Scope of Work Capulin Volcano National Monument Install SCADA system Description:

This work consists of installation of a Mission M852 SCADA (or comparable equal) system and removal of the current inoperable telemetry system on the existing water tank and wellhouse at Capulin Volcano National Monument.

Location:

The project is located in the Capulin Volcano National Monument Visitor Center located at 46 Volcano Road Capulin, New Mexico 88414 Getting to Capulin Volcano National Monument from the City of Raton (Interstate 25) Travel east on Highway 64/87 approximately 25 miles to the Village of Capulin, turn north on NM 325 and proceed approximately 4 miles to the entrance gate. Turn east into the main entrance gate and follow the road approximately 1 mile to the Visitors Center.

SCOPE

Installation of SCADA system:

The contractor will be expected to do the following:

1. Install Two (2) units for system monitoring and control.

a. 1 at well site utilizing existing 120-volt power

b. 1 at tank site utilizing existing solar power

2. Install 1 relay for well control at well site

3. Program relay for well pump call to run and shutdown for well

4. Program digital inputs for well pump run

5. Program digital alarm for well pump fail to run

6. Program alarm inputs for door entry notification at well site

7. Program analog input for tank level to call to run and turn off along with alarm threshold for low and high tank level alarm thresholds.

8. Program input for temperature alarm at well site

9. Install tank and well software program for well pump control on/off and remote control

10. Install in tank Water pressure transducer for tank level

11. Program loss of utility power to unit at well site and solar at tank

12. Program low battery alarm at unit for well and tank

13. Program loss of communication alarm to unit for well

14. Install 18/2 twisted shielded cable for all digital inputs, analog inputs and outputs

15. Startup and commissioning and training

16. Labor and materials