This is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) to Hanson Professional Services Inc., with supporting involvement from G-A-I Consultants, Inc. and Nelson\Nygaard Consulting. The document is specifically for Task Work Order #3 under Contract No. CAU92, with the FDOT Project Manager's Financial Management Number 454345-1-22-01, focused on continuing services for the South Florida East Coast Corridor Commuter Rail project in Palm Beach County.

The task work order is a $299,870.04 lump sum contract to provide technical support for commuter rail planning along the Florida East Coast (FEC) tracks in Palm Beach County. The scope involves reviewing existing reports, conducting field reviews, analyzing potential station locations, updating capital and operational costs, and developing technical reports for three potential commuter rail operating scenarios: (1) continuing rail north of Broward County to Jupiter, (2) a starter line from Jupiter to West Palm Beach, and (3) a starter line from Jupiter to Boca Raton. The project is set to be completed by October 15, 2029, with an estimated timeline of 6 months from the notice to proceed, and will involve approximately 12 initial meetings with FDOT and the Palm Beach Transportation Planning Organization (TPO).

View the file

Other files

File Type Posted
CN-550000-CAU92-00020000.pdf PDF
CN-550000-CAU92.pdf PDF
CN-550000-CAU92-00050000.pdf PDF
CN-550000-CAU92-00060000.pdf PDF
CN-550000-CAU92-00070000.pdf PDF
CN-550000-CAI75-00110000.pdf PDF
CN-550000-CAU92-00010000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

10/16/2029

*Limiting or Estimating/Budgeted Amount.

Distribution:

Consultant Acceptance:

Signature

Consultant, Procurement, Financial Services, FDOT Project Manager, File

Sr. Vice President

$299,870.04

$0.00

(name) (title)

Jeffrey L. Bowen

$299,870.04

Total authorizations to date (including this one):

Departmental Approval:

$299,870.04 Limit

The purpose of this Task Work Order is to provide support the Palm Beach TPA conduct a refresh of past studies on commuter rail looking at stations, costs, and operating scenarios.

Hanson Professional Services Inc.

8075 Gate Parkway West, Suite 204 Jacksonville, Florida 32216

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$299,870.04

(LS2) Lump sum paid based on % of completion

Page 1 Total

Page 2 thru 6 Subtotal

Total

Basic Services

$400,131.30

(name) (title) Signature

Shaneka Bolden Contract Coordinator

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Task Work Order No.:

Contract No.: Payment FM No.:

CAU92 454345-1-22-01

Docusign Envelope ID: 479610AE-0412-4FC4-B952-6FFFDEDA5679

03/12/2025 | 8:22 AM EDT

EXHIBIT "A"

CONTINUING SERVICES FOR SOUTH FLORIDA EAST COAST CORRIDOR

COMMUTER RAIL

Contract No.: CAU92

FDOT FM# 454345-1-22-01

Scope of Work – Task Work Order # 3

Palm Beach County Refresh

Background:

The most recent significant FEC commuter rail corridor planning work for Palm Beach County was completed in 2014 as part of ‘Phase 3’ of the Tri-Rail Coastal Link Study.

This study included 85 miles of the FEC Corridor that covered Miami Dade, Broward and Palm Beach Counties. Since the study was completed there have been significant developments along the corridor as well as additional studies. These include the introduction of the Brightline Intercity train service and acquisition of the passenger rail rights for the corridor, Miami Dade and Broward County completing and gaining approval for two separate NEPA studies and both projects are currently in the FTA’s New Starts program at different stages (MD is in Engineering and BC is in Project Development).

Palm Beach County has shown a desire to move forward with Commuter Rail as well and had a preliminary report done in 2023 to help them assess Commuter Rail in Palm Beach County along the FEC as well as extending Tri-Rail in various fashions. As a result of the southern counties’ work, knowledge gained and coordination with FTA, Brightline, SFRTA and FECR there are significant developments that will need to be considered in re-assessing Commuter Rail options in Palm Beach County.

PURPOSE OF TASK WORK ORDER

The purpose of this Task Work Order is to provide continuing technical support for new and existing planning and design efforts for commuter rail along the FEC tracks in Palm Beach County to support the Florida Department of Transportation, District Four, Office of Modal Development (OMD) staff in collaboration with the Palm Beach County TPO.

This Task Work Order will provide an overview of potential commuter rail transit in Palm Beach County, to include updated characteristics and assumptions, station analysis, capital costs, and operations and maintenance cost.

This assessment report will evaluate the previously proposed 8 station locations and will not evaluate new general station locations. If through the coordination efforts as well as the results of this report additional locations need to be assessed and developed that would be done under a future scope and work order. This report also will not assume or address the access fees that the county will need to address with Brightline and FECR or identify additional lease fees that may be needed with options that will also utilize the

SFRC or maintenance facilities. In addition, the Transit-Oriented Development Concept Plan will not be updated at this time.

Task Work Order # 03 - Scope of Work:

Task 1: Review Existing Reports and Data Work efforts conducted during this task will be to review past reports on the corridor, including but not limited to FDOT Tri-Rail Coastal Link data and reports, Palm Beach County TPO reports, Broward Commuter Rail South/Miami Dade Northeast Corridor data and reports, PalmTran and Tri-Rail reports and data, FECR/Brightline Track Charts, previous reports outlining station locations and other relevant studies. The effort will also include researching existing data from GIS and other sources that will be needed in the assessment and verification of information that includes street networks, current existing and future land use and demographics, parcel information, zoning and transit routes as well as other significant developments.

Work Product: Draft and Final Technical Memorandum documenting results of Task 1.

Timeline: Draft Memorandum 4 weeks after receipt of data, Final Memorandum 1 week after receipt of FDOT comments.

Task 2: Field Review, Update and Develop Assumptions Based on the results of Task 1 as well as interaction with the County and FDOT staff, work conducted during this task will include a field review, as well as verification of the existing track infrastructure. This field review as well as the review of existing data will assist in the development of study assumptions.

These include, but are not limited to the following:

Station Locations. Regarding Stations, the Consultant will perform a field review and validate proposed sites from the previous Tri Rail Coastal Link Station Refinement Report 2013/2014. If sites are no longer available, the Consultant will identify potential new locations. The validated/updated plan will be presented like the aerial graphics in the original study. This task will include the desktop mapping to assist in the field review.

Parking Locations. Previous studies outlined various locations for parking.

Based on the previous Tri-Rail Coastal Link 2035 ridership projections, parking space requirements will be estimated, and locations suggested for consideration in conjunction with the station locations.

Operating Scenarios. At the outset, it is envisioned that up to three different operating scenarios will be developed for capital and O&M costing.

These include:

o A continuation of commuter rail north of the Broward County line to Jupiter along the FEC corridor;

o A Jupiter to downtown West Palm Beach starter line along the FEC corridor; and o A Jupiter to Boca Raton starter line that accesses the SFRC via the Northwood crossover between the FEC and SFRC.

Task 2.

Timeline: Draft Memorandum 12 weeks after NTP, Final Memorandum 1 week after receipt of FDOT comments.

Task 3: Station Analysis For thirteen station locations in Palm Beach County, update documentation and analysis from the previous study including:

Context o Overview narrative.

o Future Land Use map and narrative description of land use patterns including new development, approved but unbuilt development, and proposed but not approved development.

o Transit map and narrative description of transit network within the station area.

Station Location and Platform Analysis o Current aerial and basemap with parcels and key nearby sites.

o Platform location and parking analysis with respect to land use and

TOD opportunities, mobility, engineering feasibility, municipal input, and parking.

Station Area Plan o Up-to-date map overview of ½ mile station area identifying important proximate land uses and development opportunities.

o Narrative description of influencing plans and policies, land use and urban form, and infrastructure.

Task 3.

Timeline: Draft Memorandum 16 weeks after NTP, Final Memorandum 1 week

Task 4: Update Capital Costs Work efforts for this task would include developing estimated capital costs for the above three operating scenarios. These costs would be provided in summary form in the Federal Transit Administration SCC format and would be provided in current year (2025) cost. These costs would be based upon prototypical station and corresponding track layouts from the BCR/NEC project to the south; the up-to-date Palm Beach County station locations, parking locations and supply; and the anticipated track geometry based on the proposed operating scenarios.

Task 4.

Timeline: Draft Memorandum 18 weeks after NTP, Final Memorandum 1 week

Task 5: Update Operations and Maintenance Costs Based upon the three operating scenarios developed in the previous task, the estimated Operations and Maintenance (O&M) cost would be developed using assuming a 30-minute peak/60-minute base for the continuation of the commuter rail line and proposed schedule north of Broward County. For the two starter line scenarios, the costs will be estimated using both a 30-minute peak/60-minute base as well as a 60 minute all day headway. Costs will be reported in 2025 dollars. In addition, each scenario will be assessed for an estimated number of train sets and cars and the likely storage and maintenance areas that may be available and the estimated costs for the improvements needed to house and maintain at the yard(s).

Task 5.

Timeline: Draft Memorandum 18 weeks after NTP, Final Memorandum 1 week

Task 6: Technical Report Development For this task, there will be a detailed project technical report. This report will provide:

Project Introduction, History and Purpose Summary of data collection and reference materials Summary of station location analysis Introduction/Summary of operating scenarios Summary of capital and operating cost analysis Recommendations for next steps

Work Product: Draft and Final Technical Report documenting results of Study.

Timeline: Draft Report 22 weeks after NTP, Final Report 2 weeks after receipt of FDOT comments.

Task 7: Meetings and Presentations Based upon conversations with the FDOT Project Manager and the Palm Beach TPA, it is anticipated that 12 meetings will be required initially for this Task Work Order.

INFORMATION PROVIDED BY THE DEPARTMENT

The CONSULTANT shall be entitled to rely on the completeness and accuracy of all information provided by the Department. The Department shall provide information requested by the CONSULTANT during the project.

METHOD OF COMPENSATION

Services for this task work order will be provided on a lump sum amount. The fee estimate for the work effort will be $299,870.04. A detailed fee sheet is contained in Attachment A.

This Task Work Order includes services to be provided by:

Hanson Professional Services Inc.

G-A-I Consultants, Inc.

Nelson\Nygaard Consulting

SCHEDULE

It is estimated that this work order and a final technical report will be completed within 6 months of notice to proceed.

All services are to be completed on or before October 15, 2029.

Staff Hour Costs

Work Task G-A-I Nelson/Nygaard

Total Cost $135,676.44 $107,909.84 $56,283.76

TOTAL ADJ COST $299,870.04

Hanson

Attachment "A"

Staff Hour Estimate for:

CONTINUING SERVICES FOR SFECC COMMUTER RAIL

Contract No.: CAU92 FM No.: 454345-1-22-01

Task Work Order Number: TWO #03

Palm Beach County Refresh

Manhour Summary

Staff Hour Costs Hanson Professional Services Inc.

Sub-total

Work Task Hours

6.1 Existing 4 8 4 80 96

6.2 Field and Assumptions 8 40 8 80 136

6.3 Station Analysis 4 4 6 0 14

6.4 Capital Cost 4 4 2 80 90

6.5 O&M Cost 4 8 2 0 14

6.6 Report 4 16 16 60 96

6.7 Meetings 12 12 14 25 63

Total Hours 40 0 0 92 0 0 0 0 0 52 0 0 0 0 325 0 0 0 0 509

Hourly Rates 441.93$ 291.07$ 257.43$ 610.02$ 254.72$ 190.48$ 257.09$ 200.24$ 238.52$ 285.95$ 149.33$ 305.01$ 147.66$ 141.80$ 144.64$ 122.19$ 117.34$ 169.07$ 97.09$

Staff Hour Costs $17,677.20 $0.00 $0.00 $56,121.84 $0.00 $0.00 $0.00 $0.00 $0.00 $14,869.40 $0.00 $0.00 $0.00 $0.00 $47,008.00 $0.00 56121.+ $0.00 $0.00 $135,676.44

Sub-total

Description Unit Cost Hours Sub-total Expenses

EXPENSES

Sub-total $0.00 $0.00

TOTAL EXPENSES $0.00

TOTAL COST $135,676.44

Senior Engineer 1 A Home-Task Lead Senior Planner Home

Senior Environmental Specialist Home

Senior Designer Home

Senior Engineering Technician Home

Task Work Order Number: TWO #03

Palm Beach County Refresh

Project Manager 3 Home Chief Designer HomeChief Scientist Home

Senior Engineer 2 Home Engineer 1 Home

Engineering Intern Home

Engineering Technician Home GIS Specialist Home

Secretary/Clerical Home

Chief Engineer 2 Home

Chief Engineer 1 Home Chief Planner Home

Senior Engineer 2 A Home-Task Lead

Senior Engineer 1 Home

Attachment "A"

Staff Hour Estimate for:

Hanson Professional Services, Inc.

CONTINUING SERVICES FOR SFECC COMMUTER RAIL

Contract No.: CAU92 FM No.: 454345-1-22-01

Work Task Hours

6.1 Existing 12 24 48 84

6.2 Field and Assumptions 12 24 104 140

6.3 Station Analysis 112 104 104 320

6.4 Capital Costs 4 4 4 12

6.5 O&M Cost 0 0 0 0

6.6 Report 16 16 64 96

6.7 Meetings 12 8 8 28

Total Hours 0 0 0 168 180 332 680

Hourly Rates 249.01$ 217.56$ 202.72$ 225.66$ 189.72$ 107.98$

Staff Hour Costs $0.00 $0.00 $0.00 $37,910.88 $34,149.60 $35,849.36 $107,909.84

Sub-total

Description Unit Cost Hours Expenses

EXPENSES

$0.00

TOTAL EXPENSES $0.00

TOTAL COST $107,909.84

Attachment "A" Staff Hour Estimate for:

G_A_I Consultants, Inc.

CONTINUING SERVICES FOR SFECC COMMUTER RAIL

Contract No.: CAU92 FM No.: 454345-1-22-01

Task Work Order Number: TWO #03

Chief Planner A Home-Task

Lead Planner Home

Palm Beach County Refresh

Chief Landscape

Architech Home

Senior Landscape

Architect Home Chief Planner

Home Senior Planner

Home

Work Task Hours

6.1 Existing 4 4

6.2 Field and Assumptions 8 8

6.3 Station Analysis 0 0

6.4 Capital Cost 0 0

6.5 O&M Cost 160 160

6.6 Report 4 4

6.7 Meetings 8 8

Total Hours 0 0 184 0 0 0 0 184

Hourly Rates 257.76$ 225.14$ 305.89$ 303.56$ 134.32$ 225.14$ 164.97$

Staff Hour Costs $0.00 $0.00 $56,283.76 $0.00 $0.00 $0.00 $0.00 $56,283.76

Sub-total

Description Unit Cost Hours Expenses

EXPENSES

Sub-total $0.00

TOTAL EXPENSES $0.00

TOTAL COST $56,283.76

Palm Beach County Refresh

Project Manager 3

Home Chief Engineer

1 Home

Chief Planner A Home - Task

Lead Chief Planner

Home Planner Home

Senior Engineer 1

Home Senior Planner

Home

Task Work Order Number: TWO #03

Attachment "A" Staff Hour Estimate for:

Nelson\Nygaard Consulting

CONTINUING SERVICES FOR SFECC COMMUTER RAIL

Contract No.: CAU92 FM No.: 454345-1-22-01

Table 1
Insert from: "8775.pdf"
INFORMATION PROVIDED BY THE DEPARTMENT
METHOD OF COMPENSATION
It is estimated that this work order and a final technical report will be completed within 6 months of notice to proceed.
All services are to be completed on or before October 15, 2029.
Insert from: "BC09.pdf"
Summary
Hanson
G-A-I
NN

File details come from the government source that posted it. Updated .