This Statement of Work outlines requirements for replacing a concrete boat ramp at the Havasu National Wildlife Refuge in Topock, Arizona. The project involves removing an existing 70' x 16' x 1' concrete boat ramp and constructing a new ramp of identical dimensions at the 5-mile Landing Recreation Area.
The contractor must provide all equipment, materials, tools, and labor to remove the existing ramp, stockpile the old concrete on-site, compact the area with 51 tons of aggregate base, install #4 rebar every 2 feet on center, and pour approximately 60 yards of 3,000 PSI concrete with fiber and rolling stamp finish. Work must be completed within 120 days of award, with operations permitted Monday-Friday 7am-6pm except federal holidays. The project is set aside for small businesses with an estimated value between $25,000-$100,000. A site visit is scheduled for February 5, 2025 at 10:00am local time. The contracting agency is the Department of Interior Fish and Wildlife Service, and quotes should be submitted to Nicole Johnson via email.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140FC125Q0008
STATEMENT OF WORK
Havasu National Wildlife Refuge (NWR)
Boat Ramp Construction Lake Havasu National Wildlife Refuge Complex
Topock, Arizona January 2025
BACKGROUND
This Statement of Work summarizes the justification for a construction contract to replace an existing boat ramp with a new concrete boat ramp at a recreation area that provides public vessel access in the Topock Marsh Impoundment at Havasu NWR.
DESCRIPTION OF PROJECT NEEDS
A contracted vendor will need to remove a boat ramp consisting of concrete and rebar. The ramp is located at 5-mile Landing Recreation Area just north of Golden Shores, AZ on County Road 1. The ramp measures 70-feet long x 16-feet wide x 1-foot thick. The removed concrete is to be stockpiled on site for refuge staff disposal or to utilize as rip-raff within the recreational area.
The ramp is to be replaced with a boat ramp of identical dimensions. The underlying ground must be compacted with approximately 51 tons of aggregate base for the 16-foot x 70-foot section and approximately 4 tons of aggregate base for the 16-foot x 20-foot section of each dock. Forms must be set with #4 rebar every 2-feet on center.
Pour back and finish approximately 60 yards of concrete total for the entire project the concrete is to be 3,000 PSI with fiber and rolling stamp finished.
SCOPE OF WORK
The vendor will provide all equipment, materials, tools, and labor to remove and replace the boat ramp.
• Remove the boat ramp consisting of the following dimensions.
o 1’ x 16’ x 70’ with rebar
• Stockpile the old concrete and rebar for refuge staff disposal.
• Compact each area with 51 tons of aggregate base for the 70’ long section.
• Form and set ramps with #4 rebar set every 2’ on center.
• Pour back and finish approximately 30 yards of concrete for the boat ramp approximately
30 yards total for entire project. Concrete is to be 3,000 PSI with fiber and rolling stamp finished.
PLACE/ DELIVERY LOCATIONS
U.S. Fish and Wildlife Service Havasu National Wildlife Refuge 12750 Riverfront Parkway Mohave Valley, AZ 86440
PERIOD OF PERFORMANCE
Work must be completed within 120 days of contract award date.
HOURS OF OPERATION
The Contractor is responsible for conducting business, between the hours of 7:00 a.m. and 6:00 p.m. Monday through Friday except Federal holidays at the contractor’s option. The contractor must always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this contract when the government facility is not closed. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the workforce are essential. The facility is closed on recognized Federal holidays. The contractor is not required to perform work on these holidays:
New Year’s Day, January 1st or the Friday preceding or Monday following Martin Luther King’s Birthday, 3rd Monday in January President’s Day, 3rd Monday in February Memorial Day, Last Monday in May Juneteenth, June 19th or the Friday preceding or Monday following Independence Day, July 4th or the Friday preceding or Monday following Labor Day, 1st Monday in September Columbus Day, 2nd Monday in October Veteran’s Day, November 11th or the Friday preceding or Monday following Thanksgiving Day, 4th Thursday in November Christmas Day, December 25th or the Friday preceding or Monday following
PROJECT DIAGRAM
Exis ng Boat Ramp
Photo taken at the top of the boat ramp where the 16’x20’ pad is to be installed
From the bo om of the exis ng ramp.
Side shot of exis ng ramp
Photo taken from the top of the exis ng ramp. There is a pile of concrete near the construc on site (arrow). This is where the concrete removed from the exis ng ramp is to be stored for refuge personnel to move at a later date.
REFERENCE PHOTOS
These photos are from another project that was completed on the refuge last fiscal year.