This is a Change Order (No. 1) issued by the Department of Environmental Protection for Task Assignment No. 3 under Contract CN223 with TKW Consulting Engineers and Mike McGee for continuing professional services at Highlands Hammock in Florida. The contract involves coordination with the City of Sebring and was managed by project manager Brian Miller and contract manager Mae Roth of the Florida Department of Environmental Protection, with consultant Pat Day, P.E., representing TKW Consulting Engineers.

The change order extends the task completion timeline by 90 days, from the original completion date of April 5, 2016, to a new completion date of July 4, 2016, due to pending coordination with the City of Sebring. The change order specifies a fixed-price modification with no changes to subtask amounts; the original task amount of $18,198.68 remains unchanged with zero cost impact. The total task duration increased from 210 days to 300 days. The document was executed on April 5, 2016, by authorized representatives from both the Department of Environmental Protection and the contractor.

View the file

Other files

File Type Posted
CN-370000-CN223-CMC1.pdf PDF
CN-370000-CN223-T5.pdf PDF
CN-370000-CN223-T6CO1.pdf PDF
CN-370000-CN223-T8.pdf PDF
CN-370000-CN223-CMC2.pdf PDF
CN-370000-CN223-T12.pdf PDF
CN-370000-CN223-T13.pdf PDF
CN-370000-CN223-T13CO1.pdf PDF
CN-370000-CN223-T3.pdf PDF
CN-370000-CN223-T6CO3.pdf PDF
CN-370000-CN223-T6CO4.pdf PDF
CN-370000-CN223-T8CO1.pdf PDF
CN-370000-CN223-T9.pdf PDF
CN-370000-CN223-T1CO1.pdf PDF
CN-370000-CN223-T1CO2.pdf PDF
CN-370000-CN223-T4.pdf PDF
CN-370000-CN223-T5CO1.pdf PDF
CN-370000-CN223-T5CO2.pdf PDF
CN-370000-CN223-T6.pdf PDF
CN-370000-CN223-TA2.pdf PDF
CN-370000-CN223-TA8CO2.pdf PDF
CN-370000-CN223-Task 11.pdf PDF
CN-370000-CN223-CMC3.pdf PDF
CN-370000-CN223-T10.pdf PDF
CN-370000-CN223-T2CO1.pdf PDF
CN-370000-CN223-T6CO2.pdf PDF
CN-370000-CN223-TA1.pdf PDF
CN-370000-CN223.pdf PDF
PC-370000-CN223.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

From: Roth, Mae To: Roth, Mae Subject: FW: Highlands Hammock task assignment extension Date: Tuesday, April 5, 2016 10:06:47 AM Attachments: image001.png

From: Patrick J. Day [mailto:pat.day@tkwonline.com] Sent: Tuesday, April 05, 2016 9:12 AM To: Miller, Brian D.

Cc: Mike Mcgee Subject: RE: Highlands Hammock task assignment extension

Brian, 90 days would be better considering that we are waiting on the City of Sebring before we can start.

Regards, Pat

Patrick J. Day, P.E.

Environmental Engineering Manager pat.day@tkwonline.com

TKW Consulting Engineers, Inc.

5621 Banner Drive Fort Myers, Florida 33912 Tel: (239) 278-1992 ext. 301 Fax: (239) 278-0922 http://www.tkwonline.com

From: Miller, Brian D. [mailto:Brian.D.Miller@dep.state.fl.us] Sent: Tuesday, April 05, 2016 8:55 AM To: Patrick J. Day <pat.day@tkwonline.com> Cc: Mike Mcgee <mike.mcgee@tkwonline.com> Subject: Highlands Hammock task assignment extension

Pat, I have setup the change order already for the time extension only and just wanted to confirm that 90 days will be a sufficient amount of time for you to complete any remaining subtasks on the Task Assignment? Thanks mailto:/O=EXCHANGELABS/OU=EXCHANGE ADMINISTRATIVE GROUP (FYDIBOHF23SPDLT)/CN=RECIPIENTS/CN=8F8E7E67C5A641109AF6427BAECF7463-ROTH_M mailto:Mae.Roth@dep.state.fl.us mailto:pat.day@tkwonline.com mailto:pat.day@tkwonline.com http://www.tkwonline.com/ mailto:Brian.D.Miller@dep.state.fl.us mailto:pat.day@tkwonline.com mailto:mike.mcgee@tkwonline.com

Brian Miller Engineering Specialist Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399 Brian.D.Miller@dep.state.fl.us (link sends e-mail) Office: 850.245.2684 Cell: 850.294.4366

This communication does not constitute an authorization for any increase in the scope of work, cost, or time for the project being discussed. All changes to services, cost, or time must be accomplished in accordance with the formal process outlined in the contract. The DEP objects to, and shall not be responsible for, any changes to services, costs, or additional time not authorized by an executed Contract Amendment, Task Assignment Change Order, Construction Change Order, or Construction Change Directive, as appropriate for this contract.

Take our Customer Survey:

Office of Operations Customer Survey http://www.dep.state.fl.us/ mailto:Brian.D.Miller@dep.state.fl.us%20(link%20sends%20e-mail) http://www.surveygizmo.com/s3/2204130/DEP-Office-Of-Operations-Customer-Survey-FY-15-16 http://survey.dep.state.fl.us/?refemail=Brian.D.Miller@dep.state.fl.us

File details come from the government source that posted it. Updated .