This document is a performance time tabulation form outlining the construction schedule for repair of an aircraft parking ramp for Solicitation Number FA441824R0001 from the Department of the Air Force Air Mobility Command. The form provides the estimated construction start date of May 1st, 2024, allows 60 days for mobilization and submittal preparation, and estimates construction completion by July 20th, 2024 with 30 additional days for closeout activities. It includes a month-by-month breakdown of estimated construction days while accounting for typical monthly inclement weather percentages and allowable weather delay days. The total estimated number of contract days is 170 with 14 days allotted for inclement weather. The first sentence of construction must clearly convey that the 60 days for mobilization and submittals are excluded from the construction period. Liquidated damages will be assessed from the construction completion date rather than the end of closeout.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2-Mar-24
NA
1-May-24 Number of Construction Days: 66
Construction Complete 20-Jul-24
Number of Closeout Days: 30
19-Aug-24
Month
Days In
Month
Average Inclement Weather
Days/Month
Number of Construction Days/Month
% of Days of Month
Construction
Possible Inclement Weather Days Per
% of Month Impacted by
Inclement Weather
Allowed Inclement Weather Days Per
Jan 2024 31 6 0 0% 0 100% 0 Feb 2024 28 5 0 0% 0 100% 0 Mar 2024 31 5 0 0% 0 100% 0 Apr 2024 30 5 0 0% 0 100% 0 May 2024 31 5 31 100% 5 100% 5 Jun 2024 30 8 30 100% 8 100% 8 Jul 2024 31 9 5 16% 1 100% 1 Aug 2024 31 9 0 0% 0 100% 0 Sep 2024 30 7 0 0% 0 100% 0 Oct 2024 31 5 0 0% 0 100% 0 Nov 2024 30 4 0 0% 0 100% 0 Dec 2024 31 6 0 0% 0 100% 0 Jan 2025 31 6 0 0% 0 100% 0 Feb 2025 28 5 0 0% 0 100% 0 Mar 2025 31 5 0 0% 0 100% 0 Apr 2025 30 5 0 0% 0 100% 0 May 2025 31 5 0 0% 0 100% 0
Total: 66 Total: 14
Note: We have to clearly convey to the contractor that his construction time does not include the 60 for mobilization and submittals. Once work begins, the balance of the 60 days go away. Also need to Convey that LDs will be charged starting at the end of Final Inspection/Constr. Complete and not at the end of closeout period.
TOTAL Construction + Weather =
Contract Complete:
Total Contract Days:
Number of Inclement Weather Days:
Notice to Proceed
Special Order Materials Lead Time:
Construction Start Date:
Insert number of days for any Special Order Materials Lead Time you are allowing.
Insert the Number of Construction Days/Month for each month without consideration of inclement weather days.
Mobilization & Submittal Preparation:
Insert the % of Month Impacted by Inclement Weather
Construction Complete Date is displayed below.
Performance Time tab data is linked to the Liquidated Damages tab. Coordinate current LD rates with Contracting.
Insert current date (data linked to Liquidated Damages tab).
Performance Time Tabulation Form
DKFX 1093394, Repair Aircraft Parking Ramp - Phase 2 17-May-23
Total number of Contract Days is displayed below.
Insert Project Number and Title (data linked to Liquidated Damages tab).
Instructions:
Insert estimated Construction Start Date.
Insert number of Mobilization & Submittal Preparation days you are allowing.
Performance Time