Attachment D - Submittal Log.pdf
PDF 640 KB Posted
- Solicitation number
- 89503120BWA000025
About this file
This document contains a submittal log and details of a federal contract opportunity for structure replacement construction work. The submittal log outlines 48 required submittals for the Carr-Keswick 230-kV Transmission Line project, including construction schedules, safety plans, material testing reports, drawings, and as-built documents. Submittal due dates range from 10 days prior to notice to proceed to after project completion.
The related federal contract opportunity is a competitive small business set-aside for structure replacement and transmission line installation work. The solicitation will be available on May 15, 2020 at http://www.beta.sam.gov and bids are due between $1-3 million. The work includes removing one lattice tower, installing a monopole structure and 0.5 miles of double circuit transmission line along with a temporary shoo-fly line. The performance location is in Whiskeytown National Recreation Area, California. The Department of Energy Western Area Power Administration is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Title: Award Date:
Contract No.: NTP:
Contractor: Completion Date:
Location Submittal Item In Date Date
# # Submittal Item Standards CSO DSW Date Due Submitted Approved COMMENTS
STANDARD 1
1 Construction Schedule 1.1.4.1. 3 (see project spec)
2 Breakdown of Contract Prices 1.1.6.1. 1 1 NLT 30 days after
NTP
3 Electrical Equipment & Steel Purchase Orders 1.2.3.1. 1 NLT 10 working days after PO award
4 Safety and Health Program 1.4.1.5. 1 NLT 10 days prior to start of construction
5 Copies of Certifications, Test Records & Technical Data 1.4.1.10. 1 Prior to use
6 - Load Performance Tests 1.4.1.10.(1) 1 Prior to use
7 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) 1 Prior to use
8 - Brake Performance Test 1.4.1.10.(3) 1 Prior to use
9 - Test Results of Protective Ground Leads 1.4.1.10.(4) 1 Prior to use
10 - Material Safety Data Sheets 1.4.1.10.(5) 1 Prior to use
11 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) 1 Prior to use
12 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 1 Prior to use
13 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 1 Prior to use
14 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 1 Prior to use
15 Assurance of Competency in Equipment Operation 1.4.3.4. 1 Prior to use
16 Structure Erection Plan 1.4.8.1. 1 Prior to structure erection
17 Suspended Work Cart Work Procedure 1.4.12 1 Prior to use
18 Protective Ground Lead Test Results & Certification 1.4.14.3. 1 Prior to use
19 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3. 1 NLT 10 working days prior to starting work
20 Stringing Plan 1.4.17.3. 1 Prior to stringing
21 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) 1 Prior to stringing
22 Transmission Line Removal Plan 1.4.18 1 Prior to removal
23 Shoo-fly work sequence plan 1 14 days after NTP
STANDARD 2
24 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 1 20 days prior to compacting
25 Rip-ap Gradation 2.9.3 1 14 days prior to placement
26 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. 1 Immed. after test complete
27 Tree Trimmer Qualifications 2.4.4. 1 Prior to trimming
Submitted To Copies
SUBMITTAL TRACKING SHEET
89503120BWA000025
Attachment D
Location Submittal Item In Date Date
# # Submittal Item Standards CSO DSW Date Due Submitted Approved COMMENTS Submitted To
Copies
STANDARD 3
28 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3. 1 NLT 20 days prior to concrete placement
29 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. 1 NLT 10 days prior to use
30 Fly Ash For Concrete 3.1.1.2.(5) & 3.1.1.4. 1 NLT 20 days prior to use
31 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. 1 NLT 10 days prior to use
32 Batch Certificates 3.1.1.2.(7) 1 Provide at delivery
33 Test Reports 3.1.1.2.(8) 1 Immed. upon completing
34 Drawings & Data For Electrical Equip. Foundation Design 3.2.1.2. 2 T Prior to installation
STANDARD 10
35 Catalog Data Sheets of Accessories & Hardware Used In Conductor & Overhead Ground Wire Installation 10.2.2. 3
NLT 40 days prior to material installation
36 Drawings of Insulator & Overhead Groundwire Assemblies and Details 10.2.2. 3 NLT 40 days prior to material installation
37 Complete Material List 10.2.2. 1 NLT 40 days prior to material installation
38 Conductor Insulator Assembly Test Reports 10.2.3.1. & 10.3.3. 2 ASAP
39 Conductor Test Reports 10.2.3.2. & 10.6.1.2. 2 ASAP
40 Overhead Ground Wire Test Reports 10.2.3.3. & 10.6.2.2. 2 ASAP
41 Overhead Ground Wire Assemblies Test Reports 10.2.3.4. & 10.4.3. 2 ASAP
42 Ground Resistance Measurements 10.2.3.5. & 10.5.3. 2 ASAP
43 Vibration Damper Test Reports 10.2.3.6. & 10.6.4.3. 2 ASAP
44 Conductor Spacer Damper Test Reports 10.2.3.7. & 10.6.6.2. 2 ASAP
45 Assembly & Installation Instructions For Conductor Insulator Assemblies 10.3.4 2 NLT 2 weeks prior to installation
STANDARD 13
46 Recycled Materials Quantity Report 13.2.1. & 13.7.2. 1
47 Products Containing Recovered Materials Report 13.2.2. & 13.8.3. 1
48 CONCRETE Removal Silica Plan 1 2 weeks prior to use
49 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2. 1
50 Cleanup Work Management Plan 13.2.16. & 13.19.2. 1
51 Post Cleanup Report 13.2.17. & 13.19.7. 1
STANDARD 15
52 As-Built Drawings 15.2.6. 1
*Submittal required if item is used in the performance of the contract.
"T"= Submit transmittal sheet only.
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable