Attachment-S_EVER_cost-pricing_form.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- EVER Wayside Exhibit Design-Build Federal contract opportunity
- Solicitation number
- 140P2124R0045
About this file
This document appears to be a pricing and cost form for the "EVER Wayside Exhibit Design-Build" federal contract opportunity. The form itemizes costs for various tasks and materials related to the exhibit design, fabrication, and installation. Key details include:
The contract opportunity is for a design-build project to create wayside exhibits for Everglades National Park (EVER). The solicitation number is 140P2124R0045. The required products and services include project management, layout and fabrication drawings, samples/prototypes, exhibit structures, display objects, electrical/electronic components, graphic panels, audio description, project closeout, and shipping and installation. The pricing form provides a breakdown of estimated material and labor costs for each of these elements. No specific pricing, response, or award dates are provided. This appears to be a template or sample form rather than a complete solicitation document.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
cost-pricing form
| EVER: Fabrication and Installation Cost/Pricing Form | |||||
| PROJECT MANAGEMENT | $0.00 | ||||
| LAYOUTS & FABRICATION DRAWINGS | $0.00 | ||||
| PROOFS/SAMPLES/PROTOTYPE | $0.00 | ||||
| EXHIBIT STRUCTURES | $0.00 | ||||
| DISPLAY OBJECTS & SPECIALTY | $0.00 | ||||
| ELECTRICAL/ ELECTRONIC | $0.00 | ||||
| GRAPHIC PANELS | $0.00 | ||||
| AUDIO DESCRIPTION | $0.00 | ||||
| PROJECT CLOSEOUT | $0.00 | ||||
| SHIPPING | $0.00 | Total Materials Cost | $0.00 | ||
| INSTALLATION | $0.00 | Total Labor Hours | $0.00 | ||
| TRAVEL | $0.00 | ||||
| TOTAL | $0.00 | ||||
| Rounded to | $0 |
| PROJECT MANAGEMENT (excluding travel) | |||||
| LABOR | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Project Management $0.00
| Layouts and Fabrication Drawings | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Miscellaneous | job | $0.00 |
| SUBTOTAL MATERIALS | $0.00 | ||
| MARK-UP on materials | 15 | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount |
| Designer | hours @ | $0.00 |
| Detailer | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Fabrication Drawings $0.00
| Proofs/Samples/Mock-ups/Prototypes | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| map | ea | $0.00 | |||
| hot/cold | ea | $0.00 | |||
| moving aligator | ea | $0.00 | |||
| alligator nest w/babies | ea | $0.00 | |||
| sample materials | sets | $0.00 | |||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Exhibit Specialist - Fabrication | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Samples $0.00
| Exhibit Structures/Bases | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Low Profile, in ground/base plate, 36x24 | ea | $0.00 | |||
| Low Profile, rail, 36x24 | ea | $0.00 | |||
| Low Profile, sled w/ cane detection bar, 36x24 | ea | $0.00 | |||
| Low Profile, in ground, 48x24 | ea | $0.00 | |||
| Low Profile, rail, 48x24 | ea | $0.00 | |||
| Low Profile, base plate, 48x24 | ea | $0.00 | |||
| Low Profile, breakaway base plate, 48x24 | ea | $0.00 | |||
| Low Profile, in ground with concrete base, 36x24 | ea | 0 | |||
| Low Profile, in ground w/ concrete base, 12x10 | ea | $0.00 | |||
| Wall mount, 108x48 | ea | $0.00 | |||
| Wall mount, 24x48 | ea | $0.00 | |||
| Wall mount, 18x24 | ea | $0.00 | |||
| Upright, Bulletin Case, in ground, 24x36 | ea | $0.00 | |||
| Double Vertical Upright, base plate, 36x48 | ea | $0.00 | |||
| Plant ID (horiz), rail, 16x6 | ea | $0.00 | |||
| Plant ID (vert), in ground 16x6 | ea | $0.00 | |||
| Plant ID (vert), in ground (extra tall), 16x6 | ea | $0.00 | |||
| Tactile table frame for map. 60x20x30 | ea | $0.00 | |||
| $0.00 | |||||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | 0 |
TOTAL ALL MATERIALS $0.00
| LABOR | hours | x | rate | amount | |
| Shop Supervisor | hours @ | $0.00 | |||
| Exhibit Specialist - Fabrication (54 bases) | hours @ | $0.00 | |||
| TOTAL ALL LABOR | $0.00 |
TOTAL Exhibit Structures $0.00
| Display Objects and Specialty Elements | ||||
| MATERIALS: | qty. | unit | unit cost | amount |
| Tactile map - Corian | ea | $0.00 |
| hot/cold touch elements | ea | $0.00 |
| solor-powered moving aligator | ea | $0.00 |
| aligator nest with babies - bronze and concrete | ea | $0.00 |
| molds/clay/plastic | ea | $0.00 |
| SUBTOTAL MATERIALS | $0.00 | |
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Exhibit Specialist | hours @ | $0.00 | |||
| Map Model Maker | hours @ | $0.00 | |||
| 3D Printer | hours @ | $0.00 | |||
| TOTAL ALL LABOR | $0.00 |
TOTAL DO and SE $0.00
| Electrical/Electronic | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| solar panel and wiring | ea | $0.00 |
| SUBTOTAL, AV EQUIPMENT | $0.00 | |
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Exhibit Specialist - Electrical | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Electrical/Mechanical/AV $0.00
| Graphic Panels | |||||
| MATERIALS: | qty. | unit | dig output | amount | |
| 36x24, DS Aluminum | ea | $0.00 | |||
| 48x24, DS Aluminum | ea | $0.00 | |||
| 16x6, DS Aluminum | ea | $0.00 | |||
| 36x48, DS Aluminum | ea | $0.00 | |||
| 108x48, DS Aluminum | ea | $0.00 | |||
| 24x18, DS Aluminum | ea | $0.00 | |||
| 22x15.5 (solar cutout background), HPL | ea | $0.00 | |||
| 10.5x12 (donor plaque), SS Aluminum | ea | $0.00 | |||
| 9x9 (solar lift panel), SS Aluminum | ea | $0.00 | |||
| 48x24, SS Aluminum | ea | $0.00 | |||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Graphics Supervisor | hours @ | $0.00 | |||
| Graphics Specialist (59 panels) | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Graphics $0.00
| Audio Description | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Misc. | ea | $0.00 | |||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | |||
| LABOR | x | rate | amount | |
| Audio Describer (~58 exhibits x 2 hrs) | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Conservation $0.00
| PROJECT CLOSEOUT | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Miscellaneous | job | $0.00 |
| SUBTOTAL MATERIALS | $0.00 | |
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 | |||
| TOTAL ALL LABOR | $0.00 |
TOTAL Project Closeout $0.00
| SHIPPING | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Packing | job @ | $0.00 | |||
| Shipping | job @ | $0.00 |
TOTAL MATERIALS $0.00
| LABOR | hours | x | rate | amount | |
| Exhibit Specialist - Fabrication | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
Total Shipping $0.00
INSTALLATION and removal
| MATERIALS: | qty. | unit | unit cost | amount | |
| air fare | job @ | $0.00 | |||
| per diem | days @ | $0.00 | |||
| Lodging | days @ | $0.00 | |||
| Rental car and gas | days @ | $0.00 |
Misc. concrete, weights, and equipment rental job @ $0.00
TOTAL MATERIALS crew $0.00
| LABOR (~60 exhibits to install; __ to remove) | hours | x | rate | amount | |
| Project Manager (4 hours to remove/install/4 people) | hours @ | $0.00 | |||
| Exhibit Spec - Fabricator | hours @ | $0.00 | |||
| Exhibit Spec - Fabricator | hours @ | $0.00 | |||
| Exhibit Spec - laborer | hours @ | $0.00 |
TOTAL ALL LABOR $0.00
Total Installation $0.00
| TRAVEL | |||||
| Post Award with PM and audio describer | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| air fare | job @ | $0.00 | |||
| per diem | days @ | $0.00 | |||
| lodging | days @ | $0.00 | |||
| Rental car and gas | days @ | $0.00 | |||
| Misc. | job @ | $0.00 |
TOTAL MATERIALS team $0.00
| LABOR | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 | |||
| Audio Describer | hours @ | $0.00 | |||
| hours @ | $0.00 | ||||
| $0.00 | |||||
| TOTAL ALL LABOR | $0.00 |
Total Travel $0.00
File details come from the government source that posted it. Updated .