CN-550000-CAR56-00050000.pdf
PDF 946 KB Posted
- Contract number
- CAR56
- Issued by
- Florida
About this file
This is a Task Work Order (TWO No. 3) issued by the Florida Department of Transportation (FDOT) District Three to Kimley-Horn and Associates, Inc., a consulting firm located in Atlanta, Georgia. The contract is part of the Districtwide Transportation Systems Planning contract (Contract No. CAR56) and focuses on professional planning and engineering services for Santa Rosa County, Florida, including coordination with Santa Rosa County and its municipalities of Gulf Breeze and Milton.
The task order involves projecting traffic impacts to state roads within Santa Rosa County based on proposed and planned developments. Kimley-Horn will conduct research on development databases, identify approved developments, review traffic studies, and create an interactive GIS database illustrating development locations and potential roadway capacity issues at 5-year and 20-year horizons. The total compensation for these services is $83,021.00, to be paid on a lump sum basis according to percentage of completion. The work is to be completed by December 31, 2025, with bi-weekly coordination with FDOT District 3 Planning staff and monthly progress reporting requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAR56-00040000.pdf | ||
| CN-550000-CAR56.pdf | ||
| CN-550000-CAR56-00030000.pdf | ||
| CN-550000-CA683-S0020000.pdf | ||
| CN-550000-CA683.pdf | ||
| CN-550000-CAR56-00020000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
12/31/2025
*Limiting or Estimating/Budgeted Amount.
Distribution:
Consultant Acceptance:
Signature
Consultant, FS, PM, PSU A. Goines
Senior Vice President
$83,021.00
$0.00
(name) (title)
Richard Barr
$83,021.00
Remaining Balance: $0.00
Total authorizations to date (including this one):
Departmental Approval:
$83,021.00 Limit
DW Systems Planning Consultant- Support D3 in projecting traffic impacts to State roads within Santa Rosa County. Scope of Services, attached.
Kimley-Horn and Associates, Inc.
P.O. Box 932520, Atlanta, Georgia 31193
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$83,021.00
(LS2) Lump sum paid based on % of completion
Page 1 Total
Page 2 thru 6 Subtotal
Total
Basic Services (LS)
$183,021.00
(name) (title) Signature
Colby Cleveland, P.E. Interim Director of Transportation Development
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
Task Work Order No.:
Contract No.: Payment FM No.:
CAR56 42254141213
Docusign Envelope ID: 4F333125-29B0-49B3-AADA-F4C7467595E1
XXXXXXXXXXXXXXXXXXXXXXXX
Associate
Shawn Kalbli
6/16/25
DISTRICTWIDE TRANSPORTATION SYSTEMS PLANNING
CONTRACT No.: CAR56
FPID:422541-4-12-13
ATTACHMENT “A”
TASK WORK ORDER NO. 3
SANTA ROSA COUNTY DEVELOPMENT TRENDS – TRAFFIC IMPACTS TO STATE
ROADS
I. DESCRIPTION OF SERVICES
The Florida Department of Transportation District Three (Department) has requested that Kimley- Horn (Consultant) provide professional planning and engineering services to support District 3 Planning Staff in projecting traffic impacts to state roads within Santa Rosa County based on proposed and planned development.
II. SERVICES TO BE PROVIDED
Tasks that consultant services may be required with this Task Work Order include:
Identify Locations of Approved Developments and Planned Developments within Santa County, Florida
Coordination with Santa Rosa County and its Municipalities (City of Gulf Breeze, City of Milton) o Meet with staffs to discuss Purpose and Need for this study o Meet with staffs to understand their current development database (including their concurrency systems) and identify how the agencies keep up with development and future development plans in general
Kimley Horn Research o Research Santa Rosa County and its municipalities’ (City of Gulf Breeze, City of
Milton) development database(s) and/or concurrency system(s) o Identify recently approved developments (last five years as of Notice to Proceed) that may have traffic impacts on state roads in Santa Rosa County Working with District 3 Planning staff, identify thresholds for determining significant size of development review. This may be based on number of trips generated and proximity to SIS, SHS, or NHS facilities.
o Utilize Florida Traffic Online to obtain existing AADT volumes on state roads o Determine daily capacity or maximum service (MSV) of state roadways within
Santa Rosa County based on preliminary context classifications (via FDOT’s ConnectPed) and the latest Q/LOS Handbook. This identification of capacities or MSV will include new roadways or planned capacity improvements (widening) with funding identified in the FDOT Five-Year Work Plan.
Docusign Envelope ID: 29EF95E2-3376-4CB6-B96D-681DE4013D03Docusign Envelope ID: 4F333125-29B0-49B3-AADA-F4C7467595E1
Determine Traffic Impacts of Future Development on State Roads in Santa Rosa County
Review traffic studies for developments above the significance threshold identified in Research above
At 5-year and 20-year horizons, identify project land uses, trip generation, and trip assignments on state roads
At 5-year and 20-year horizons, identify forecasted total traffic volumes (existing traffic plus development traffic) as a result of new development
At 5-year and 20-year horizons, compare the total traffic volumes to the MSV for state roadway segments. Identify where and approximately when there will be potential capacity issues on state roads
Bi-weekly coordination with District 3 Planning staff to discuss progress of ongoing study and to discuss incoming information about Santa Rosa County development projects.
III. DELIVERABLES
Interactive GIS database illustrating:
o Locations of approved and planned significant development projects over the 5-year and 20-year horizons To include publicly available information about the developments such as land use, completion year, traffic impacts o State roadway network generalized service capacities, 5-year horizon LOS and volume-to-capacity ratios, and 20-year horizon LOS and volume-to-capacity ratios To reflect funded capacity improvements and planned future developments over the 5-year and 20-year horizons
Document summarizing how to use the Santa Rosa Development Trends GIS database and capacity concerns in the 5-year and 20-year horizons
IV. PROVISIONS FOR WORK
A. Key Personnel
The Consultant’s work shall be performed and directed by the key personnel identified by the Consultant and approved by the FDOT Project Manager.
B. Progress Reporting
The Consultant will provide a monthly written Progress Report and Monthly Summary Report.
The Consultant will provide weekly progress emails to the FDOT Project Manager.
Docusign Envelope ID: 29EF95E2-3376-4CB6-B96D-681DE4013D03Docusign Envelope ID: 4F333125-29B0-49B3-AADA-F4C7467595E1
V. DURATION OF SERVICES
The consultant will work with the FDOT Project Manager and each Task Manager in developing a mutually acceptable time schedule for each task.
VI. DEPARTMENT RESPONSIBILITIES
The Department will provide the Consultant such information and/or staff cooperation as may be required to complete the task assignments. Such support will include:
A. Appropriate data on file and/or access to files so that Consultant can retrieve data.
B. Standards and procedures directives from the FDOT.
C. Staff review services.
D. Any future information which may come into the possession of the FDOT which is deemed to be necessary to the completion of the assignment.