consultant) $0.00
Previous
Amount
$75,663.00
$8,566.55
Method of Compensation
(LA4) Units worked at loaded billing rates in
Table 6
$0.00
(Title)
Jason Smith
Signature
Vice President
(Name)
$407,585.86
(Name) (Title) Signature
Staci Nester District Utility Administrator
Consultant Acceptance:
Payment FM No. (must be the same as original Task Work Order):
241085-1-32-25
Check all applicable Terms:
To add funds for Basic Support Services for SRD. See scope of services.
17425 Bridge Hill Ct., STE 200 Tampa, FL 33647
SRD, INC
Address:
Consultant:
Date (To be entered upon execution of Task Work Order Amendment):Contract No.:
CAW 25
Purpose of Amendment:
Amendment No.
to Task Work Order No.
File details come from the government source that posted it. Updated .