CN-370000-WQ034-T10CO1.pdf
PDF 336 KB Posted
- Contract number
- WQ034
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form for DEP Contract No. WQ034, dated June 27, 2018. The parties involved are the St. Johns River Water Management District (SJRWMD) as the contractor, represented by Robert Naleway, P.E., Bureau of District Projects and Construction, and the Florida Department of Environmental Protection (FDEP) as the contracting agency, with Emily Forinasch of the Nonpoint Source Management Section serving as the DEP Task Manager. The change order modifies Task Assignment 10 and was approved through a multi-level authorization process involving the District Project Manager, General Counsel, Procurement Specialist, Director, and Budget Representative.
The change order reduces the scope of work for the Newton Park dredging project in Lake Apopka due to a reduction in FDEP funding for the project. The task description section is deleted and replaced with deliverables limited to conceptual engineering plans for the Newton Park dredging project. The change order references that initial work was completed under Work Order 1 with Taylor Engineering, which aligns with this change order to Task Assignment 10's revised scope of work. The document contains blank sections for changes in task amount, task time, and funding information (organizational code, object code, budget entity, special category, grant number, year, and amount), indicating this was a template form with specific financial details to be completed separately.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6/27/18
Audit Log - Associated Action V3 11 09 17 1638 (33359)
Date Time Type User Source Category Location Message
6/27/2018 7:50:05 AM ApprovalEvent Hankin, Karl(Director) Person Approved Approved Approved by khankin@sjrwmd.com - Comments: Approved by Hankin, Karl:
6/26/2018 4:56:59 PM ApprovalEvent Paulk, Pamela (x4469)(Procurement Specialist)
System Workflow Request Approval Request Approval from Hankin, Karl.
Comments: This CO modifies Task Assignment 10 to reduce the scope of work for Newton Park due to the reduction of funding for this project by FDEP. The initial work was completed under WO1 with Taylor Engineering which now matches CO1 to Task Assignment 10 scope of work.. Purpose: Contract 28344 CO1 to Task Assignment 10 under FDEP
6/26/2018 4:56:57 PM ApprovalEvent Paulk, Pamela (x4469)(Procurement Specialist)
System Workflow Request Approval Request Approval from Hankin, Karl
6/22/2018 7:21:12 AM ReviewEvent Conover, Alana Person Reviewed Reviewed Reviewed by Conover, Alana - Comments:
Reviewed by aconover@sjrwmd.com:
6/21/2018 4:11:56 PM ReviewEvent Smith, Ashley(General Counsel)
System Workflow Request Review Request Review from Conover, Alana
6/21/2018 4:11:48 PM ApprovalEvent Smith, Ashley(General Counsel)
Person Approved Approved Approved by dasmith@sjrwmd.com - Comments: Approved by Smith, Ashley:
6/21/2018 3:09:38 PM ApprovalEvent Paulk, Pamela (x4469)(Procurement Specialist)
System Workflow Request Approval Request Approval from Smith, Ashley
6/21/2018 3:09:01 PM ApprovalEvent Naleway, Robert(District
PM)
Person Approved Approved Approved by rnaleway@sjrwmd.com - Comments: Approved by Naleway, Robert:
6/21/2018 3:08:22 PM ApprovalEvent Paulk, Pamela (x4469)(Procurement Specialist)
System Workflow Request Approval Request Approval from Naleway, Robert
File details come from the government source that posted it. Updated .