This contract price schedule outlines line item costs for electrical improvements at a communications site within Lake Mead National Recreation Area. The contractor will perform coordination with the local utility provider to establish a new commercial power connection, install new electrical infrastructure including a utility H-frame, meter, breaker panel, outlets and lighting, and upgrade an existing solar and generator backup system. Optional items include converting air conditioning to commercial power or replacing an existing unit. All costs to complete the work according to the statement of work must be included in the firm fixed price. The total evaluated price will consist of the sum of line items 0010 through 0130. The related federal contract opportunity is solicitation number 140P8122Q0054 issued by the National Park Service Pacific West Region to obtain these electrical improvements at the Lake Mead site.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Transmittal.pdf | ||
| A06_Nevada_Energy_Planning_Document.pdf | ||
| B03_General_Decision_NV20220024.pdf | ||
| Sol_140P8122Q0054.pdf | ||
| B08_Release_of_Claims.pdf | ||
| B08_Invoice_Payment_Request.docx | DOCX document | |
| A06_Nevada_Energy_Power_Availability.pdf | ||
| A06_Nevada_Energy_Cost_Estimate.pdf | ||
| A04_Statement_of_Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Price Schedule
Contract Line Item Number
(CLIN)
Contract Line Item Title
Quantity
Unit of
Measure
Total Price
Perform coordination with and execute the commercial power agreement for connection with NV Energy for a minimum of a 100amp single phase service.
a. NV Energy Project Number 3008671779
LS
Provide required trenching and conduit from the NV Energy junction box which is located approximately 500ft from the communication sites proposed utility demarcation point depicted in the picture from the Statement of Work.
Provide and install a new Utility H Frame inside of the communications site existing chain-link fence in the approximate location shown on the pictures from the Statement of Work. New Utility H Frame to be tied into the existing grounding system.
Provide and install a utility meter and disconnect on the Utility H Frame
Provide and install needed conduit and wire between the Utility H frame and the communications building
Provide and install a new 100amp (minimum) breaker panel in the communications shelter
Provide and install a minimum of four 2-way electrical outlets in the equipment building
Provide and install an exterior AC Powered entry/security light that is controlled by an interior switch and a photo sensor on the light structure
Provide and install two interior AC Powered light fixtures on the ceiling
Provide needed upgrades for the existing solar power system to allow for the connection of the new commercial power service that results in the primary powering of the communications site and its equipment from commercial power with a combination of solar and back up generator providing the backup power of the sites equipment
Provide and install a 12ft wide double swing vehicle gate in the existing east fence line and tie the gate into the existing grounding system
Total of Lines 0010 - 0110
Upgrade existing DC powered Airconditioning system to AC power (Optional Item)
Replace existing DC Powered Air Conditioner with a new AC powered unit (Optional Item)
Total of Lines 0010 - 0130
This is a firm fixed price requirement. All costs associated to perform the work in accordance to the Statement of Work shall be included. It is anticipated that award will be made as a lump sum.
For price evaluation purposes, price reasonableness will be based on the total sum of CLIN’s 0010-0130.
This is a firm fixed price requirement. All costs associated to perform the work in accordance to the Statement of Work shall be included. It is anticipated that award will be made as a lump sum.