Attachment - Risk Criteria.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
C213--EL PASO FACILITY CONDITION ASSESSMENT Federal contract opportunity
Solicitation number
36C25725Q0100
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

This document is an Attachment - Risk Criteria.xlsx file that provides a risk criteria matrix for a Facility Condition Assessment (FCA) of the Central Utility Plant (CUP) Building 7776 at the El Paso VA Health Care Center. The risk criteria matrix evaluates the priority and risk levels across various facility systems and infrastructure components, including facility primary infrastructure, building main/section infrastructure/structure, patient/employee safety and life support, amenities, access, and security. The risk levels range from low to high, with each component scored on a scale of 1 to 5. This risk criteria matrix is an attachment to the FCA Statement of Work for the related federal contract opportunity, which is a solicitation (Solicitation Number: 36C25725Q0100) for an independent FCA of the CUP building.

View the file

Other files for this federal contract opportunity

Other files attached to C213--EL PASO FACILITY CONDITION ASSESSMENT, newest first.
File Type Posted
Amendment 36C25725Q0100 0001 - Cancel Solicitation.pdf PDF
Attachment - VA Seismic Design Reqs.pdf PDF
RFQ 36C25725Q0100 El Paso Facility Condition Assessment.pdf PDF
Attachment - Central Plant Drawings.pdf PDF
Attachment - FCA Scoring Guide.xlsx XLSX spreadsheet
Attachment - FCA 101 Facility Condition Assessment Guide.pdf PDF
Attachment - Elevator Survey_FCA.docx DOCX document
Attachment - Top Ten Deficiency List.xlsx XLSX spreadsheet
Attachment - FCA Correction Cost Estimate.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Risk Criteria
Facility primary infrastructure455131555554545
Building main infrastructure/structure455131555554545
Building section infrastructure/structure33413133333353N/A
Patient, employee safety/life safety/life support555131555555545
Patient/Employee amenity/convienience213131222222222
Patient/Employee access33413122222242N/A
Securtiy434131333333433
AccessArchitecturalElectricalEnergyHazmatHistoricInformation techMechanicalPlumbing (building)Sanitary (site)Steam generationStorm WaterStructuralTransportWater (site)
Systems
Priority
1Low
2Medium low
3Medium
4Medium high
5High
Definitions
Facility primary infrastructureSite utilities such as main switchgear, steam tunnels and piping, boiler plants, campus chiller piping and chiller plants, Oxygen tanks, Roads and water including water towers and treatment plants.
Building main infrastructure/structureThe buildings themselves and the primary infrastructure and systems within the building, such as plumbing, electrical, medical Gas HVAC etc
Building section infrastructure/structureSections or floors of the building and the branch infrastructure such as plumbing, electrical, medical Gas HVAC etc.
Patient, employee safety/life safety/life supportSystems and equipment that are safety related such as fire alarm, fire suppression, nurse call, fire doors and barriers, stair wells etc
Patient/Employee amenity/convienienceSystems or equipment that are primarily amenity such as floor tile, paint, ceiling tile, etc
Patient/Employee accessSystems or equipment that provide access such as elevators.
SecurtiySystems or equipment that accommodate security such as fencing, cameras, access systems etc.

FCA Risk Level Crieria Attachment to FCA SOW

File details come from the government source that posted it. Updated .