This Clarification Amendments document pertains to the Alabama Department of Conservation and Natural Resources (DCNR), State Lands Division (SLD) herbicide spray project for the Old Cahaba Prairie East Tract. The amendments provide clarifications and modifications to the original bid specifications and contract requirements for this vegetation management project. The document addresses questions and concerns raised by bidders regarding the scope of work, application procedures, equipment requirements, and environmental compliance measures for the herbicide treatment operations on the designated tract.
The clarifications establish specific requirements for herbicide selection, application methods, safety protocols, and documentation procedures that bidders must follow in their proposals and contract performance. The amendments ensure that all potential contractors understand the precise expectations for chemical handling, environmental protection, timing of applications, and reporting obligations. These modifications maintain the integrity of the procurement process by providing uniform guidance to all bidders and reducing ambiguity in contract performance standards and acceptance criteria.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarification Amendments
The following statements have been added to the specifications
• Herbicide must be applied at least five (5) feet past the outer perimeter of every cogon grass patch.
• PO will be issued as soon as practicable, after contract is awarded
• Work for 2026 will end on October 15th, 2026, and begin again when growing season starts in 2027
• Actual acreage will depend on pricing, budget and timing.
• ITB should be priced on a per acre basis and MUST include ALL costs associated with the requested application treatment of the designated area as defined in the solicitation documents.
• Costs should include, but are not limited to, travel expenses, labor, patrol (regardless of methods used), equipment mobilization, herbicide chemicals and any other costs necessary to identify and spray patches of cogon grass within any given acre.
• Contractor will be compensated at the designated per acre rate for all requested and treated acreage.