Bid Schedule - 140F0620R0002.pdf
PDF 321 KB Posted
- Attached to
- REPAIR TRAIL AND REPLACE OBSERVATION DECK AT BOWDO Federal contract opportunity
- Solicitation number
- 140F0620R0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140F0620R0002.pdf | ||
| Wage Determination - MT20200076 - 3 Jan 2020.pdf | ||
| Drawings - 140F0620R0002.pdf | ||
| Specs - 140F0620R0002.pdf | ||
| Instruction to Offerors - 140F0620R0002.pdf | ||
| Project Submittals List - 140F0620R0002 .pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
19-035
BOWDOIN NATIONAL WILDLIFE REFUGE
MALTA, MONTANA
Unit Total
QTY Unit Cost Cost
DIVISION 1 - GENERAL REQUIREMENTS
1 1 JB
Division 1 Total
DIVISION 2 - EXISTING CONDITIONS
1 1 EA
2 1 EA
Division 2 Total
DIVISION 3 - CONCRETE
1 1 JB
Division 3 Total
DIVISION 6 - WOOD, PLASTICS, AND COMPOSITES
1 1 EA
Division 6 Total
DIVISION 32 - EXTERIOR IMPROVEMENTS
1 1 JB
4 1 JB
5 1 JB
Division 32 Total
Total All Division
NOTE: Quantities listed are estimates. Contractor to verify quantities prior to submitting prices.
Crack sealant application, crack cleaning, and any appurtenances to complete the work
Concrete footings and any appurtenances to complete the work (EST 4 EA)
Sawcut asphalt replacement, geotextile, gravel, salt, and any appurtenances to complete the work (EST 29 SY)
Deck, frame, posts, cables, and any appurtenances to complete the work (EST 157 SF Deck)
Surface overlay and any appurtenances to complete the work
(EST 9293 SF)
Furnish all labor, materials, and equipment to complete the following work in accordance with the attached drawing and Section
C.
Project Description: Repair trail and replace deck at the Bowdoin NWR.
Mobilization/Demobilization, Bonding, Overhead, & Profit
Sawcut asphalt section and any appurtenances to complete the work (EST. 320 SF)
Deck and footing removal and any appurtenances to complete the work (EST 133 SY Footing and EST 157 SF Deck)
File details come from the government source that posted it. Updated .