This document contains special contract requirements for a federal solicitation to repair guardrails on the George Washington Memorial Parkway. Key details include:

  • The solicitation is issued by the National Park Service to repair guardrails along the George Washington Memorial Parkway. Work must follow load restrictions on park roads and bridges.

  • The contractor is responsible for any damages to existing features and must repair them to the CO's satisfaction. Utilities must be located according to specifications. Invoices are due by the 7th of each month.

  • Traffic control requirements include advance notification for closures, signage, barriers, and restricting work to non-peak hours. The contractor must provide a traffic control supervisor and plan.

  • Erosion and sediment control includes maintaining a SWPPP that is reviewed monthly. Removal of debris may not include burning or burying. Blasting is prohibited. Steel guardrails must be corrosion resistant.

  • Seeding and mulching specifications include rates, materials, and time periods. Temporary traffic control devices must meet MUTCD and crashworthiness standards.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Special Contract Requirements

Section 104. — CONTROL OF WORK

104.05. Add the following:

When hauling on National Park Service roads, do not exceed the load restrictions shown in Table 104-1.

Table 104-1

Load Restrictions

The CO may further load restriction or suspend hauling.

Operate loaded vehicles hauling material at speeds not exceeding 40 miles per hour or the posted speed limit, whichever is lower, and spaced at 500-foot minimum intervals. When hauling on bridges, do not exceed 25 miles per hour or the posted speed limit, whichever is lower, or operate more than 1 loaded hauling vehicle at a time.

Hauling will only be permitted from the nearest point of public access to the work site.

104.05. Add the following:

The Contractor is responsible for any damages caused by the construction activities to any existing feature, as determined by the CO. The Contractor must repair the damages to its original conditions within a timeframe established by the CO.

Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

107.02. Add the following to the sixth paragraph:

Locate utilities according to Section 645.

Section 108. — PROSECUTION AND PROGRESS

108.01. Add the following:

Single Units Gross Vehicle Weight (pounds) 2 axles 40,000 3 axles 48,000

4 or more axles 52,000 Combination Units Gross Vehicle Weight (pounds)

3 axles 57,000 4 axles 62,000

5 or more axles 66,000

Construction operations are limited as follows:

(a) No work will be permitted on National legal holidays.

(b) No work will be permitted on days with special events occurring in the vicinity, as determined by the CO.

Section 109. — MEASUREMENT AND PAYMENT

109.08(b). Add the following:

Submit invoices by the 7th day after the closing date. Invoices received after the 16th day following the closing date will not be accepted for payment processing that month.

Include late, unprocessed invoice submittals in the following month’s invoice.

109.08(c). Add the following:

Submit invoices through DOI bureaus bill Invoice Processing Platform (https://www.ipp.gov/).

Section 153. — CONTRACTOR QUALITY CONTROL

153.02. Add the following:

Submit a Quality Control Plan to the CO for approval 30 days prior to begin any guardrail construction activity.

Section 154. — CONTRACTOR SAMPLING AND TESTING

154.02. Add the following:

Submit proposals for using alternate AASHTO or state department of transportation approved test methods in writing for approval. Alternate methods may be allowed based on documented equivalence to the method specified.

154.05. Add the following:

For items accepted under Subsection 106.05, submit a copy of all current test results and pay factor calculations based on those tests on a weekly basis. When large quantities are produced, calculate pay factors as soon as possible. Use this information to make any necessary adjustments to operations to achieve acceptable pay factors. The Government may use the Contractor’s test results to determine final pay factors for acceptance.

https://www.ipp.gov/

Section 156. — PUBLIC TRAFFIC

156.04. Add the following:

Prior to beginning work, submit a milestone schedule that identifies any major closures, detours, or significant traffic impacts. After the start of work, submit a weekly two-week look-ahead schedule of planned activities including road and lane closure request(s). For any road, lane, shoulder, or sidewalk closures, submit a closure request form showing the following information:

• Date of request;

• Dates, times, and location of the work to be performed;

• Brief description of the work to be performed;

• Existing number of lanes and shoulders to be closed;

• Sidewalk and trail closures and detours;

• Field point of contact name and cell phone number;

• Traffic Control Plan and typical applications, including detours if any; and

• Enforcement request, if any. Provide advance notification for the type of closure requested as shown in Table 156-1.

Table 156-1

Advance Notification Requirements Lane Closure Type Minimum

Advance Notice Required (days)

Any road closure or a lane closure resulting in a significant impact on the flow of traffic, such as stopping traffic completely, closing two or more lanes, closing an exit or entrance ramp at freeway interchanges during peak hours, or a major change of traffic patterns. This type of closure may require extensive media and stakeholder notification efforts and coordination among various local and state agencies.

A lane or ramp closure resulting in minor or no impact on the flow of traffic, such as closing one lane on a four- lane freeway during off-peak traffic hours.

A closure that would close a shoulder (right or left) on a freeway or ramp. 7 Pedestrian/bicycle detour < 0.1 mile 7 Pedestrian/bicycle detour ≥ 0.1 mile 30

Work may be performed simultaneously on more than one site. Adjust the traffic layouts as necessary to coordinate traffic control operations between sites. Only one single lane closure in each direction of travel will be permitted at one time. The maximum length of a single lane closure will be one mile. Do not close any roads without prior approval from the CO.

Noncompliance will result in a reduction in payment to the Contractor equal to $3,000 per hour, for each hour or portion thereof. This reduction in payment will be subtracted from the Contractor’s progress payments and will be unrecoverable.

Submit a completed “Traffic Control Permit Application” form to the Maryland State Highway Administration (MSHA) at least 14 days before placing the Portable Changeable Message Sings (PCMS) within MSHA right-of-way.

Perform the work outside of the rush hour windows shown in Table 156-3.

Table 156-3

Rush Hours (Monday to Friday)

Morning (Inbound) 6:15 a.m. to 09:30 a.m.

Evening (Outbound) 3:00 p.m. to 7:00 p.m.

Do not install traffic control devices during the rush hours.

Before rush hours begin, remove materials, equipment, and non-applicable traffic control devices from the roadway and install the necessary traffic control devices to safely maintain traffic. The CO may direct the Contractor to stop operations to ensure the Contractor completes all work, including the appropriate setup of traffic control devices, before the rush hours begin. Failing to complete work and removing traffic control devices before a rush hour begins or installing or removing them during rush hours will be considered Contractor noncompliance.

Noncompliance will result in a reduction in payment to the Contractor equal to $3,000 per hour, for each hour or portion thereof.

This reduction in payment will be subtracted from the Contractor’s progress payments and will be unrecoverable.

156.05(f). Add the following:

Ensure that drains and inlets within the project limits are fully functional throughout the duration of the project.

156.07(d). Add the following:

The Contractor may use the GWMP maintenance yard as shown on the contract plans as a staging area. Obtain approval from the CO before using this location for staging.

Restore staging areas to their original condition as directed by the CO.

156.07(i). Delete the Subsection and substitute the following:

(i) Limit construction-caused delays to public traffic to a maximum of 15 minutes per passage through the project; and

156.08. Add the following:

Contractor must complete Schedule A during dayshifts. However, Contractor may complete Schedules B and C during dayshift or nightshift as approved by the CO.

156.09. Add the following:

Provide a full-time traffic control supervisor exclusively for the project. Ensure the traffic control supervisor is always on the site when work is being performed and available during non-work periods.

Section 157. — SOIL EROSION AND SEDIMENT CONTROL

157.01. Add the following:

This work includes updating and maintaining a SWPPP.

157.04. Add the following:

Update the Government-provided draft SWPPP in accordance with the EPA and State requirements using the information provided in the plans, specifications, and permits obtained for the project. Submit an electronic copy of the SWPPP to the CO at least 7 days before the preconstruction conference in accordance with Subsection 104.03 for approval. Update the SWPPP constantly throughout the project as work is performed and when changes are made to the project.

Maintain a copy of the current SWPPP on-site at all times.

157.16. Add the following:

The SWPPP will be evaluated under Subsection 106.02. The SWPPP will be jointly reviewed for accuracy and completeness by the CO and the Contractor before the submission of each monthly invoice. If the review finds that the SWPPP is not in compliance, payment of the Contractor’s invoice will be withheld until the SWPPP is brought up to date as outlined in Subsection 109.08(a).

157.18. Add the following:

Progress payments for updating and maintaining a SWPPP will be paid as follows:

• 25 percent of the pay item amount will be paid upon acceptance of the SWPPP.

• An additional 50 percent of the pay item amount will be prorated based on total work complete.

• The remaining portion of the pay item amount will be paid upon submittal of the NOT copy and evidence of its submission to the CO.

Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS

203.04(c). Add the following after the second sentence of the first paragraph:

On structures, use power-driven hand tools and other hand tools in accordance with Subsection 203.04(e).

203.05(b). Delete the Subsection and substitute the following:

(b) Burn. Burning is prohibited.

203.05(c). Delete the Subsection and substitute the following:

(c) Bury. Burying debris is prohibited.

Section 204. — EXCAVATION AND EMBANKMENT

204.06(a). Delete the Subsection and substitute the following:

Rock blasting is NOT permitted.

Section 617. — GUARDRAIL

617.03. Add the following:

Use steel guardrail material type IV – Corrosion resistant (weathering) steel, class B (10-gauge).

Prior to ordering and installing any material, submit a sample for approval to the CO for any material used under the Section 617.02. The sample size will be determined by the

CO.

Section 625. — TURF ESTABLISHMENT

625.04. Add the following to the second paragraph:

Apply agricultural limestone (85 percent CaCO3) at the rate of 3,100 pounds per acre.

625.06. Add the following:

Apply fertilizer at a rate of 700 pounds per acre for both methods.

625.07. Add the following:

Apply seed at the rates shown in Table 625-1 for both methods from April 15 to May 31, and September 15 to October 31.

Table 625-1 Composition of Seed Mix

Botanic Name Common Name

Rate (pounds per acre of pure live seed)

Lolium arundinaceum Tall Fescue 247

Poa pratensis Kentucky Bluegrass 13

TOTAL

625.08. Delete the text of the first paragraph and substitute the following:

Use straw mulch. Apply mulch the same day as seeding by the following methods:

625.08(a). Delete the second sentence and substitute the following:

Apply straw mulch uniformly at a rate of 5,500 pounds per acre (1- to 2-inch mat).

625.08(b). Add the following:

Apply straw mulch uniformly at a rate of 5,500 pounds per acre (1- to 2-inch mat).

Section 635. — TEMPORARY TRAFFIC CONTROL

635.04. Add the following:

Submit a Traffic Control Plan to the CO for approval 30 days prior to begin any guardrail construction activity.

Use a single lane closure layout to set up a work zone for this project according to the MUTCD, the VDOT WAPM, and as shown in the contract plans.

Provide and install two portable changeable message signs (PCMS) as part of your Traffic Control Plan.

635.04(g). Add the following:

The CO will provide a written notification of “marginal” or “unacceptable” traffic control devices that are not in compliance with this contract. If the Contractor fails to bring the “marginal” or “unacceptable” devices into compliance within a 24-hour period, the CO may assess a daily reduction in payment to the Contractor of $2,000 per day.

The CO may continue to assess the daily reduction in payment for each additional 24-hour period until the items are corrected. This reduction in payment will be subtracted from the Contractor’s progress payments and will be unrecoverable.

Use of this reduction in payment does not waive the CO’s right to suspend the work in whole or in part according to Subsection 108.05.

635.04(i). Add the following:

Submit a certification indicating that the devices are crashworthy as defined in Subsection 101.04.

635.07. Add the following:

Furnish 16-inch (minimum) square flags that are fluorescent orange or fluorescent red-orange in color. Mount flags on top of signs in accordance with the MUTCD.

635.11. Add the following after the first sentence of the first paragraph:

Use FHWA-approved temporary barriers meeting test level 2 (TL-2) criteria, according to industry crashworthiness standards. For a list of acceptable manufacturers and products, refer to the FHWA longitudinal barriers listing found at https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.

cfm?code=workzone

Install temporary barriers according to manufacturer’s recommendations.

635.18. Add the following:

Use FHWA-approved temporary crash cushions meeting test level 2 (TL-2) criteria, according to industry crashworthiness standards. For a list of acceptable manufacturers and products, refer to the FHWA Barrier System Terminals and Crash Cushion listing found at https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.

cfm?code=cushions

Section 645. — LOCATING UTILITIES

Description https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.cfm?code=workzone https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.cfm?code=workzone https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.cfm?code=cushions https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/listing.cfm?code=cushions

645.01 This work consists of locating and marking existing utilities.

Material

645.02 Replace excavated materials with equivalent materials that meet the applicable requirements of this specification.

Construction Requirements

645.03 General. Contact Miss Utility at 811 or 1-800-552-7001 at least two full business days before any excavation to have the utilities marked in the field.

If Miss Utility does not perform this service at the utilities in the field before any excavation begins. Notify the CO 48 hours before any excavation.

Perform work around Pepco underground utilities in accordance with Pepco’s Process and Procedure for Working in Close Proximity to Pepco Underground Facilities. Existing utilities have been generally located and shown on the as-built drawings provided as they are believed to exist. Exercise special care and extreme caution in order to protect and avoid damage to any utility company facilities.

Locate by test pit any utility that may conflict with the proposed work. If a conflict appears to exist, then notify the CO in writing immediately and provide information on the location and elevation of the utility so that the CO can adjust the proposed work. Restore the test pit area to its original condition.

The Government assumes no responsibility for the accuracy of locations shown in the as-built drawings. Locate and ensure the safety of all existing utilities.

Coordinate the repair of damage caused by construction with the utility owners. Pay costs associated with these repairs. See Subsection 107.02 for additional requirements.

645.04 Locating Utility. Use geophysical prospective techniques, including electromagnetic, sonic, or other energy field devices to establish alignment of utilities where applicable. When necessary, thread a metal rod through non-metallic utility pipes to locate them. Where neither method is feasible, locate the utility by perpendicular trench or test pits.

645.05 Excavation. Excavate carefully to the assume depth using hand tools as needed to avoid disturbing utilities. When excavating within roadway pavements where traffic is being maintained, excavate by air-vacuum methods or equivalent, keeping the area of disturbance to a minimum. Uncover the utility sufficiently to make accurate measurements.

645.06 Record. Describe the utility found (size, material, function), determine the elevation of the top of utility and prepare a field sketch of the pit. Indicate the date and the station and offset of the utility, noting whether the baseline or the centerline of proposed facility is being referenced. Submit one copy to the CO within 24 hours.

645.07 Marking. Mark the utility location by flags or paint. Maintain the markings, including repainting faded or damaged markings, for the duration of the project, or until the CO determines that the markings are no longer needed.

645.08 Restoration. Backfill using the excavated material or an approved equal. Thoroughly compact backfill material using compaction methods approved by the CO.

645.09 Acceptance. Locating utilities will be evaluated under Subsection 106.02.

Measurement

645.10 Measure the Section 645 items listed in the bid schedule according to Subsection 109.02.

Payment

645.11 The accepted quantities will be paid at the contract price per unit of measurement for the Section 645 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Progress payments for locating utilities by the lump sum will be paid as follows:

(a) 50 percent of the pay item amount will be paid after initial marking.

(b) An additional 25 percent of the pay item amount will be paid following completion of 50 percent of the original contract amount.

(c) Payment of the remaining portion of the pay item amount will be paid when the maintenance of the utility markings is no longer required as determined by the CO.

Section 104. — CONTROL OF WORK
Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Section 108. — PROSECUTION AND PROGRESS
Section 109. — MEASUREMENT AND PAYMENT
Section 153. — CONTRACTOR QUALITY CONTROL
Section 154. — CONTRACTOR SAMPLING AND TESTING
Section 156. — PUBLIC TRAFFIC
Section 157. — SOIL EROSION AND SEDIMENT CONTROL
Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Section 204. — EXCAVATION AND EMBANKMENT
Section 617. — GUARDRAIL
Section 625. — TURF ESTABLISHMENT
Section 635. — TEMPORARY TRAFFIC CONTROL
Section 645. — LOCATING UTILITIES