Attachment E - Pricing and Level of Effort.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- B599--HITC Power Study Federal contract opportunity
- Solicitation number
- 36C10X21Q0019
About this file
This combined synopsis and solicitation requests quotes for a power study to be conducted at the Hines Information Technology Center. Vendors must submit quotes by November 19th referencing solicitation number 36C10X21Q0019. The Department of Veterans Affairs Strategic Acquisition Center Frederick will award a 150-day contract to conduct the power study in accordance with the requirements in the performance work statement. Vendors must attend a mandatory pre-bid walkthrough on November 10th and submit any questions by November 12th. The solicitation also includes an attachment with a pricing table and level of effort template for vendors to complete in their quotes.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment E - Level of Effort.xlsx | XLSX spreadsheet | |
| Attachment F - Pricing.xlsx | XLSX spreadsheet | |
| 36C10X21Q0019 0003.pdf | ||
| ATTACHMENT D.2 - PAST PERFORMANCE REFERENCES.pdf | ||
| 36C10X21Q0019 0002.pdf | ||
| 36C10X21Q0019 0001.pdf | ||
| 36C10X21Q0019_1.docx | DOCX document | |
| 36C10X21Q0019.docx | DOCX document | |
| Attachment C - Past Performance Questionnaire.docx | DOCX document | |
| Attachment D - Past Performance References.pdf | ||
| Attachment B - Wage Determination Cook County IL.pdf | ||
| Attachment A3 - HITC Main Electrical Drawing.pdf | ||
| Attachment A2 - First Floor Area B.pdf | ||
| Attachment A1 - First Floor Area C.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Power Study Attachment E - Pricing_Level of Effort
| Task / Deliverable | Electrician | Project Manager | |||||
| Hours | Hours | Hours | Units | Unit Rate | Total | ||
| 0001 | Kick-Off/Pre-Construction | ||||||
| 0001A | Kick-Off/Pre-Construction Meeting | 1 | $0.00 | $0.00 | |||
| 0001B | Draft Work Plan | 1 | $0.00 | $0.00 | |||
| 0001C | Draft Activity Hazard Analysis | 1 | $0.00 | $0.00 | |||
| 0001D | Draft Project Schedule | 1 | $0.00 | $0.00 | |||
| 0002 | Method of Procedures | 1 | $0.00 | $0.00 | |||
| 0003 | Final Activity Hazard Analysis | 1 | $0.00 | $0.00 | |||
| 0004 | Final Work Plan | 1 | $0.00 | $0.00 | |||
| 0005 | Project Management | $0.00 | |||||
| 0005A | Contractor Project Management Plan | 1 | $0.00 | $0.00 | |||
| 0005B | Contractor Outline for Block of Instruction | 1 | $0.00 | $0.00 | |||
| 0006 | Weekly Reports | 21 | $0.00 | $0.00 | |||
| 0007 | Power Study | $0.00 | |||||
| 0007A | Power Study Report | 1 | $0.00 | $0.00 | |||
| 0007B | Unused Circuit Breakers | 1 | $0.00 | $0.00 | |||
| Total Hours | 0 | 0 | 0 | ||||
| Labor Rate | $0.00 | $0.00 | $0.00 | ||||
| Sub Totals | $0.00 | $0.00 | $0.00 | ||||
| TOTAL | $0.00 |