A06_Nevada_Energy_Planning_Document.pdf
PDF 510 KB Posted
- Attached to
- Electrical Improvements, Lake Mead, NV Federal contract opportunity
- Solicitation number
- 140P8122Q0054
About this file
This document contains a planning memo from a utility distribution department and information on a related federal contract opportunity. The planning memo provides guidance for serving a new communication building near Consolidation Point in Lake Mead National Recreation Area, including connecting to an existing feeder, minimum capacity requirements, and no special directives at this time. The related federal contract opportunity is solicitation number 140P8122Q0054 for electrical improvements at Lake Mead National Recreation Area, issued by the Department of the Interior National Park Service Pacific West Region. The work involves consolidation point security improvements. The document provides relevant details on the utility project and associated federal contract opportunity in a concise and logically structured summary.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Transmittal.pdf | ||
| B03_General_Decision_NV20220024.pdf | ||
| B08_Contract_Price_Schedule.pdf | ||
| Sol_140P8122Q0054.pdf | ||
| B08_Release_of_Claims.pdf | ||
| B08_Invoice_Payment_Request.docx | DOCX document | |
| A06_Nevada_Energy_Power_Availability.pdf | ||
| A06_Nevada_Energy_Cost_Estimate.pdf | ||
| A04_Statement_of_Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Confidential Confidential
1/19/22 IO3008671779-CONSOLIDATION POINT COMMUNICATION BUILDING AVAILABILITY.docx Page 1 of 1
DISTRIBUTION PLANNING DEPARTMENT
PLANNING MEMO
Note
No capacity will be reserved for this project and the requirements to serve will be reevaluated and may be different following receipt of request for Binding Design/Formal Planning.
Minimum Requirements
1. Install any intercept DF-9’s as required. If a feeder extension and new fuse cabinet are needed, please contact Distribution Planning for a revision to this planning memo.
2. Serve from the source feeder near location (1).
3. Distribution Planning has no special directives for this project at this time.
Date: January 19, 2022 ISD: 5/21/22
Project ID: 3008671779 Source Fdr: PBC1208
EPD: 3 kVA Reviewed by:
Planner: Chris Hicks Cc:
Subject: CONSOLIDATION POINT COMMUNICATION BUILDING AVAILABILITY