Attch 2. Statement of Objectives (SOO).pdf

PDF 98 KB Posted

Attached to
Slide Replacement for Moody AFB Pool Federal contract opportunity
Solicitation number
FA483021Q0021
Issued by
Department of the Air Force Air Combat Command

About this file

This combined synopsis/solicitation is seeking quotes for the demolition of an existing outdoor pool slide and installation of a new pool slide at Moody Air Force Base. Quotes are due by September 9, 2021 and must include an anticipated period of performance, statement of work, and drawings. The contractor will demolish the existing slide, staircase, pump and connections; install a new slide, staircase, and pump within the existing footprint; design and install new concrete footers; and update utilities in the mechanical room. The contractor must coordinate with Moody AFB squadrons and comply with Moody, DoD, and regulatory design standards. This is a 100% small business set-aside requiring attendance at an on-base site visit on September 1, 2021. The point of contact is Kalyn Runey for any questions.

View the file

Other files for this federal contract opportunity

Other files attached to Slide Replacement for Moody AFB Pool, newest first.
File Type Posted
Attch 1. COMBO-Synopsis.pdf PDF
Attch 7. Moody AFB Pool Slide Photos.pdf PDF
Attch 1. COMBO-Synopsis.pdf PDF
Attch 6. Pool Slide Questions and Answers.pdf PDF
Attch 5. Base Map.pdf PDF
Attch 6. Q&A Template.pdf PDF
Attch 4. Base Pass Request Form.pdf PDF
Attch 1. COMBO-Synopsis.pdf PDF
Attch 3. Project Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF OBJECTIVES

DEMO/REPLACE OUTDOOR POOL SLIDE

1. The contractor shall furnish all labor, supervision, equipment, and material to accomplish the demolition of the existing outdoor pool slide and the installation of a new pool slide along with all associated mechanical work.

2. The contractor is to demolish and remove the existing slide, staircase, pump and all connections to the existing mechanical room.

3. The contractor is to install a new slide, staircase, and pump within the footprint of the existing slide and staircase.

4. The contractor is to design and install new concrete footers and structural requirements to support new slide. Concrete deck will be finished up to seam of existing foundation to look as though it was installed with original pool construction.

5. The contractor is to update existing mechanical room with all necessary utilities required for new slide.

6. The contractor shall coordinate all aspects of the work with 23rd Contracting Squadron and 23rd Civil Engineer Squadron to ensure timely completion of all work. The contractor shall coordinate, be accountable and responsible for all of the work of all separate contractors as required to ensure completion of all work.

7. The contractor will comply with the Moody AFB Design Guide, Moody Specifications, Unified Facilities Criteria and applicable State, local, and Federal regulatory agencies, to include but not limited to OSHA and Accident Prevention Plan.

File details come from the government source that posted it. Updated .