This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT), involving PMA Consultants LLC as the contractor. The contract is part of the broader Contract No. CAO84, which covers risk management services related to transportation facilities. The specific Task Work Order (No. 2) is for a research project to be completed by 10/28/2026, with a total contract value of $47,977.92.
The scope of work involves analyzing the performance of Cost & Schedule Risk Analysis (CSRA) conducted by FDOT over the past 15 years. PMA Consultants will conduct a phased research project to compare actual project outcomes with CSRA predictions, with the first phase focusing on one pilot project. The objectives include evaluating CSRA effectiveness, improving future cost and schedule forecasts, developing key performance indicators (KPIs), and establishing a user-friendly database for ongoing performance monitoring. Deliverables will include a preliminary report summarizing findings, proposed KPIs, a prototype framework, and a PowerPoint presentation. The contract is structured as a lump sum payment upon completion, with the fee determined by the billing rates specified in the contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAO84-00030000.pdf | ||
| CN-550000-CAO84-00010000.pdf | ||
| CN-550000-CAO84-00040000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-CAO84-W0010000.pdf | ||
| CN-550000-CAL09-W0020100.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
10/28/2026
*Limiting or Estimating/Budgeted Amount.
Distribution:
Task Work Order No.:
Contract No.: Payment FM No.:
CAO84 190258-1-32-83
$12,482,042.89
(name) (title) Signature
Bobby Bull Value Engineer
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
(LS1) Lump sum paid at completion
Page 1 Total
Page 2 thru 6 Subtotal
Total
PMA Consultants LLC
PMA Consultants
4901 Vineland Road, Suite 330 Orlando, FL 32811
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$47,977.92
$47,977.92 Limit
To analyze the performance of Cost & Schedule Risk Analysis (CSRA) conducted over the past 15 years by comparing actual project outcomes with CSRA predictions.
This initiative aims to evaluate the effectiveness of CSRA, improve future cost and schedule forecasts, develop key performance indicators (KPIs), and establish a robust, user-friendly database to support ongoing performance monitoring, forecasting, and analysis. The scope of work will be executed in two distinct phases to gauge the viability and effectiveness of the proposed risk KPIs tool.
Signature
File, Procurement, Comptroller, Bobby Bull, Gaelan Bishop, April Combs, Jeanine Pumphrey
Managing Director
$47,977.92
$0.00
(name) (title)
Richard L. Johnson
$47,977.92
Total authorizations to date (including this one):
Departmental Approval:
Consultant Acceptance:
Docusign Envelope ID: D458C19C-14A3-482D-9128-E68FFEC46376
05/01/2025 | 4:56 PM EDT
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
CAO84
5/1/2025
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR JASON ADANK, CPA, COMPTROLLER ON 5/1/2025
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55410100966
Expansion Option: A4
Object Code: 131500
Amount: $47,977.92
Financial Project: 19025813283
Work Activity (FCT): 011
CFDA:
Fiscal Year: 2025
Budget Entity: 55100100
Category/Category Year: 088849/25
Amendment ID: W002
Sequence: 00
User Assigned ID: TWO 2
Enc Line (6s)/Status: 0001/04
Total Amount: $47,977.92
Contract: CAO84
Contract Type: CA - ENGINEERING (ENGINEER)
Vendor Name: PMA CONSULTANTS LLC
Vendor ID: F383327768001
Beginning Date of This Agreement: 07/28/2023
Ending Date of This Agreement: 07/27/2028
Contract Total/Budgetary Ceiling: bc = $5,000,000.00
Method of Procurement: C - REQUEST FOR PROPOSAL (287.55,F. S.)
Description: Provide risk management services related to transportation facilities and to conduct training in the principles of risk
Page1 of 1
To: Jeanine.Pumphrey@dot.state.fl.us
EXHIBIT A
SCOPE OF SERVICES
Risk Key Performance Indicators for Cost and Schedule Forecasting and Analysis on Florida Department of
Transportation (FDOT) Completed Projects
CONTRACT NO: CAO84
Task Work Order: Number 2
Task Work Order Title: Risk Key Performance Indicators – Phase 1
Overview FDOT seeks to analyze the performance of Cost & Schedule Risk Analysis (CSRA) conducted over the past 15 years by comparing actual project outcomes with CSRA predictions. This initiative aims to evaluate the effectiveness of CSRA, improve future cost and schedule forecasts, develop key performance indicators (KPIs), and establish a robust, user-friendly database to support ongoing performance monitoring, forecasting, and analysis.
The scope of work will be executed in two distinct phases to gauge the viability and effectiveness of the proposed risk KPIs tool. PMA will conduct independent and objective research on a selected sample of completed projects that used CSRA. The sample will initially include five (5) projects to ensure manageable scope and detailed analysis. PMA will use a phased approach to perform this research by assessing one (1) project during Phase 1 for Task 1 only, and then moving to the next four (4) projects during Phase 2. This phased approach will ensure that our team understand the level of effort and quality of data that will be yielded during the collection process.
The steps to complete Phase 1 are discussed in further detail on the following pages.
Tasks The following pages contain each of the key tasks PMA will perform to complete this study.
Phase 1 – Pilot Project Research and Prototype Framework Development for One (1) FDOT Project
Task 1: Research and Database Prototype Development
Research Methodology
PMA will collect and analyze data from one (1) identified project on programmed and actual costs and schedules, CSRA reports, risk registers, and supplemental agreements (SA), comparing these outcomes to CSRA predictions.
This phased approach ensures a manageable scope and allows detailed insights to inform subsequent phases. Each project’s data will undergo collection, normalization, assessment, calibration, and deployment processes.
Data Collection To ensure comprehensive research, PMA will request access to various FDOT data sources and software applications:
a) Long Range Estimates (LRE): To obtain historical project cost data.
b) Project Suite Enterprise Edition (PSEE): For detailed project documentation, scope, budgets, schedules, resource allocations, and milestones.
c) Programs and Services Application: To gather funding and programming data.
d) Contract Information & Monitoring (CIM): To review contract details and performance.
e) AASHTOware Project Construction (PrC): For construction phase insights, including change orders and delays.
f) ProjectSolve SharePoint (PSSP): To access centralized project documentation.
g) Z/Server Dependent Production Applications: For financials, reporting, tracking, and legacy project data.
h) State Construction Office Site: For supplemental agreements (SA) and project completion reports.
PMA will also follow FDOT’s Application Development Standards to ensure compatibility with existing systems and adherence to cybersecurity protocols. The database will reside in an FDOT environment; PMA will collaborate on this effort, but it may be done by others.
Data Normalization
The collected data will be standardized to ensure consistency across all projects. Coordination with the Department’s Project Finance Office is needed to be consistent with our inflation indices.
Steps include:
Converting monetary values to constant dollars using inflation indices.
Standardizing time units and milestones for uniform schedule analysis.
Categorizing risks using a common taxonomy (e.g., cost risks, schedule risks, design, utility, construction, and right of way risks).
Data Assessment
Each project’s financial and schedule data, including CSRA data, will be assessed for accuracy and completeness. This includes:
Comparing programmed and actual costs at key milestones. Additional milestones that may be outside the typical CSRA process will also be considered.
Verifying risk registers against documented risks that materialized.
Ensuring that schedule data aligns with actual completion dates.
Data Calibration
PMA will calibrate the data to align with FDOT’s historical benchmarks. This involves:
Analyzing the data to detect inconsistencies, outliers, missing values, or biases that might affect the overall accuracy
Comparing the data to a reliable external source or standard dataset to identify deviations and make necessary adjustments, such as amending probability distributions in CSRA predictions to match observed outcomes.
Applying statistical methods to quantify the level of error and determine the appropriate adjustments needed.
Establishing calibration factors for cost overruns and schedule delays.
Incorporating expert judgment to refine risk severity and likelihood estimates.
Data Deployment
The calibrated data will be used to populate the risk database. Key deployment steps include:
Mapping normalized data to database fields.
Testing data integrity and functionality through pilot analyses.
Refining database structure based on user feedback.
Analytical Framework
For each selected project, PMA will:
1. Review and Document Costs: Capture base costs, 70% percentile risk-based costs, and final actual costs at a minimum of five lifecycle milestones, such as PD&E and 90% design completion.
2. Analyze Cost Overruns/Underruns: Compare actual costs to the 70% Cost Probability Distribution (S-curve) and overrun or underrun percentages.
3. Evaluate Schedule Performance: Analyze schedule durations and completion dates (base, risk-based, and actual) and evaluate schedule performance, including delays or underruns, using the 70% Schedule Probability Distribution (i.e., S-curve).
4. Risk Materialization Analysis: Investigate whether risks identified during CSRA were mitigated, if risks materialized during pre-construction and if they were documented, identify their associated costs, and their schedule impacts. Investigate if the main drivers of cost and schedule over or underrun were captured as risks.
5. Supplemental Agreement Impact Ranking: Examine the extent to which risks were communicated to Construction teams and materialized as supplemental agreements, and rank SA impacts based on cost and schedule severity.
Deliverables A Preliminary Report summarizing findings, Proposed KPIs, prototype framework, and analyses for the selected project.
A PowerPoint presentation highlighting key results.
Fee Estimate The activities will be completed for a lump sum fee amount of $47,977.92 established by the billing rates of the contract. Refer to Exhibit 1.