This is a procurement proposal document for CMHC (Community/County Mental Health Center or similar facility) project B-51749 regarding replacement of a kitchen dishwasher hot water supply system. The document outlines the scope of work for a facility seeking to replace aging equipment that has been in service since 2003, including a hydronic copper boiler manufactured by A.O. Smith Water Products Company (Model GB-300), a 50-gallon storage tank, and associated piping and circulation components that support a Hobart CRS 86A commercial dishwasher.
The project requires replacement of all components including the hydronic boiler, hot water storage tank (if necessary), copper piping, two circulating pumps, six ball valves, two relief valves, check valves, and four thermometers with thermal wells. The new system must deliver water temperatures of 180-195°F for proper dish sanitation, with specific minimums of 150°F for wash cycles, 160°F for rinse cycles, and 180°F for final rinse cycles. The contractor shall provide all materials, perform installation and connections in accordance with manufacturer specifications, properly insulate all piping, dispose of existing equipment, and conduct operational testing. The project requires a mandatory onsite pre-bid meeting and must be coordinated with facility operations to minimize downtime. Building supply flow pressure must be maintained at 20 PSI (±5 PSI), and system pressure relief valves shall not exceed 125 psi.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| V.23.2 standard-terms-and-conditions~27.pdf | ||
| B-51749 Question and Answer.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CMHC - Kitchen Dishwasher Hot Water Supply System B-51749 Facility is seeking the replacement of equipment making up the kitchen dishwasher hot water supply system. Current equipment includes a hydronic copper boiler, a 50-gallon storage tank, circ pumps, an expansion tank, system valves, temperature gauges, drain lines, etc. Existing hydronic boiler has been in service for 23 years and this model no longer available or supported by the manufacturer. All hot water piping, valves, gauges, etc. shall be replaced up to and including the last isolation valves to the hot water supply loop. Project entails properly insulating all system lines to reduce heat loss and promote efficiency.
Existing Hydronic Copper Boiler shall be removed of and disposed of by contractor. New hot water supply equipment shall be capable of providing 180-195F water for the proper hot water sanitation of hospital dishes. Unit shall have manual start and stop operation. Pressure relief valves shall not exceed 125psi. Unit shall be installed in accordance with manufactures instructions. Contractor shall provide all required fittings and make connections. Existing hot water storage tank shall be replaced if a storage tank is necessary to sustain adequate flows and temperatures for continuous operation of the dishwasher. All copper piping, circulating pumps (x2), ball valves (x6), relief valves (x2), check valves, and thermometers to thermal wells (x4) shall be replaced. New piping shall be insulated by contractor. The existing expansion tank may be reused or otherwise replaced and properly sized for application. All materials shall be provided by contractor. Installation and all connections shall be performed by contractor. Old equipment shall be disposed of by contractor unless otherwise directed by facility Chief Engineer. Project schedule must be coordinated with facility to minimize interference with routine operations. Down time shall be minimized to feasible extent. Project requires a satisfactory operational test and verified operation temp minimums during wash and rinse cycles.
*Mandatory onsite pre-bid meeting for prospective bidders. Existing conditions shall be verified by bidding contractor.
Existing Hydronic Copper Boiler A. O. Smith Water Products Company Burkay Genesis
| MODEL | GB-300 200 |
| SERIAL | G – 03 74424 |
| A O SMITH Part Number | GB300E22N000000 |
Max Working Pressure 160 psi Start Up 8/18/03 Existing hot water storage tank data Mo. # 50st Ser # 12035342T 50 Gallons Existing centrifugal pump data (x2) Grundfos
P/N: 115V 60 HZ
527225520P1 Unit serves hot water supply to (1) HOBART CRS 86A DISHWASHER
| MODEL | CRS 86A | ||
| SERIAL | 85-1032648 H | ||
| ML | 103911 | ||
| DATE CODE | UAC | ||
| VOLTS | 480 | HZ 60 | PH 3 |
| AMPS MOTORS | 11 | ||
| WATTS ELECTRIC HEAT | 25 KW |
INSTALLED 8/7/03
Hot Water Sanitizing Minimums: Wash 150F; Rinse 160F; Final Rinse 180F Building Supply Flow Pressure Required 20 PSI (+/- 5 PSI)