B08_40581251_Statement_of_Work.pdf

PDF 766 KB Posted

Attached to
Asphalt Paving - Arches National Park
Solicitation number
140P1222Q0076
Issued by

View the file

Other files

File Type Posted
Sol_140P1222Q0076.pdf PDF
B08_40581251_Attachments.pdf PDF
B08_40581251_Wage_Determination.pdf PDF
B08_40581251_Bid_Schedule.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARCHES NATIONAL PARK

WINDOWS ASPHALT PAVING

STATEMENT OF WORK &

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

INTERMOUNTAIN REGION 7

MAY 2022

WINDOWS ASPHALT PAVING TOC-1

ARCHES NATIONAL PARK 230673

TABLE OF CONTENTS

DIVISION 1 – GENERAL REQUIREMENTS

011000 Summary of Work…………………………………………………………………………………………………………………….

012700 Definition of Bid Items………………………………………………………………………………………………………………

013100 Project Meetings………………………………………………………………………………………………………………………

013200 Schedules…………………………………………………………………………………………………………………………………

013300 Submittals………………………………………………………………………………………………………………………………..

013600 Accident Prevention…………………………………………………………………………………………………………………

014300 Contractor Quality Control……………………………………………………………………………………………………….

015100 Temporary Services………………………………………………………………………………………………………………….

015600 Barriers and Traffic Control………………………………………………………………………………………………………

015700 Temporary Controls…………………………………………………………………………………………………………………

016000 Material and Equipment………………………………………………………………………………………………………….

017700 Project Closeout………………………………………………………………………………………………………………………

DIVISION 31 – EARTHWORK

310000 Watering………………………………………………………………………………………………………………………………….

312213 Excavation and Grading……………………………………………………………………………………………………………

312216 Finish Grading………………………………………………………………………………………………………………………….

DIVISION 32 -EXTERIOR IMPROVEMENTS

321126 Prime and Tack Coat…………………………………………………………………………………………………………………

321216 Hot Mix Asphalt……………………………………………………………………………………………………………………….

WINDOWS ASPHALT PAVING 011000-1

ARCHES NATIONAL PARK SUMMARY OF WORK

Statement of Work: Windows Paving

Work Location: Arches National Park, Moab, UT

May 2021

PROJECT SPECIFICATIONS

PART 1 GENERAL

1.1 DESCRIPTION

A. Synopsis. Supply and install hot mix asphalt pavement for parking areas and curbing located in the Windows Loop area of Arches National Park. The required pavement installation includes the associated removal of existing road base material, regrading and compaction of the base coarse material. A three-inch finished layer of asphalt pavement is to be installed in the areas designated in the Attachment A-plan sheet P10. The Contractor’s pavement installation is to seamlessly match the existing pavement finished grade at all asphalt cuts and to ensure the drainage slopes as indicated in the plan sheets. The Windows Road will be closed to the public for three consecutive days in order for the base removal, grading and pavement installation work to be completed in total. The road closure is a significant impact to the Park;

therefore, it is imperative that the Contractor meet the scheduling requirements agreed upon.

B. Location. The work site is located in Arches National Park, 5 miles North of Moab, Utah, off U.S. Highway 191. The Windows area is accessed by traveling 9 miles along the Park Scenic Drive, and turning east just past the Balanced Rock on to Windows Road. The Windows area is

2.5 miles away at the east end of the loop drive.

C. Period of Performance: The period of performance for this project is a three, consecutive week-day, window from 10/3/2022 to 10/20/2022. Example dates: October 4-6, or October 18-20.

D. Warranty: The Contractor shall warranty the materials and workmanship for one year and shall replace or repair any defective work. Defective work that is the result of the Park’s roadway bench, such as inadequate compaction or improper drainage, is not covered under this warranty.

E. Site Visit. The Park encourages potential Contractors to visit the site to determine the extent of the pavement installation in the roadways that are included in the statement of work.

F. Submittals. Provide electronic cut sheets (in PDF format) that document that the product meets the requirements of 2.1.A Salient Features, and provide the trade name, name and address of the manufacturer, recommended application temperature and methods. If the cut sheets do not specifically address items in 2.1.A then a letter from the manufacturer documenting that the product does meet the salient features will be accepted. If more than one product type is listed on the cut sheet, the product to be supplied must be noted on the cut sheet or called out on a separate sheet.

This information must be included with the quote, even if an approved product is being supplied.

1. Provide cut sheets for the hot mix asphalt meeting the requirements of 2.1A.

WINDOWS ASPHALT PAVING 011000-2

2. Provide a temporary traffic control plan (TTC) for review by the Park safety officer at least one month before commencing work. The traffic control plan is to be developed in accordance with Part 6, Temporary Controls of the FHWA Manual on Uniform Traffic Control Devices (MUTCD).

3. Provide a safety plan that addresses the following:

a) Use EM 385-1-1, Appendix A as a guide for a basic accident prevention plan.

b) Name of responsible on-site supervisor to carry out the safety program.

c) Local Contact Information. Provide a list, which includes telephone numbers and addresses, of the nearest: ambulance, physician, hospital, fire department, and police.

d) Emergency Equipment. Provide a list of Contractor first aid kit locations. At a minimum the Contractor shall have at least one first aid kit on site. Provide a list of Contractor fire extinguisher locations and type. At a minimum the Contractor shall have at least one 20 pound class C fire extinguisher on site.

e) Hazardous work phases and materials. Briefly outline each phase of the work, and identify any hazardous materials, associated hazards, and the methods proposed to ensure protection of property and safety of the public, Park personnel, and the Contractor's employees.

f) Personal Protective Equipment (PPE). Provide a list of required PPE and a statement requiring PPE be worn by employees.

g) Address site and job specific safety hazards (i.e., traffic control, hot asphalt hazards, etc.).

1.2 PROJECT CONDITIONS

A. Work days and hours. The Contractor shall perform the services required under this contract from Monday through Thursday from 6:00 am until 6:00 am (during daylight hours). No work is to be performed on weekends or Federal Holidays. Any work requested outside of the designated times and dates shall first be approved by Brad Larsen, (435) 719-2152, prior to work commencing. The Contractor shall pay overtime for any employees working over 40 hours in a week as required by the Davis Bacon Act and this contract.

B. Services. Power – The Contractor shall provide for all their power needs. Cell phone coverage is spotty or non-existent within the Park. NPS Phones are not available to the Contractor.

Restrooms are available for Contractor use at the Visitor Center and a various locations within the Park. Food and Lodging. Commercial Lodging and Restaurants and Groceries are available in Moab at several locations. Motels can typically be fully booked in the spring and fall seasons.

C. Staging Areas. The staging areas are located outside of the maintenance shop fencing and at the Balanced Rock storage area. Vehicles and equipment may be parked overnight along the pull outs within the Windows loop roadway during the road closure period. The Windows Road shall be kept accessible to emergency vehicle traffic if necessary.

WINDOWS ASPHALT PAVING 011000-3

D. Limits of Disturbance. The Contractor shall keep all vehicles and equipment on the roadway surface. Vegetation, structures and natural features are to be protected from work related impacts at all times. The Contractor is to keep vehicles and equipment properly maintained and to address fluid leaks and material spills promptly.

E. Existing Utilities: There are no utilities in the construction zone.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the State of Utah load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage that may result from moving of equipment.

1.3 FIELD VERIFICATION: The Contractor shall field verify all new and existing dimensions affecting the work of this contract before beginning construction or ordering products.

PART 2 PRODUCTS NOT USED

PART 3 EXECUTION NOT USED

END OF SECTION

PART 4 MEASUREMENT AND PAYMENT

4.1 Measurement. Products will be measured and paid according to the bid schedule.

WINDOWS ASPHALT PAVING 012700-1

ARCHES NATIONAL PARK DEFINITION OF BID ITEMS

SECTION 012700

DEFINITION OF BID ITEMS

PART 1 GENERAL

1.1 DESCRIPTION

A. The intent of this section is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends, and another begins.

B. If no bid item exists for a portion of the work, include the costs in a related bid item.

1.2 MEASUREMENT AND PAYMENT

A. Measurement and payment for contract work shall be made only for and under those pay items included in the schedule of items. All other work materials will be considered as included in the payment for the items shown.

B. All measurement will be by units defined and determined according to U.S. standard measure and by the following:

1. A mile is 5280 linear feet measured along the roadway.

2. Lump sum quantities denote one complete unit of work required or as described in this section. They will not be measured.

C. Payment will be based on final quantities as measured in the field for unit price bid items, except for bid item 4 will be paid at the full amount, with no variation either way.

1.3 BID ITEM NO. 1 - GENERAL CONDITIONS: This bid item consists of the following items:

bonds, temporary construction controls, traffic control, preparation of the accident plan and construction schedule. Work also includes all labor costs for the Prime Contractor’s Project Superintendent before, during and after construction. These costs also include on-site per diem, vehicle and mobilization costs for the Project Superintendent. Payment will be made at the contract lump-sum price.

1.4 BID ITEM NO 2: This line item consists of Quality Control work, which includes: preparation of the quality control plan, survey control, and inspection testing. Payment will be made at the contract lump-sum price.

1.5 BID ITEM NO 3: This line item consists of approximately 20 TON of asphalt removal. Work includes asphalt cutting, removal, hauling off and recycling the asphalt. Payment will be made at the contract unit price.

1.6 BID ITEM NO 4: This line item is to excavate and remove the base on the existing parking area, and prep the subgrade for the new base. The 185 CY is the estimated in place material, and the pay item is for in place material. The CY rate includes truck time (17 ton dump truck) with driver, and all costs associated with excavating, loading, pushing up pile at unloading site, and preparation of the subgrade for new base. This line item is being estimated in CY due to the removed base will be stockpiled at the Park’s Balanced Rock boneyard, and there will not be a method to weigh for tonnage hauled. Haul distance is 3.2 miles one way. The estimated in

WINDOWS ASPHALT PAVING 012700-2

ARCHES NATIONAL PARK DEFINITION OF BID ITEMS

place CY was calculated as (18,136 SF) x (3” thickness/12”/FT) x (1.1 Safety Factor)/27 FT/CY ~ 185 CY. The estimate was based on the absolutely thinnest asphalt section believed to be in place, and this should be conservative in the Contractor’s favor. This line item will be paid at 185 CY with no variation in quantity either way. The Contractor may verify the 18,136 SF at any time if there is any concern about the quantity.

Payment will be made at the contract unit price.

1 .7 BID ITEM NO 5: This line item consists of approximately 2,018 SY of finish grading.

Payment will be made at the contract unit price.

1 .8 BID ITEM NO 6: This line item is for approximately 330 TON of hot mixture asphalt paving.

Lift thickness shall be 3” with prime coat underneath. Tack coat along all existing asphalt and concrete joints. Payment will be made at the contract unit price.

PART 2 PRODUCTS NOT USED.

PART 3 EXECUTION NOT USED.

WINDOWS ASPHALT PAVING 013100-1

ARCHES NATIONAL PARK PROJECT MEETINGS

SECTION 013100

PROJECT MEETINGS

1.1 PRECONSTRUCTION CONFERENCE

A. Before the start of construction, the Contracting Officer will arrange an on-site meeting with the Contractor. The meeting agenda will include the following as a minimum:

1. Correspondence procedures

2. Designation of responsible personnel

3. Labor standards provisions

4. Payroll reports

5. Contract modifications

6. Payments to Contractor

7. Subcontractors

8. National Park Service regulations

9. Accident prevention program (including name of responsible supervisor)

10. Accident reporting

11. Contractor’s Quality Control Program

12. Documents required under the contract

13. Park rules and regulations

14. Saturday, Sunday, holiday and night work

15. Safety program (compliance with the "Accident Prevention" clause of the contract)

16. Tentative construction schedule

17. Traffic Control

18. Submittals

19. Claim Procedures

20. Project closeout requirements

1.2 PROGRESS MEETINGS

A. The short period of performance for this contract removes the need for recurring progress meetings.

4.1 PROJECT MEETINGS

A. Payment will be included in the bid item to which this work relates.

WINDOWS ASPHALT PAVING 013200-1

ARCHES NATIONAL PARK SCHEDULES

SECTION 013200

SCHEDULES

1 .1 DESCRIPTION: The work of this section consists of schedule requirements before and during construction.

1 .2 SCHEDULES

A. As specified in Section 013300.

B. Submit a Construction Schedule with the bid proposal.

1. Construction Schedule: Submit two copies of the Construction Schedule. Show each bid item and area of work and break down work into the smallest element. The schedule shall correspond to each specification section and shall identify the critical path of the project.

C. As soon as possible after Notice of Award and before beginning any work, submit Schedule of

Values. Contracting Officer’s Representative will review the Schedule of Values for format and content.

1. Schedule of Values:

a. Submit a schedule of dollar values based on the Contract Bid Schedule. Include bond costs, mobilization, general condition costs, overhead, and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include bond premiums, mobilization, general condition costs, overhead, or profit as separate items; however, payment for bond premiums can be made based upon evidence of payment to the surety. Bond premiums may be shown as a separate item.

b. Break down each lump-sum bid item into component parts of work for which progress payments may be requested. The total costs for the component parts of work shall equal the bid amount for that lump-sum item. The Contracting Officer’s Representative may request data to verify accuracy of dollar values. Do not break down unit price bid items. Use only the bid amount for unit price items.

c. The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments as provided for in the terms of the contract.

WINDOWS ASPHALT PAVING 013300-1

ARCHES NATIONAL PARK SUBMITTALS

SECTION 013300

SUBMITTALS

PART 1 GENERAL

1 .1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.

1 .2 RELATED REQUIREMENTS: Closeout submittals - Section 017700.

1 .3 SUBMITTAL AND APPROVAL PROCEDURES

A. All submittals shall be transmitted using National Park Service form CM 16, Rev 06/06, unless submittal is required with the bid proposal. (A copy of the form is included at the end of this section.) No action will be taken on a submittal item unless accompanied by the transmittal form.

B. As specified in the individual sections, forward submittals to Contracting Officer’s Representative at least five days before need for approval. Provide submittals as PDF documents.

Hard copies will not be accepted.

C. Contracting Officer’s Representative reserves the right to require submittals in addition to those called for in individual sections.

D. Approved Equals:

1. For each item proposed as an "approved equal," submit supporting data, including:

a. Drawings and samples as appropriate.

b. Comparison of the characteristics of the proposed item with that specified.

c. Changes required in other elements of the work because of the substitution.

d. Name, address, and telephone number of vendor.

2. A request for approval constitutes a representation that Contractor:

a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

b. Will provide the same warranties for the proposed item as for the item specified.

c. Has determined that the proposed item is compatible with interfacing items.

d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

e. Waives all claims for additional expenses that may be incurred as a result of the substitution.

3. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.

E. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.

F. Submittal Identification:

1. All sets of shop drawings, manufacturer's catalog sheets, samples, and other documents submitted to the Contracting Officer’s Representative must have the identification information on the submittal. Identification shall include the park name, package number, project title, contract number, and transmittal number.

WINDOWS ASPHALT PAVING 013300-2

2. Identification information shall be applied to the bottom right margin on each page.

Identification information on samples shall be applied to the most readily visible area on the sample or on tags attached to sample.

G. Submittal Numbering:

1. Number each submittal consecutively.

2. For re-submittals use the original submittal number, plus a letter suffix beginning with A.

3. Additional re-submittals of the same item shall contain the original number with the next consecutive letter.

H. Contracting Officer’s Representative's Review:

1. Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out;

submittals are not coordinated; or submittals do not show evidence of Contractor's approval.

2. Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.

3. After reviewing submittals, the Contracting Officer’s Representative will return one copy of form DSC-1(CS) and one copy of applicable (marked up) submittal sheets to the Contractor. Shop drawing review notations will be returned on the reproducible original shop drawing. All other submitted items will be retained. The Contractor is responsible for producing additional copies for his/her own use.

4. The returned submittal will be marked in one of three ways as defined below:

a. APPROVED: Acceptable with no corrections.

b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required.

All comments are clear, and no further review is required. The Contractor shall address all review comments when proceeding with the work.

c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer’s Representative will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

1.4 REQUIRED SUBMITTALS

A. The following is a list of required submittals. If a submittal is required in the specifications but omitted from this list it is still required.

1. Proposed Notice to Proceed start date

2. Construction Schedule

3. Accident Prevention Plan

4. Contractor Quality Control Plan with subcontractors listed

5. Traffic Control Plan if different than what is shown on the drawings

6. As built Drawings

7. Asphalt Job Mix Formula

WINDOWS ASPHALT PAVING 013300-3

4 .1 SUBMITTALS

A. Payment will be included in the bid item to which this work relates.

WINDOWS ASPHALT PAVING 013600-1

ARCHES NATIONAL PARK ACCIDENT PREVENTION

SECTION 013600

ACCIDENT PREVENTION

1 .1 DESCRIPTION

A. The work of this section establishes the framework necessary for establishing an effective accident prevention program and providing a safe environment for all personnel and visitors. In accordance with generally accepted construction practices, the Contractor will be solely and completely responsible for safety conditions on the work of the project, including the safety of all persons and property during the performance of the work. The Contractor shall comply with all federal, state, and local safety laws and regulations. The Contracting Officer’s Representatives (COR) review of this accident prevention plan does not alleviate the Contractor from the burden and all responsibility of providing safe working conditions. The COR’s review and the guidelines of this section are intended solely as an aid to the Contractor.

1 .2 SUBMITTALS

A. Per section 013300

B. Accident Prevention Program: As soon after award as possible, submit for acceptance an accident prevention program. This plan must be accepted before the pre-construction meeting can take place. The COR will review the proposed program for compliance with the requirements of these specifications. Under no circumstances is onsite work allowed to be performed until this program has been accepted. The plan shall address the items listed below as a minimum.

Ensure that all employees have access to a copy of this plan on-site.

1. Name of responsible on-site supervisor to carry out the program.

2. Local Contact Information. Provide a list, which includes telephone numbers and addresses, of the nearest: ambulance, physician, hospital, fire department, and police.

3. Emergency Equipment. Provide a list of onsite first aid kit locations. At a minimum the Contractor shall have at least one first aid kit onsite. Provide a list of onsite fire extinguisher locations and type. At a minimum the Contractor shall have at least one UL class 2A, 2 ½ gallon water type fire extinguisher, and one UL class 10, Type I, 15 pound, B:C carbon dioxide fire extinguisher onsite.

4. Emergency Medical Training. Provide documentation of employees with current emergency medical training. The Contractor shall ensure that there is always one person with emergency medical training on-site. Emergency medical training shall include first aid and CPR, and be at least an 8 hour course. Training shall be provided by the Red Cross, the American Heart Association or equivalent. The Park will identify Park staff that has emergency medical training at the pre-construction meeting.

5. Hazardous work phases and materials. Briefly outline each phase of the work and any hazardous material, the hazards associated with each major phase and or materials, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. At a minimum address the following for this project: working around heavy equipment, and heat exhaustion.

WINDOWS ASPHALT PAVING 013600-2

6. Personal Protective Equipment (PPE). Define applicable PPE for employees, and when and under what circumstances it must be utilized. For this project hard hats and safety vests are required at all times. A statement requiring the aforementioned two items be worn shall be included under this item number in the safety plan submittal.

1 .3 QUALITY ASSURANCE

A. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees:

1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.

Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

1 .4 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires.

Notify Contracting Officer’s Representative immediately in the event of a reportable accident.

Within 7 days of a reportable accident, fill out and forward to Contracting Officer’s Representative an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.

B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer’s

Representative as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

PART 2 PRODUCTS

2 .1 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

2 .2 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of NIOSH.

WINDOWS ASPHALT PAVING 013600-3

PART 3 EXECUTION

3 .1 EMERGENCY INSTRUCTIONS

A. All employees shall have on-site access to the safety plan.

3 .2 FIRE AND LIFE SAFETY

A. Provide appropriate UL listed fire-extinguishers.

3 .3 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3 .4 SAFETY MEETINGS

A. Conduct one weekly safety meeting each week. Submit documentation to the COR.

3 .5 TRAINING

A. Emergency Medical Training: Provide training as required for the accident prevention plan.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

WINDOWS ASPHALT PAVING 014300-1

ARCHES NATIONAL PARK CONTRACTOR QUALITY CONTROL

SECTION 014300

CONTRACTOR QUALITY

CONTROL

1 .1 DESCRIPTION: The work of this section consists of preparing and executing a quality control program.

Work will include providing construction control surveys and providing an independent testing lab for compaction testing.

1 .2 RELATED REQUIREMENTS: "Inspection of Construction" clause of the contract.

1 .3 SUBMITTALS

A. As specified in section 013300.

B. Quality Control Plan:

1. At the time of the preconstruction conference, submit for approval a written Contractor Quality Control (CQC) plan. The plan shall identify the proposed survey subcontractor and their plan for construction control. The plan shall identify the proposed independent testing inspector.

2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.

4. No change in the approved plan may be made without written concurrence by the Contracting Officer’s Representative.

5. The plan shall include:

a. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

d. Methods of performing, documenting, and enforcing quality control of all work.

e. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

f. The Contractor shall clearly show their schedule for construction control surveys, compaction testing of UBC placed and their schedule for density testing of the asphalt.

C. Off-Site Inspection Reports: Submit prior to shipment.

1 .4 QUALITY ASSURANCE

A. General:

1. The quality of all work shall be the responsibility of the Contractor. Construction control surveys shall be by a licensed surveyor, and compaction testing shall be the responsibility of an independent testing company.

WINDOWS ASPHALT PAVING 014300-2

2. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance complies with applicable specifications and drawings.

3. The Contracting Officer’s Representative may designate locations of tests.

B. Quality Control Staff:

1. The Contractor's Quality Control Supervisor may also perform the duties of Project Superintendent and shall be on the project site whenever contract work is in progress.

2. The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor, supplemented as necessary by additional certified testing technicians.

C. Construction Control Surveys

1. All surveys shall be by a licensed surveyor.

2. The construction control surveys shall document the slopes and grades of the old parking lot, and then provide adequate construction control for the re-establishment of those grades after the removal of the asphalt and base, and then the re-construction.

D. Testing Laboratory and Equipment:

1. Employ certified independent laboratories to perform sampling and testing. The testing laboratory organization shall be certified for the type of testing work to be done.

2. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards. Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.

PART 3 EXECUTION.

3 .1 OFF-SITE CONTROL: Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.

3 .2 ON-SITE CONTROL

A. Notification:

1. Notify the Contracting Officer’s Representative at least 48 hours in advance of the preparatory phase meeting.

2. Notify the Contracting Officer’s Representative at least 24 hours in advance of the initial and follow- up phases.

B. Preparatory Phase: Perform before beginning each feature of work.

1. Review control submittal requirements with personnel directly responsible for the quality control work. As a minimum, the Contractor's Quality Control Supervisor and the foreman responsible for the feature of work shall be in attendance.

2. Review all applicable specifications sections and drawings related to the feature of work.

3. Ensure that provisions have been made for field control testing.

WINDOWS ASPHALT PAVING 014300-3

4. Examine the work area to ensure that all preliminary work has been completed.

5. Verify all field dimensions and advise the Contracting Officer’s Representative of discrepancies with contract documents.

6. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.

C. Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:

1. Quality of on-going work is unacceptable.

2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.

3. Work on a particular feature of work is resumed after a substantial period of inactivity.

3 .3 ENFORCEMENT: The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer’s Representative.

WINDOWS ASPHALT PAVING 015100-1

ARCHES NATIONAL PARK TEMPORARY SERVICES

SECTION 015100

TEMPORARY SERVICES

A. The work of this section consists of providing temporary services required for Contractor's performance of the work of this contract.

2 .1 GENERAL

A. Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

2 .2 SANITARY FACILITIES

A. The Contractor may utilize the Park restroom facilities located at the Windows loop.

2 .3 FIRE PROTECTION EQUIPMENT

A. A minimum of one UL Class 2A, 2-1/2 gallon, water type, stored pressure extinguisher and one UL Class 10, Type I, 15 pound, B:C carbon dioxide fire extinguisher shall be provided by the Contractor.

3 .1 ELECTRICITY AND LIGHTING

A. No electrical service is available on site for Contractor's use. If needed, the Contractor shall supply portable generators to provide for power and lighting.

3 .2 TELEPHONE

A. No telephone service is available on site for Contractor's use.

3 .3 WATER

A. The Contractor is to provide and apply all water for construction purposes. There is no available construction water supply within the Park.

B. Furnish cool, potable water for construction personnel in locations convenient to work stations.

3 .4 FIRE PREVENTION AND PROTECTION

A. Responsible Person: A capable and qualified person shall be placed in charge of fire protection.

The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.

B. Hazard Control: Take all necessary precautions to prevent fire during construction.

WINDOWS ASPHALT PAVING 015100-2

ARCHES NATIONAL PARK TEMPORARY SERVICES

C. Spark Arresters:

1. Written determinations of periods and areas of potential fire hazard will be issued by Contracting Officer’s Representative.

2. Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the U. S. Forest Service.

D. Service and Refueling Areas: Locate areas a minimum of 100 feet from the work area. Shut down equipment before refueling.

E. Smoking: Smoking near service and refueling areas is prohibited.

WINDOWS ASPHALT PAVING 015600-1

ARCHES NATIONAL PARK BARRIERS AND TRAFFIC CONTROL

SECTION 015600

BARRIERS AND TRAFFIC CONTROL

A. The work of this section consists of providing a traffic barrier and traffic personnel at the junction of the Park Scenic Drive and the Windows Road. The barrier purpose is to prevent visitor traffic at all times on the Windows Road during the paving construction time frame. The Contractor’s traffic personnel are to allow construction and NPS vehicle traffic access and to prevent unauthorized vehicle travel on the Windows Road. Pedestrian and bicycle traffic are not allowed on the Windows Road at all times during the construction road closure.

B. The Park has a supply of plastic barricades and portable fence sections that are available for the Contractor to use.

1 .2 SUBMITTAL

A. As specified in Section 013300. Layout of all traffic control products on a plan drawing.

2 .1 GENERAL

A. Material may be new or used, but shall be suitable for intended purpose. Fences and barriers shall be structurally adequate and neat in appearance.

2 .2 FENCING

A. Safety Barrier Fence: Orange plastic fence, minimum height, 4 feet.

2 .3 BARRICADES AND SIGNS

A. Products shall meet the standards of the Manual on Uniform Traffic Control Devices (MUTCD), Part VI, 2009 edition.

B. Provide an adequate number of flashing warning lights at the barricades during nighttime closures.

2 .4 BARRIER TAPE

A. Banner Guard, imprinted with "CAUTION: CONSTRUCTION AREA", manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.

WINDOWS ASPHALT PAVING 015600-2

ARCHES NATIONAL PARK BARRIERS AND TRAFFIC CONTROL

PART 3 EXECUTION

3 .1 PROTECTION OF PUBLIC

A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

B. Erect and maintain barricades, lights, danger signals, and warning signs in accordance with

MUTCD-2009.

C. Illuminate barricades and obstructions at night; keep safety lights burning from sunset to sunrise.

D. Adequately barricade and post open cuts in or adjacent to thoroughfares.

E. Protect pedestrian traffic by guardrails or fences.

F. Erect and maintain sufficient detour signs at road closures and along detour routes.

G. Barrier Tape: Install where directed by COR. Keep a minimum of two rolls on site at all times.

3.2 TRAFFIC CONTROL

A. Provide the traffic control as required on the drawings.

B. Provide an adequate amount of traffic control personnel to keep visitor traffic from parking along the turn onto the Windows Road and to allow authorized vehicle traffic through the barricades.

C. All traffic control devices including warning signs shall be properly placed and in operation before any construction is allowed to start.

D. The Park will advise visitors that the Windows Parking area is Closed and under Construction.

E. If at any time the Contracting Officers Representative (COR) determines that proper provisions for safe traffic control are not provided or maintained, work will be ordered to be suspended until the proper level is maintained.

F. In cases of serious or willful disregard for safety of the public or his employees by the Contractor, the COR may proceed forthwith to place traffic control measures in proper condition and deduct the cost thereof from monies due or becoming due to the Contractor.

G. The Contractor shall designate or otherwise provide personnel to furnish continuous surveillance over their traffic control operations. This designee will also be available at night to respond to calls involving damage to barricades, lights, signs, etc., either through weather events, vandalism or traffic accident. The Contractor shall make known the name of the person providing the surveillance at the pre-construction conference.

3.3 REMOVAL: Completely remove all barriers no longer needed when approved by the COR.

WINDOWS ASPHALT PAVING 015700-1

ARCHES NATIONAL PARK TEMPORARY CONTROLS

SECTION 015700

TEMPORARY CONTROLS

1 .1 DESCRIPTION: The work of this section consists of providing temporary controls.

3 .1 HOUSEKEEPING

A. Keep project neat, orderly, and in a safe condition at all times.

B. Provide enough containers for collecting construction debris and construction materials to be recycled, or disposed of outside of the park in a legal manner.

C. Provide individually marked containers for recycling personal items, such as aluminum cans, newspapers, glass, plastic, corrugated cardboard. These items may be recycled by the Contractor or turned over to the Park recycling committee.

D. Wet down dry materials and rubbish to prevent blowing dust.

E. Keep volatile wastes in covered containers.

F. Utilize excavated material as soon as possible.

3 .2 DISPOSAL

A. Dispose of excess excavated material (including asphalt, rocks, and boulders) that cannot be used in construction outside the park at a legal disposal facility.

B. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.

C. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the park. Do not burn or bury refuse inside the park.

3 .3 AIR AND WATER POLLUTION CONTROL

A. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.

B. Do not dispose of volatile wastes or oils in storm or sanitary drains.

C. Do not allow waste materials to be washed into streams or bodies of water.

WINDOWS ASPHALT PAVING 015700-2

ARCHES NATIONAL PARK TEMPORARY CONTROLS

3.4 PROTECTION OF PARK LANDS AND WILDLIFE

Due to the fragile ecological systems of Arches National Park comply with the following:

A. All vehicles and equipment will be inspected before their entry into the Park for mud, weeds, weed seeds, and other unwanted substances. Power-wash all earth-moving equipment (including hauling vehicles) before their initial entrance into the Park; subsequent entries will not require cleaning unless requested. Clean interior as well as exterior of all seeding equipment, particularly hydro seeder tanks and hoses. Notify the CO a minimum of 48 hours before entry of vehicles and equipment to Arches National Park.

B. Do not feed or disturb wildlife. To prevent unnatural attractants to wildlife, keep all foods, pet foods, garbage, drinks, trash, or food and drink containers inside vehicles, or enclosed construction equipment, except during actual use. Remove all garbage and food trash from the project site daily.

WINDOWS ASPHALT PAVING 016000-1

ARCHES NATIONAL PARK MATERIAL AND EQUIPMENT

SECTION 016000

MATERIAL AND EQUIPMENT

1 .1 DESCRIPTION: The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.

1 .2 TRANSPORTATION AND HANDLING: Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible. Contractor is encouraged to obtain materials in biodegradable or recyclable/reusable packaging which uses the minimum amount of packaging possible.

1 .3 STORAGE AND PROTECTION

A. Store materials in accordance with manufacturer's instructions, with seals and labels accessible for inspection.

B. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.

C. Exterior Storage:

1. Store products subject to damage by the elements in weathertight enclosures.

2. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.

3. Store loose granular materials in a well-drained area on solid surfaces to prevent mixing with foreign matter.

D. Protection After Installation: Provide adequate coverings as necessary to protect installed materials from damage resulting from natural elements, traffic, and subsequent construction.

Remove when no longer needed.

WINDOWS ASPHALT PAVING 017700-1

ARCHES NATIONAL PARK PROJECT CLOSEOUT

SECTION 017700

PROJECT CLOSEOUT

1 . 1 DESCRIPTION

A. The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.

PART 2 PRODUCTS – N/A

3.1 CLEANING

A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.

Pick up all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.

B. CLEANING OF CONCRETE: Protect all colored concrete from asphalt. Any colored concrete that has asphalt on it shall be cleaned off immediately.

3.2 PROJECT RECORD DRAWINGS

A. Maintain one complete full-size set of contract drawings and one full-size set of vendor-supplied drawings. Clearly mark changes, deletions, and additions. On completion of the total project, submit complete record drawings. Include all shop drawings, sketches, and additional drawings that are to be included in the final set, with clear instructions showing the location of these drawings.

3.3 CLOSEOUT SUBMITTALS

A. Submit before final inspection request.

1. Project Record Drawings: As specified above.

2. Guarantees and Bonds: As specified in individual sections.

3.4 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer’s Representative will proceed with inspection within two days of receipt of request or will

WINDOWS ASPHALT PAVING 017700-2

ARCHES NATIONAL PARK PROJECT CLOSEOUT

advise the Contractor of items that prevent the project from being designated as substantially complete.

B. If, following final inspection, the work is determined to be substantially complete, Contracting

Officer’s Representative will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within seven calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer’s Representative may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.

C. If, following final inspection, the work is not determined to be substantially complete, Contracting Officer’s Representative will notify Contractor in writing. After completing work, Contractor shall request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.

3 .5 FINAL ACCEPTANCE OF THE WORK

A. After all deficiencies have been corrected, a Letter of Final Acceptance will be issued.

WINDOWS ASPHALT PAVING 310000-1

ARCHES NATIONAL PARK WATERING

SECTION 310000

WATERING

A. The work of this section consists of furnishing, hauling, and applying water required for compaction of embankments, backfills, subgrade, and base course, and for landscaping, dust control, and other construction operations.

1 .2 RELATED REQUIREMENTS: Temporary Services - Section 015100.

2 .1 WATER

A. Free of debris, organic matter, and other objectionable substances.

3 .1 WATER TRUCK

A. At least 1,000-gallon capacity.

3 .2 APPLICATION

A. Use pressure type distributors or a pipeline equipped with sprinkler system. Provide approved meter devices near points of discharge.

B. Ensure a uniform application of water for optimum moisture content. Avoid excessive runoff and minimize water waste.

C. The Contractor may water material before it is brought on-site. The Contractor is still responsible for ensuring moisture content is correct in the field.

D. If overwatering occurs, de-water at no additional expense to the Government.

WINDOWS ASPHALT PAVING 321213-1

ARCHES NATIONAL PARK EXCAVATION AND GRADING

SECTION 312213

EXCAVATION AND GRADING

A. The work of this section consists of site excavation and grading.

1 .2 RELATED WORK

A. Finish Grading - Section 312216.

1 .3 CLASSIFICATION

A. Rock excavation consists of material that cannot be excavated without blasting or using rippers, including boulders having a volume of 2 cubic yards or more.

B. All other excavation under this section will be considered unclassified regardless of the nature of material encountered.

1 .4 PROJECT CONDITIONS

A. Maintain fills, slopes, and ditches within the limits of the new construction until final acceptance. Repair damaged areas at no additional expense to the Government.

2 .1 FILL

A. All fill material shall be imported fill material meeting UDOT state specification for UBC.

B. NPS has a supply of 1-inch minus UBC for the Contractor’s use at the Balanced Rock boneyard.

2 .2 CUT

A. Cut material may be hauled and stockpiled at the Balanced Rock boneyard in the 1-inch minus UBC pile.

B. Contractor is to push material up onto the pile to allow vehicle passage around the pile.

2.3 WATER

A. Section 310000.

WINDOWS ASPHALT PAVING 321213-2

ARCHES NATIONAL PARK EXCAVATION AND GRADING

3 .1 ASPHALT REMOVAL

A. Cut and remove existing damaged asphalt sections and other asphalt as needed to provide an adequate bonding joint. The existing asphalt thickness is estimated at 3 inches. All asphalt shall be removed from the Park and disposed of in a legal manner.

3 .2 FIELD QUALITY CONTROL

A. Testing required to determine compliance for the work of this section will be the responsibility of the Contractor, at no additional expense to the Government.

B. AASHTO T99-81, Method D, will be used to determine maximum density, and AASHTO T191-61, or a standard nuclear method, will be used to determine in-place density.

C. Perform one density test on every 1000 square feet (SF) of newly compacted material in the new parking lot areas.

3 .3 EXCAVATION

A. Excavate to lines and grades shown. Haul excavated UBC material to the Balanced Rock boneyard.

3 .4 FILL CONSTRUCTION

A. Before placing fill, scarify ground surface to provide ample bond between old and new material. Place fill material in layers not exceeding 8 inches loose measurement. Compact each layer before placing the next layer. As the compaction progresses, continually level and manipulate to ensure uniform moisture and density. Add water to obtain optimum moisture content.

3 .5 COMPACTION

A. Compact the fill material to 95 percent of the maximum density, at plus or minus 2 percent of the optimum moisture content.

3 .6 SUBGRADE TOLERANCE

A. The finish subgrade elevation shall not vary above or below the theoretical grade more than

0.05 foot.

3 .7 DISPOSAL

A. Asphalt shall be recycled. The Contractor shall provide a…