B08_Att_1_Scope_of_Work_GRCA_250440.pdf

PDF 492 KB Posted

Attached to
GRCA 250440 Shuttle Bus Facility Federal contract opportunity
Solicitation number
140P2024R0028
Issued by
Department of the Interior National Park Service National Office

About this file

This document is the Scope of Work for the GRCA 250440 Shuttle Bus Facility project, a design-build solicitation issued by the National Park Service.

The project involves the design and construction of a new shuttle bus maintenance and administration facility at Grand Canyon National Park, including removal of the existing facility and site restoration. The new facility will include administration areas, maintenance areas with 4 vehicle work bays, bus parking for up to 42 buses with charging systems, and a separate bus wash building. The scope also includes performing required environmental and sustainability requirements, developing the design documents, and providing construction support services. Key deliverables and schedule milestones are specified, along with NPS contact information. The project aims to address deferred maintenance issues and provide adequate space to support the park's shuttle bus system, which has experienced significant ridership growth.

View the file

Other files for this federal contract opportunity

Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRAND CANYON NATIONAL PARK

GRAND CANYON VILLAGE, ARIZONA

SOLICITATION 140P2024R0028

SHUTTLE BUS FACILITY

GRCA 250440

DESIGN-BUILD SCOPE OF WORK

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

March 12, 2024

Table of Contents

1.0 PROJECT INTRODUCTION

1.1 SCOPE

1.2 NPS PROVIDED PROJECT WEBSITE

1.3 LOCATION

1.4 BACKGROUND

1.5 DESCRIPTION

1.6 SCHEDULE

DB DESIGN DEVELOPMENT DOCUMENTS:

100% DRAFT DB CONSTRUCTION DOCUMENTS:

100% COMPLETE DB CONSTRUCTION DOCUMENTS:

COMPLETE STAMPED AND SIGNED DB CONSTRUCTION DOCUMENTS:

CONSTRUCTION:

AS-CONSTRUCTED DRAWINGS:

1.7 NPS CONTACTS AND ADDRESS:

2.0 PROJECT REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

2.1.2 MAINTAIN THE CLIN STRUCTURE AS IDENTIFIED IN SPECIFICATION

SECTION 01 27 00

2.1.3 PROGRESS PAYMENTS

2.1.4 PROJECT MEETINGS

2.1.5 PROJECT SCHEDULE

2.2 DESIGN REQUIREMENTS

2.2.1 DB DESIGN DEVELOPMENT DOCUMENTS AND DB CONSTRUCTION

DOCUMENTS

2.2.2 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS FOR DESIGN

2.3 CONSTRUCTION REQUIREMENTS

2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS

2.3.2 SCHEDULE OF VALUES

2.3.3 CONSTRUCTION SUPPORT

2.3.4 SUBMITTALS DURING CONSTRUCTION

2.3.5 CONSTRUCTION COORDINATION

2.3.6 DIGITAL IMAGES

2.3.7 QUALITY CONTROL

2.3.8 WORKING HOUR RESTRICTIONS

2.3.9 TEMPORARY SERVICES

2.3.10 ACCESS

2.3.11 PRESERVATION OF ADJACENT FEATURES

2.3.12 EXISTING UTILITIES

2.3.13 HAULING RESTRICTIONS

2.3.14 ACCIDENT PREVENTION

2.3.15 TEMPORARY CONTROLS

2.3.16 FIELD ENGINEERING

2.3.17 PROJECT CLOSE-OUT

2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

2.4 SAMPLE AND TEMPLATE

3.0 PERFORMANCE REQUIREMENTS

3.1 DESIGN IMPERATIVES

3.2 SUSTAINABILITY

3.3 INTEGRATED DESIGN PRINCIPLES

3.4 FACILITY PERFORMANCE

3.5 ELEMENTS AND PRODUCTS

4.0 TECHNICAL REQUIREMENTS

4.1 SUBSTRUCTURE

4.2 SHELL

4.3 INTERIORS

4.4 FACILITY SERVICES

4.5 EQUIPMENT AND FURNISHINGS

4.6 HAZARDOUS WASTE REMEDIATION

4.7 SITE

4.8 PROCESS

1.0 PROJECT INTRODUCTION

Park Acronym and PMIS Number: GRCA 250440

Project Title: Shuttle Bus Facility

Project Drawing Number: GRCA/113/182929

1.1 Scope

In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.

Architect-Engineer (A/E) Services required in this RFP shall be performed by licensed

Architects and Engineers registered in Arizona.

The work of this contract shall be performed in accordance with the Denver Service Center

(DSC) Design-Build (DB) Workflows website.

The DB homepage includes links to design phases describing required workflow process from

Predesign (PD) through Construction Documents. Each design phase webpage contains links to definitions, forms, templates, samples, and guidelines.

The DB homepage also includes links to the Design Standards and Design Deliverables sections which provide design requirements and criteria that shall be used for completing the work of this contract:

• Design Standards are arranged by discipline and/or specialty.

• DB Design Deliverables - Content and Format Requirements:

o Design phase submission requirements for:

o Technical content o Submission format

In addition, the Information section in the DB Workflows website has links directly to:

• Definitions: A list of terms relevant to design and construction in National Parks.

• Forms/Templates/Samples/Guidelines: A list of forms, templates, samples, and guidelines used for a typical project.

o Division 1 Specifications Templates: These templates represent standard information that may need clarification and addition to the DB RFP template on some projects.

• Law/Regulations/Polices/Guidance: A list of sources for retrieving laws, regulations, policies, and guidance applicable to NPS projects.

• Quality Assurance (QA) Guideline & Review Checklists: Overview of the DSC QA

Process for reviewing Design Documents.

https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designbuild.htm https://www.nps.gov/dscw/information.htm https://www.nps.gov/dscw/definitions.htm https://www.nps.gov/dscw/publicforms.htm https://www.nps.gov/dscw/publicforms.htm#div1 https://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=235859 https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/qaguideline.htm

In case of conflict between this contract and the DSC DB Workflows website, this contract shall take precedence and shall be used in lieu of conflicting portions.

The A/E remains fully responsible for determining if the standards or provisions cited on the

DSC DB Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the

Contracting Officer.

1.2 NPS Provided Project Website

Use the NPS provided Project website to host and manage project communication and documentation until Final Completion. The project website will be used for:

• Project directory

• Project correspondence

• Meeting agendas and minutes

• Contract modifications documentation and logs

• RFI (Request for Information) form and processing

• Task and issue management

• Photo documentation

• Baseline schedule, schedule updates and calendar management

• Submittal form and processing

• Drawing and specification document hosting, viewing, and updating

• Online document collaboration

• Reminder and tracking functions

• Archiving functions

• Notification of submittal and RFI statuses and current responsible party

1.3 Location

This project is located on Shuttle Bus Road Grand Canyon Village, Grand Canyon National

Park, AZ.

1.4 Background

Grand Canyon has had a shuttle bus transit system since 1974. Since its inception, the system has grown to include 30 buses for four routes. It is the largest bus transit system in the NPS with a record 7.5 million boardings in 2016; ridership is comparable to that of mid-sized cities throughout the United States. The existing shuttle bus system is operated through a ten-year service contract that requires the operator to maintain the park-owned buses.

The existing bus maintenance and operations facility is not adequate for current transit operations and does not allow room for growth, which is needed to meet current visitation levels.

It consists of a small, two-bay metal building garage, which was originally built in the 1970s and upgraded in the 1990s to accommodate compressed natural gas vehicles. The existing facility also includes a prefabricated office trailer for operations staff and dispatch and a separate storage building. The combined existing facilities are about 5,000 square feet on an approximately 1.5-acre site.

A replacement facility addresses deferred maintenance both on the facility itself and on buses that are maintained in the facility. It would ensure that buses are maintained properly and that workers have adequate and safe places to maintain buses and operate the shuttle bus system. A new facility would provide adequate space for drivers to train and would realize efficiencies of being able to train numerous drivers at once. A larger site with properly design parking and circulation will result in more efficient end of the day operations, such as fueling and cleaning of vehicles.

Schematic Design Basis of Design Report was completed for this project in August 2020. The

Basis of Design Report is for reference and bidding purposes. All design shall be prepared by the design build contractor utilizing latest applicable standards, codes, and regulations.

1.5 Description

The proposed approach places all functions in one building to include administration, maintenance, and storage. Administration areas would have offices for staff and dispatch; a training space for drivers; restrooms and showers. Maintenance areas would have 4 vehicle work bays with lifts; a wash bay; parts storage; office space for lead mechanic; and a room with lockers for mechanics. The maintenance area would accommodate alternative fuel types including battery electric buses (BEBs), and longer buses. In addition to the admin/maintenance building, bus washing would be provided in a separate building. The near 3-acre site would accommodate bus parking for up to 42 buses with charging systems, and a separate parking for up to 60 personally owned vehicles (POVs) for bus drivers and admin staff; vehicular circulation to promote safety and accommodate efficiencies in bus cleaning and end of day operations; a fence around the compound; and access to the adjacent CNG fueling facility. Once complete, the existing facility shall be removed, and the site rehabilitated.

The scope of this project consists of the design and preparation of the plans, specifications, and estimates for construction, acquiring government furnished permits, and supplemental services.

NPS anticipates the possibility of individual early works packages for certain elements as design is finalized on other work elements.

1.6 Schedule

Complete work in this RFP according to following schedule:

DB Design Development Documents:

Submit DB Design Development Documents no later than 120 calendar days after Notice to

Proceed.

Complete NPS Review no later than 15 calendar days after submitting DB Design Development

Documents.

100% Draft DB Construction Documents:

Continue work on 100% Draft DB Construction Documents during DB Design Development

Documents review. After receiving DB Design Development review comments, address and incorporate comments in 100% Draft DB Construction Documents.

Submit 100% Draft DB Construction Documents and responses to NPS Review form with responses to DB Design Development Documents no later than 90 calendar days after submitting

DB Design Development Documents.

Complete NPS Review no later than 15 calendar days after receiving 100% Draft DB

Construction Documents.

100% Complete DB Construction Documents:

Submit 100% Complete DB Construction Documents and NPS Review form with responses to

100% Draft DB Construction Documents review comments no later than 30 calendar days after submitting 100% Draft DB Construction Documents.

Complete NPS review no later than 15 calendar days after receiving 100% Complete DB

Construction Documents.

Complete Stamped and Signed DB Construction Documents:

Submit Complete Stamped and Signed DB Construction Documents and NPS Review form with responses to 100% Complete DB Construction Documents review comments no later than 15 calendar days after receiving NPS review comments.

Construction:

Construction begins when Contracting Officer issues DB Notice to Proceed. Early works packages will be allowed to specific release work elements, but will require full design review of those individual packages prior to commencement of that construction activity.

Complete construction no later than 730 calendar days after Notice to Proceed of contract.

As-Constructed Drawings:

Complete As-Constructed Drawings no later than 21 calendar days after Substantial Completion.

Submit DB Design Development Documents, DB Construction Documents, and As-Constructed

Drawings to NPS Project Manager (PM).

1.7 NPS Contacts and Address:

Contractual:

Contracting Officer (CO): Jeremiah Rogers, 303-969-2633, Jeremiah_Rogers@nps.gov

Contract Specialist (CS): Brenda Smith, Brenda_Smith@nps.gov

Technical:

Project Manager (PM)/ Contracting Officer’s Representative (COR): Mike Pisano, 303-987-

6887, Michael_Pisano@nps.gov

Project Specialist (PS): Nate Ritchie, 720-930-7617, Nathan_Ritchie@nps.gov

Address:

National Park Service - Denver Service Center

12795 West Alameda Parkway

Post Office Box 25287

Denver, Colorado 80225

2.0 PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 Scope of Work and Project Summary/Requirements

The project will consist of the design and construction of:

• Removal of existing facility and revegetation of the site.

• The proposed scope of work includes providing a new shuttle bus maintenance and administration facility, across the street from the existing bus maintenance facility, on undisturbed ground. The proposed location is adjacent to the existing CNG fueling facility - all other improvements shown and/or described in the following narratives are new construction/disturbance. The project site is located at the South Rim of the Grand

Canyon, east of Shuttle Bus Road (east of the existing shuttle bus maintenance area) and northeast of the existing Grand Canyon Park Maintenance Warehouse Complex

(constructed in 2003). Tusayan is the nearest town, approximately 6 miles due south of the Shuttle Bus Maintenance area. For construction purposes, Flagstaff, AZ and Phoenix, AZ are the nearest major metropolitan areas.

• The total site disturbance is approximately 5.65 acres. The preferred alternative offers a circulation system facilitated by two drives: a north drive associated with bus and maintenance vehicles and a west drive to access the main entrance to the building and employee and visitor parking. Forty-two bus parking spaces, seven maintenance vehicles and fifty-nine visitor/employee parking spaces are accommodated.

• NOTE: This project will be conducted near other major construction efforts in the vicinity including the Tans-Canyon Waterline (includes an expansion of the helibase for aerial construction operations and a construction road) with an FY26 completion, and the mailto:Jeremiah_Rogers@nps.gov

South Rim Wastewater Treatment Plant approximate start FY25. Durations are anticipated.

The project will include:

• Construct project

• Create and provide operations and maintenance manual.

• Design site, site utilities, building and foundation system.

• Life Cycle cost analysis

• Perform geotechnical analysis.

• Provide as-constructed drawings.

• Provide schedule of construction work.

• Review Schematic Designs provided in the RFP package.

• Review site data.

• Secure work area and provide for continued access to the facility.

• Submit DB Design Development and DB Construction Documents for review and approval, as required.

• Submit list of required permits.

• Upon award, determine and provide design schedule of work.

2.1.2 Maintain the CLIN structure as identified in Specification Section 01 27 00.

2.1.3 Progress Payments

Design Phase - Progress payments will be based on percentage of work complete on items listed in approved schedule of values.

Construction Phase - Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment. DB Contractor shall verify percent complete under direction of the

Contracting Officer Representative unless Contracting Officer waives this requirement in a specific instance. DB Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested.

DB Contractor shall furnish to Contracting Officer originals of field notes and other records relating to basis for payment. Contracting Officer shall use as necessary to determine final amount of progress payments. DB Contractor shall retain copies of material furnished to

Contracting Officer.

2.1.4 Project Meetings

Predesign Meeting

After award of contract and acceptance of Performance and Payment bonds, Contracting Officer will arrange a design meeting with DB Contractor. Meeting agenda shall include the following as a minimum:

• Areas available for use by DB Contractor

• Access requirements of the Park

• Commissioning (review requirements in ASHRAE 0-2005 paragraphs 6 and 7)

• Design schedule

• Environmental and sustainability requirements

• Natural and Cultural Resource Protection

• Payments to DB Contractor

• Review and emphasize Park needs and design objectives.

• Modifications during design

• Schedule of Values

• Submittals during design

Preconstruction Meeting

Submit Project Requirement deliverables a minimum of one week prior to Preconstruction

Meeting.

• Accident Prevention Program

• DB Contractor’s Commissioning Plan

• Evidence of liability insurance coverage and workman’s compensation for DB Contractor and Subcontractors

• Historic Preservation Treatment Program

• Letter designating your Project Superintendent

• List of required permits

• List of Subcontractors for project (same as proposal)

• Project Schedule with construction portion fully developed

• Quality Control Plan

• Schedule of Values

• Storm Water Pollution Prevention Plan (SWPPP) Submittal process

• Waste Management Plan

• Written statements from Subcontractors certifying compliance with applicable labor standard clauses

After 100% Complete DB Construction Documents are approved (or completed portions of DB

Construction Documents necessary for fast tracking the project), and before start of construction, Contracting Officer will arrange on-site Preconstruction meeting with DB Contractor.

Progress Meetings

DB Contractor shall participate in weekly telephone conference calls with Contracting Officer and other project team members with updates to following meeting agenda items:

• Approval of minutes of previous meetings.

• Modifications

• Review of off-site fabrication and delivery.

• Requests for Information (RFI) and issues.

• Schedule update. (Provide updated Critical Path Method schedule.)

• Status of Project Record Drawings and Operation & Maintenance (O&M) Manuals.

• Submittal status.

• Work in progress and projected.

• Other business relating to work.

2.1.5 Project Schedule

General: DB Contractor shall upload project schedule to NPS/DSC SharePoint Project website and provide two (2) color copies after award and before design meeting. Schedule shall include detailed design phase with design deliverable submission dates, review periods, and summary construction schedule with important milestones included for both phases.

Fully develop construction portion of project schedule and submit to Contracting Officer on

NPS/DSC SharePoint Project website before Preconstruction meeting or construction begins.

Update project schedule monthly throughout contract period until project substantial completion.

Status date of each schedule update shall be 10 calendar days before progress payment request date.

Construction work cannot begin until Government approval is obtained for either:

• Entire set of 100% Complete DB Construction Documents.

• Fast track construction: 100% Complete DB Construction Documents affecting work to be constructed.

Purpose: Project schedule ensures adequate planning, coordinating, scheduling, and reporting of

DB Contractor’s design and construction activities. Project schedule will assist DB Contractor and Contracting Officer to monitor work progress, evaluate proposed changes, and process DB

Contractor's monthly progress payment requests.

Software: Latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.

Schedule Development: Project schedule shall cover entire contract period. Late finish date is same as contract’s established completion date.

DB Contractor shall use Critical Path Method with limited use of lead or lag durations between schedule activities. DB Contractor's project schedule shall consist of procurement activities

(including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities.

DB Contractor's project schedule shall consist of, but not be limited to, the following for each activity:

• Identify activities and numbers numerically (maximum 5-digit). Number activities in increments of 10.

• Concisely describe work represented by activity (maximum 48 characters). Avoid using non-standard abbreviations. Limit work related to each activity to one work trade.

• Activity duration shall be in whole calendar days with maximum duration 21 calendar days each, unless otherwise approved by Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

DB Contractor shall ensure project schedule includes own work and Subcontractor work.

Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. DB Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be DB Contractor's best estimate of time required to complete activity, considering scope and resources planned. Resource loading of each activity shall list personnel by labor category and equipment type, and capacity proposed to complete activity in duration shown. Include permit requirements and constraints. Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within contract time.

Project Schedule Updates

Monthly Updates: Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of Contracting Officer, DB Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, DB Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.

Narrative: Include in report:

• Brief description actual progress made during update period.

• Actual and potential delaying activities.

• Impediments to progress.

• Issues related to inclement weather.

• Progress toward established milestones.

• Project float.

• Brief description of work anticipated to be performed in next month.

• Identify minor revisions to schedule for evaluation and accepted or rejected.

As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after contract completion date, at a minimum, include the following in narrative with submission:

• Known delays.

• Actions taken to get back on schedule.

• Pending modifications.

• Impediments or constraints affecting progress.

Progress Payments: Update currently accepted construction schedule monthly. If DB

Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor

Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or DB Contractor revises project schedule, DB Contractor shall submit to

Contracting Officer a written time impact analysis illustrating influence of each modification, change, delay, or DB Contractor’s request on the contract time.

• Time Extensions: Activity delays shall not automatically mean an extension of contract time is warranted or due to DB Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time. Time extensions will be granted according with terms of contract.

• Float: Float is not for exclusive use or benefit for NPS or DB Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.

2.2 Design Requirements

2.2.1 DB Design Development Documents and DB Construction Documents

Prepare DB Design Development Documents and DB Construction Documents using English

System of Weights and Measurements and according to DSC Design Standards and DSC Design

Deliverables - Content and Format Requirements for DB Design Development Documents and

DB Construction Documents.

List salient characteristics for products and materials specified. Refer to Guide for Specifiers.

Deliverables

• Submit documents in native and Portable Document Format (PDF) file formats.

• PDF files shall be unlocked to allow printing and saving.

• See DB Submittal Requirements, Design Deliverables.

The following deliverables are required (refer to Section 1.6 for schedule):

https://www.nps.gov/dscw/del_designdevelopdb.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=242817 https://www.nps.gov/dscw/del_submitformatdb.htm

• Submit DB Design Development Documents for Review o Draft DB Design Development Drawings o draft level technical performance specifications Product File o Statement of Structural Tests and Special Inspections o Design Calculations

• Submit 100% Draft DB Construction Documents for individual work packages for

Review o 100% Draft DB Construction Drawings o 100% draft level technical performance specifications or similar to provide NPS a clear understanding of products and their characteristics to be used,.

o Product File o Statement of Structural Tests and Special Inspections o Design Calculations

▪ Complete calculations, including an arc flash study, coordination study, lightning risk assessment, fault current, and voltage drop are required to be engineered by and submitted for review.

o Checklists for internal review of drawings, specifications, calculations, and cost estimates

▪ Required documents for each submission are included and complete per contract requirements.

▪ Required documents have been through a Quality Control (QC) review.

NPS requires documentation and submittal of QC work performed.

o NPS Review form with responses to DB Design Development Documents review comments.

• Submit 100% Complete DB Construction Documents for individual work packages for

Final Approval prior to beginning those work activities o 100% Complete DB Construction Drawings o Technical Performance Specifications o Product File o Statement of Structural Tests and Special Inspections o Design Calculations o Checklists for internal review of drawings, specifications, calculations, and cost estimates o Required documents for each submission are included and complete per contract requirements.

o Required documents have been through a QC review. NPS requires documentation and submittal of QC work performed.

o NPS Review form with responses to 100% Draft DB Construction Documents review comments.

• Submit Complete Stamped and Signed DB Construction Documents o Upon final approval of 100% Complete DB Construction Documents, submit

Complete Stamped and Signed DB Construction Documents per following table for

NPS archiving and general use.

o The recipient of the files is Technical Information Center.

o Final Construction Drawings shall be printed from native Computer Aided Design

(CAD)/BIM (Building Information Modeling) equivalent software (e.g., AutoCAD .dwg). Final Construction Drawings printed from secondary software

(e.g., Adobe .pdf) are not acceptable as they often result in off-scale product.

o A/E team to stamp and sign cover sheet.

o Filled out Submittal List

COMPLETE STAMPED AND SIGNED

DB CONSTRUCTION DOCUMENTS

FILE FORMATS

DB Construction Drawings PDF & CAD/BIM

Performance Specifications PDF & Microsoft Word

Product File PDF

Statement of Structural Tests and Special Inspections PDF & Microsoft Word

Supplemental Design Reports (if applicable) PDF

Design Calculations PDF

Checklists for internal review of drawings, specifications, calculations, and cost estimates PDF & Microsoft Excel

NPS Review form with responses to 100% Complete DB Construction

Documents review comments PDF & Microsoft Excel

2.2.2 Environmental and Sustainability Requirements for Design

NPS established environmental and sustainability requirements for project. Notify Contracting

Officer if conflicts arise between performance of work and environmental and sustainability requirements. NPS does not intend to limit alternative means of achieving these requirements.

For sustainability requirements for design, see 3.0 Performance Requirements below and attachment NPS Project Sustainability Checklist. Complete checklist by concisely explaining how each credit/requirement will be met.

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to Performance Requirements and NPS

Project Sustainability Checklist. General requirements:

• Indoor Air: Follow recommended approach of Sheet Metal and Air Conditioning

Contractor’s National Association Indoor Air Quality Guidelines for Occupied Buildings, 2007. Conduct building flush-out prior to occupancy according to Federal requirements.

• Site Disturbance: Minimize construction limits of project to reduce impact on site.

• Toxic Chemicals: Avoid materials that can leach toxic chemicals into ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water. Refer to NPS Project Sustainability Checklist for additional requirements.

https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=387018

• Soil Erosion: Protect against erosion and topsoil depletion according to SWPPP. Projects with a footprint exceeding 5,000 square feet must use site planning, design, construction, and maintenance strategies to control storm water runoff. Reference Stormwater

Requirements included under Section 438 of the Energy Independence and Security Act.

• Habitats: Protect natural habitats and ecological systems on facility site as identified in

Environmental Assessment.

• Noise: Minimize noise during construction. Operate power equipment according to local noise restrictions.

• Waste Management: Employ processes ensuring minimal waste output and in landfills.

Recycling is a requirement of this project. Specific recycling goals were established in

NPS Project Sustainability Checklist. Legally dispose materials unsuitable for recycling at public or private dumping areas outside the Park.

• Compliance Mitigations: Refer to attachment CE New Shuttle Bus Facility 68273 for mitigations required.

DB Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing environmental and sustainability requirements of this project. Distribute copies of environmental and sustainability requirements to Job Site Foreman and each Subcontractor.

Waste Management Plan: Prior to scheduled Preconstruction meeting, DB Contractor shall submit draft Waste Management Plan to Contracting Officer for approval. Develop and implement according to ASTM E1609 and as required in contract documents. Plan shall include, but not be limited to:

• List of recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.

• List of proposed materials to be reused or recycled.

• List of materials that cannot be recycled or reused with explanation or justification.

• Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.

• Describe means of transporting recyclable materials and estimate frequency of emptying bins.

• Identity person or persons responsible for ensuring project recycling goals are achieved.

• Revise and resubmit Plan per Contracting Officer. Approval of DB Contractor’s Plan does not relieve DB Contractor of complying with applicable environmental regulations.

Progress Documentation: Supplemental to Waste Management Plan, document solid waste disposal, diversion, and cost/revenue analysis, and submit completed worksheet monthly. See

Project Waste Management Plan Worksheet Sample, provided at Pre-construction Meeting, and report totals to date for column headings.

Prior to commencement of work, schedule and conduct meeting with Contracting Officer.

Discuss proposed Waste Management Plan and develop mutual understanding of details of environmental protection.

Minimize Construction Impacts

Implement following mitigation measures to minimize impacts of construction activities:

Soil Erosion: Protect against erosion and topsoil depletion. SWPPP is required.

Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds. Incorporate following procedures:

• Obtain fill, rock, or additional topsoil needed from a Government approved source.

• Use approved native seed and/or plants and revegetate areas disturbed by construction.

Vegetation Salvage and Revegetation Plan: Required for this project. For revegetation efforts, the park will grow and provide seed and plants for this work. Contractor shall coordinate directly with GRCA vegetation management staff to determine appropriate plant types, density, and any requirements for preparing the soil. The contract will require some temporary irrigation source with reclaimed water. Contractor shall incorporate Park policies regarding vegetation and site restoration. Policy related to revegetation will be referenced in NPS Management Policies 2006

(Section 9.1.3.2).

Special Status Species: To protect unknown or undiscovered threatened, endangered, or special status species, construction contract will include provisions for these discoveries. DB Contractor should contact Park for direction to evaluate special species at the site.

Visitor Experience: Incorporate following mitigation measures to minimize impacts of construction activities on visitor experience:

Air and Water Pollution Control: Air quality impacts are expected to be temporary and localized. To minimize these impacts, take following actions:

• To reduce tailpipe emissions, do not leave construction equipment idling longer than necessary for safety and mechanical reasons.

• To reduce construction dust, apply water to problem areas. Limit equipment to fenced project area to minimize soil disturbance and dust generation.

• Take necessary reasonable measures to reduce air and water pollution with material or equipment used during construction. Keep volatile wastes in covered containers.

• SWPPP: Submit a SWPPP, according to applicable State Water Resources Control

Board's requirements, to Contracting Officer for approval. (See Technical Requirements.)

Before starting construction, DB Contractor shall implement approved SWPPP.

Archaeological Monitoring: Ground disturbance must be monitored by an archaeologist.

Coordinate with the Contracting Officer minimum of two weeks in advance for coordination of monitoring. Refer to compliance document attachment CE New Shuttle Bus Facility 68273.

Cultural Resources: An Archeological Monitor will be present at work site. If archeological resources are discovered at project site while Archeological Monitor is absent, immediately stop work in vicinity of discovery and report discovery to Contracting Officer.

https://www.nps.gov/policy/mp/policies.html

2.3.2 Schedule of Values

After contract award and before Design Meeting, submit schedule of dollar value based on

Contract Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. Total costs for component parts of work shall equal contract line item amount for that lump-sum item.

Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead, and profit in total dollar value of unit price item and in component parts of work for each lump-sum item, as described below. Include mobilization, general condition costs, overhead, or profit as separate items.

Do not break down unit price items. Only use contract line item amount for unit price items.

Total cost of items shall equal contract sum. Schedule of Values will form basis for progress payments.

Before first progress payment is processed, DB Contractor and Contracting Officer shall agree on an acceptable Schedule of Values. A cost loaded project schedule is an acceptable substitute for a schedule of values in some cases.

2.3.3 Construction Support

Staging Areas

Limit construction sites to smallest feasible area. Carefully control ground disturbance and site management to prevent undue damage to vegetation, soils, and archeological resources, and to minimize air, water, soil, and noise pollution.

Staging is limited in or near construction area for a construction office or trailer. Locate construction equipment and material storage in previously disturbed areas near construction site.

Obtain Contracting Officer’s approval for staging area location for construction equipment. Once construction is complete, return staging areas to pre-construction conditions. Consult with

Contracting Officer and develop standards and methods for determining standards.

Structures: Trailers, Storage, Field Offices, Staging Area, and Sheds: Contracting Officer to approve location.

DB Contractor's Field Office: Structurally sound construction and weather tight. Location determined by NPS before issuing Notice to Proceed.

Storage Sheds: If used, provide weather tight sheds or other covered facilities for materials subject to weather damage and remove temporary water, sewer, sanitary facilities and electric utilities upon project completion. Remove temporary utility connections.

Construction Camp

Establishment of a construction camp will not be permitted.

Construction Zones

Before construction activity, use construction barrier, plastic, or portable fencing, approved by

Contracting Officer, to define construction zone, minimum area required for construction.

Clearly state protection measures in construction specifications and instruct workers to avoid conducting activities beyond construction zone.

Protection of Public

Use fence, barricade, or other means to block immediate work area and prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs according to current version of Manual on Uniform Traffic Control Devices.

DB Contractor shall protect tree trunks and root systems of trees in, or adjacent to, work areas.

Special Construction Requirements

N/A

Parking of Construction Vehicles

Limit to existing roads in legally designated areas and within approved staging area(s).

2.3.4 Submittals During Construction

Construction Submittals:

Construction Submittal Types

Action Submittals: Written, graphic information, and physical samples that require

Government’s responsive action.

• Product Data: Collect information in single submittal for each element of construction and type of product or equipment.

• Shop Drawings: Prepare project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of Contract Documents or standard printed data

(unless submittal of CAD/BIM Drawings is otherwise permitted).

• Samples: Submit samples of kind, color, pattern, and texture for reviewing characteristics with other elements and comparing between submittal and actual component as delivered and installed.

• Construction Materials: DB Contractor is encouraged to submit, for approval, products made of recycled or environmentally responsible material. NPS will make every effort to approve these materials.

Informational Submittals: Written information not requiring Government’s responsive action.

Submittals may be rejected for not complying with requirements.

• Prepare and submit Informational Submittals required by individual Specification

Sections.

• Informational submittals include, but are not limited to, Coordination Drawings LEED™

Submittals Product Data, Certificates, Test reports, Manufacturer’s instructions, Division

01 Management Plans, etc.

Contractor’s Review

Review each submittal for coordination with other work of contract and compliance Contract

Documents. Note corrections and field dimensions.

General Submittal Procedures

Prepare and submit submittals shown in 4.0 Technical Requirements below. See individual technical sections for details on requirements for each.

Contracting Officer reserves the right to require submittals in addition to those identified in individual sections.

Coordination: Coordinate submittal preparation and processing with construction activity performance. Review for legibility, accuracy, completeness, and compliance with Contract

Documents.

• Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities requiring sequential activity.

• Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

Processing Time: Allow enough time for submittal review and re-submittals. Start review when

Contracting Officer, or designee, receives email indicating submittal has been posted on the

NPS/DSC SharePoint project website. After Contracting Officer completes review, an email is sent to the DB Contractor indicating submittal has been processed. Contract time extensions will not be authorized if submittals are not transmitted with enough time to permit processing, including re-submittals.

• Action Submittals: Allow 30 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

• Informational Submittals: Allow 10 calendar days for review of each submittal.

Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

• Electronic Submittal Review Form (CM-SPE): Use NPS/DSC SharePoint Project website to access and complete this form and to transmit submittals. For actions taken on submittal items, this form must accompany.

o Complete general information at the top.

o Provide required information based on submittal type.

o Attach related documents.

o Sign Electronic Submittal Review Form in Contractor section towards bottom and select Submit when complete.

• Physical Samples: Complete Electronic Submittal Review Form on the NPS/DSC

SharePoint Project website as described above. Deliver physical sample to Contracting

Officer, or designee, on site for processing. Document comments and actions on

Electronic Submittal Review Form.

Contracting Officer's Review

Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate appropriate action on Electronic Submittal

Review Form in one of three ways:

• Approved: Acceptable with no corrections required.

• Approved with Notations: Minor corrections or clarifications required. Comments are clear and no further review required. DB Contractor shall address review comments when proceeding with work.

• Disapproved - Resubmit: Rejected for not according with contract or requiring major corrections or clarifications. Contracting Officer will identify reasons for disapproval. DB

Contractor shall revise and resubmit with changes clearly identified.

Informational Submittals: Contracting Officer will review submittals and accept or reject.

Submittal List

Use the Submittal List with Review Estimate Template, provided at Pre-construction Meeting, to provide overall summary of submittal requirements, not a comprehensive list. Technical requirements indicate type and specify submittal requirements. Contract terms and conditions apply regardless of indication on submittal list.

Use for Construction

Use only final submittals marked with Approved or Approved with Notations. Ensure notations are incorporated and, at a minimum, keep one copy of final approved submittal on site during construction.

2.3.5 Construction Coordination

Notification: Contracting Officer provides necessary written notification and/or direction to DB

Contractor. An on-site independent Construction Management Representative (CMR) coordinates DB Contractor’s construction efforts with Park Staff’s daily operations and transmits/receives correspondence between DSC and DB Contractor. CMR does not have authority to accept or reject work, authorize changes to contract terms and conditions, or obligate

NPS for time or money.

2.3.6 Digital Images

Provide a minimum of 10 existing condition images and 5 images per day documenting construction. Upload digital images to NPS DSC SharePoint Project website and identify sets of images with date, location, title, description, and other information pertinent to subject captured in photos.

Capture digital images documenting construction progress and problems. For example, capture items that will be seen later. Post digital images of each work activity weekly or as directed by

Contracting Officer.

2.3.7 Quality Control

General

DB Contractor is responsible for quality of work. Independent testing laboratory is responsible for testing. Inspect and test work as needed to ensure quality of materials, workmanship, construction, and finish, and to ensure functional performance is in compliance with applicable specifications and drawings. Contactor is responsible for all testing and testing requirements per specifications.

DB Contractor accepts ultimate responsibility, liability, and duty to control quality of services provided to the Government as stipulated in FAR Part 36.609-2. DB Contractor shall be responsible for professional quality, technical accuracy, and coordination of designs, drawings, specifications, and other services furnished by DB Contractor, their Employees, Agents, Assignees, and Subcontractors under the contract. DB Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other services.

DB Contractor shall demonstrate existence of a QC system used for work submitted to NPS. DB

Contractor and Subcontractors shall use this QC system and, at a minimum, include:

• Coordination of drawings and specifications within each discipline and between disciplines.

• Verification that documents to be submitted are accurate and correct.

• Checklists for internal review of drawings, specifications, calculations, and cost estimates.

o Required documents for each submission are included and complete per contract requirements.

o Required documents have been through a QC review. NPS requires documentation and submittal of QC work performed.

Use Accessibility Inspection Report (Contractor Quality Control (CQC) & Final) to document compliance with Architectural Barriers Act (ABA) Accessibility Standards. As needed, inspect at various stages of construction ensuring finished product meets guidelines. Complete applicable sections of Accessibility Inspection Report and attach to CMR & CQC Daily Report https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=6109253 https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=362820

(Construction Management Representative (CMR) and Contractor Quality Control (CQC)) form

(download and complete using Adobe Acrobat).

CQC Supervisor will complete CQC Daily Reports.

Person performing tests will complete test reports.

Contracting Officer may designate test locations.

Quality Control Staff

CQC Supervisor will not be assigned other duties.

CQC Supervisor, designated by DB Construction Contractor, shall be on project site whenever contract work is in progress.

DB Construction Contractor's job supervisory staff may assist CQC Supervisor supplement, as necessary, by adding certified testing technicians.

Testing Laboratory and Equipment:

• Employ certified independent laboratories to perform sampling and testing. Testing laboratory organization shall be certified for type of testing work.

• Calibrate measuring devices, laboratory equipment, and instruments at established intervals against certified standards according to National Bureau of Standards requirements. Upon request, Government will make available measuring and testing devices for verification tests.

Submittals

Quality Control Plan: Prior to Preconstruction meeting, submit written CQC plan for approval.

If plan requires revisions or corrections, DB Construction Contractor shall resubmit plan within

10 calendar days.

Government reserves right to require changes to the plan during contract period as necessary to obtain quality specified.

No change in the approved plan may be made without written concurrence by Contracting

Officer.

The plan shall include:

• A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

• A copy of a letter of direction to CQC Supervisor outlining assigned duties.

• Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

• Methods of performing, documenting, and enforcing quality control of work.

• Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

Daily Reports: Submit and include inspections and tests on first workday following date covered by report. Use Daily Test Report Information Report Sheet and CMR & CQC Daily

Report forms that will be provided at the Pre-Construction Meeting.

Test Reports: Submit Daily Test Information Sheets with CQC Daily Reports.

Submit failing test results and proposed remedial actions within four hours of noted deficiency.

Submit three copies of complete test results no later than one calendar day after test performed.

If CQC plan and CQC Daily Reports are not submitted as specified, Contracting Officer may retain payments until a plan is accepted and implemented. Or Contracting Officer may retain payments for work completed on days with no CQC Daily Reports.

Accessibility Inspection Report: Submit Accessibility Inspection Report (CQC and Final) no later than 3 calendar days after inspection.

Off-Site Inspection Reports: Submit prior to shipment.

Execution

Off-Site-Control: Items fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.

On-Site Control: Notify Contracting Officer at least 48 hours in advance of preparatory phase meeting.

Notify Contracting Officer at least 24 hours in advance of initial and follow-up phases.

Quality Control Phases

Preparatory Phase: Perform before…