This is a Technical Specifications document for the Oregon Youth Authority (OYA) Tillamook Youth Correctional Facility (TYCF) Living Units Addition & Renovations project, located at 6700 Officer Row, Tillamook, Oregon. The project consists of construction of new dormitories and clinic facility, plus renovation of selected portions of the existing building, including the break room, laundry, clinic, clinic office, and portions of indoor recreation. The work includes demolition, alteration of existing plumbing, HVAC, electrical power and lighting, fire suppression sprinklers, fire alarm, and security systems while maintaining continuous facility operation. The project will be performed in phases with existing dormitories remaining occupied during construction before demolition upon completion of new construction. The Owner will remove non-fixed furniture before work commences and will supply and install clinic furniture, medical equipment, electronics, security technology components, and certain fixture accessories. The Contractor is responsible for all trade permits, system development charges, utility installation costs, scheduling, coordination, and comprehensive site security and safety measures appropriate to a youth correctional facility.

The project manual establishes detailed administrative requirements including a Schedule of Values submission within 10 days of the Owner-Contractor Agreement using AIA G703 forms, progress payment applications using AIA G702 and G703 forms submitted at regular intervals, and a complete construction schedule in Critical Path Method format submitted within 20 days. Unit prices are provided for photovoltaic array expansion or reduction (per Watt), gravel pad expansion or reduction (per square foot), and chain link fence enclosure expansion or reduction (per lineal foot) to facilitate adjustment of the system to meet Oregon's 1.5% Green Energy Technology requirement. Two alternates are available: Alternate No. 1 provides for a new 300kW generator with automatic transfer switches and associated infrastructure, and Alternate No. 2 provides for partial infrastructure for new electrical service for the PV array system. The Contractor must maintain asbestos-free certification, coordinate with Owner occupancy requirements, conduct work during specified hours (9 a.m. to 4 p.m. Monday-Thursday for noisy exterior work), provide security measures including personnel monitoring and tool control, and maintain detailed field record drawings showing all utility locations and as-built conditions for submission prior to final payment.

View the file

Other files

File Type Posted
S-DASOBO-00015981~1.pdf PDF
Attachment C Plans and Drawings~3.pdf PDF
Addendum 1 ITB S-DASOBO-00015981.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OREGON YOUTH AUTHORITY

TILLAMOOK LIVING UNITS ADDITION &

RENOVATIONS

6700 Officer Row

Tillamook, OR 97141

Project No. 80072

PROJECT MANUAL

Permit Set

08/20/2024

Owner Representative Jeremy Wright, Construction Project Manager

503-507-2590

Architect Oh planning+design, architecture

7 SE Stark Street, Suite 900 Portland, OR 97214

503-280-8000

DOJ Review Set 05/04/2026

NOTE: The STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS (“General Conditions”) dated January 1, 2021, as modified by the Supplemental General Conditions apply to this Contract. In the event of a conflict between these Specifications and the General Conditions or Supplemental General conditions, parties shall refer to Section A.3 Interpretation of Contract Documents for guidance.

80072 OYA - Tillamook Living Units

00 01 03 - 1 08/20/2024 Permit Set

SECTION 00 01 03

PROJECT TEAM

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Identification of project team members and their contact information.

1.02 OWNER:

Oregon Youth Authority Physical Plant Operations 530 Center Street NE, Suite 35 Salem, OR 97301-3765 Name: Andre Billingsley Email: andre.I.billingsley@oya.oregon.gov

Primary Contact: All correspondence from the Contractor to the Architect will be direct, with copies to this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.

Name: Jeremy Wright Email: jeremy.wright@oya.oregon.gov Phone: 503-507-2590

1.03 ARCHITECT:

Design Professional of Record. All correspondence from the Contractor regarding construction documents authored by Architect's consultants will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.

Architecture Firm:

Oh planning+design, architecture 7 SE Stark Street, Suite 900 Portland, OR 97214 Telephone: 503-280-8000

Principal In Charge:

Deb France, AIA, NCARB, LEED AP

Primary Contact:

Name: Andrew Pearson Email: andrew.pearson@ohpd.net Telephone: 503-902-6983

1.04 CONSULTANTS:

Civil Engineering Consultant:

Westech Engineering, Inc.

341 Fairview Industrial Drive, SE, Suite 100 Salem, OR 97302 Telephone: 503-585-2474

Primary Contact:

Name: Ray Engel, P.E.

Email: rengel@westech-eng.com

Structural Engineering Consultant:

ABHT Structural Engineers

1022 NW Marshall Street #350 Portland, OR, 97209 Telephone: 503-243-6682

Primary Contact:

Name: Clinton Ambrose, Principal Email: clinton@abht-structural.com

00 01 03 - PROJECT TEAM

OYA - Tillamook Living Units

00 01 03 - 2 08/20/2024 Permit Set

Mechanical/Plumbing/Electrical Engineering Consultant:

PAE Engineers

151 SW 1st Avenue, Suite 300 Portland, OR, 97204 Telephone: 503-542-0521

Primary Contact:

Name: Ruwan Jayaweera, Principal Email: ruwan.jayaweera@pae-engineers.com

Building Security Consultant:

HK Electrical Engineers (Sub-consultant to PAE Engineers)

10512 SE French Road Vancouver, WA, 98664 Telephone: 503-625-4443

Primary Contact:

Name: Frank Hopkins Email: frank@hkeng.com

Hazardous Materials Consultant:

PBS Engineering and Environmental, Inc.

4412 S Corbett Avenue Portland, OR, 97239 Telephone: 503-248-1939

Primary Contact:

Name: Joel McCarthy Email: joel.mccarthy@pbsusa.com

Building Envelope Consultants:

Forensic Building Consultants

12901 SE 97th Avenue, Suite 310 Clackamas, OR 97015 Telephone: 503-772-1114

Primary Contact:

Name: Matt Smith Email: matt@forensicbuilding.com

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION 00 01 03

OYA - Tillamook Living Units 00 01 07 - 1 08/20/2024

Permit Set

SECTION 00 01 07

SEALS PAGE

PART 1 GENERAL

ARCHITECT OF RECORD:

Oh planning+design, architecture 7 SE Stark Street, Suite 900 Portland, Oregon 97214 Phone: 503-280-8000

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

00 01 07 - Seals Page

OYA - Tillamook Living Units 00 01 07 - 2 08/20/2024

Permit Set

CONSULTANTS

Civil Engineering Consultant:

Westech Engineering, Inc.

341 Fairview Industrial Drive, SE, Suite 100 Salem, OR 97302 Telephone: 503-585-2474

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

OYA - Tillamook Living Units 00 01 07 - 3 08/20/2024

Permit Set

Structural Engineering Consultant:

ABHT Structural Engineers

1022 NW Marshall Street #350 Portland, OR, 97209 Telephone: 503-243-6682

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

OYA - Tillamook Living Units 00 01 07 - 4 08/20/2024

Permit Set

Mechanical Engineering Consultant - Plumbing:

PAE Engineers

151 SW 1st Avenue, Suite 300 Portland, OR, 97204 Telephone: 503-542-0521

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

OYA - Tillamook Living Units 00 01 07 - 5 08/20/2024

Permit Set

Mechanical Engineering Consultant - HVAC:

PAE Engineers

151 SW 1st Avenue, Suite 300 Portland, OR, 97204 Telephone: 503-542-0521

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

OYA - Tillamook Living Units 00 01 07 - 6 08/20/2024

Permit Set

Electrical Engineering Consultant:

PAE Engineers

151 SW 1st Avenue, Suite 300 Portland, OR, 97204 Telephone: 503-542-0521

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

OYA - Tillamook Living Units 00 01 07 - 7 08/20/2024

Permit Set

Building Security Consultant:

HK Electrical Engineers

10512 SE French Road Vancouver, WA, 98664 Telephone: 503-625-4443

Design Professional of Record:

Name: ____________________ Email: ____________________

Date:

Seal:

END OF SECTION

OYA - Tillamook Living Units 00 01 10 - 1 08/20/2024

Permit Set

SECTION 00 01 10

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 01 - Project Title Page 00 01 03 - Project Team 00 01 07 - Seals Page 00 01 10 - Table of Contents

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 10 00 - Summary (Revised 5/4/2026) 01 20 00 - Price and Payment Procedures 01 22 00 - Unit Prices (Revised 5/4/2026) 01 23 00 - Alternates 01 25 00 - Substitution Procedures (Revised 5/4/2026) 01 25 00.01 - Substitution Request Form - Procurement Phase (Added 5/4/2026) 01 25 00.02 - Substitution Request Form - Construction Phase (Added 5/4/2026) 01 30 00 - Administrative Requirements 01 31 13 - Coordination and Control of the Site Work 01 40 00 - Quality Requirements 01 45 29 - Laboratory Services 01 50 00 - Temporary Facilities and Controls 01 51 00 - Temporary Utilities 01 57 13 - Erosion and Pollution Control 01 57 19 - Temporary Environmental Controls 01 60 00 - Product Requirements 01 61 16 - Volatile Organic Compound (VOC) Content Restrictions 01 70 00 - Execution and Closeout Requirements 01 71 23.16 - Survey Work During Construction, By Contractor 01 74 19 - Construction Waste Management and Disposal 01 78 00 - Closeout Submittals 01 79 00 - Demonstration and Training

DIVISION 02 -- EXISTING CONDITIONS

02 41 00 - Demolition 02 41 13 - Site Demolition and Salvage 02 82 13 - Lead Handling Procedures

DIVISION 03 -- CONCRETE

03 30 00 - Cast-in-Place Concrete 03 35 11 - Concrete Floor Finishes

DIVISION 04 -- MASONRY

04 20 00 - Unit Masonry

00 01 10 - Table of Contents

OYA - Tillamook Living Units 00 01 10 - 2 08/20/2024

Permit Set

04 72 00 - Cast Stone Masonry

DIVISION 05 -- METALS

05 12 00 - Structural Steel Framing 05 31 00 - Steel Decking 05 40 00 - Cold-Formed Metal Framing 05 50 00 - Metal Fabrications 05 51 33 - Metal Ladders 05 52 13 - Pipe and Tube Railings

DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

06 10 00 - Rough Carpentry 06 17 53 - Shop-Fabricated Wood Trusses 06 20 00 - Finish Carpentry 06 41 00 - Architectural Wood Casework 06 83 16 - Fiberglass Reinforced Paneling

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07 21 00 - Thermal Insulation 07 25 00 - Weather Barriers 07 41 13 - Metal Roof Panels 07 46 46 - Fiber-Cement Siding 07 54 00 - Thermoplastic Membrane Roofing 07 62 00 - Sheet Metal Flashing and Trim 07 71 23 - Manufactured Gutters and Downspouts 07 84 00 - Firestopping 07 92 00 - Joint Sealants 07 95 13 - Expansion Joint Cover Assemblies

DIVISION 08 -- OPENINGS

08 11 13 - Detention Grade Metal Doors and Frames 08 14 16 - Flush Wood Doors 08 31 00 - Access Doors and Panels 08 71 00 - Door Hardware 08 71 63 - Detention Door Hardware 08 80 00 - Glazing 08 91 00 - Louvers

DIVISION 09 -- FINISHES

09 06 00 - Schedule of Finishes 09 21 16 - Gypsum Board Assemblies (Revised 02/25/2025) 09 24 00 - Cement Plastering 09 51 00 - Acoustical Ceilings 09 65 00 - Resilient Flooring 09 67 00 - Fluid-Applied Flooring 09 68 16 - Sheet Carpeting

OYA - Tillamook Living Units 00 01 10 - 3 08/20/2024

Permit Set

09 72 00 - Wall Coverings 09 83 00 - Acoustic Finishes 09 90 00 - Painting and Coating 09 96 00 - High-Performance Coatings

DIVISION 10 -- SPECIALTIES

10 14 00 - Signage 10 14 19 - Dimensional Letter Signage 10 21 13.17 - Solid Color Reinforced Composite Toilet Compartments 10 26 00 - Wall and Door Protection 10 28 00 - Toilet, Bath, and Laundry Accessories 10 44 00 - Fire Protection Specialties

DIVISION 11 -- EQUIPMENT

11 30 13 - Appliances 11 68 33 - Athletic Field Equipment 11 81 29 - Facility Fall Protection

DIVISION 12 -- FURNISHINGS

12 36 00 - Countertops 12 50 00 - Furniture

DIVISION 21 -- FIRE SUPPRESSION

21 05 00 - Common Work Results for Fire Suppression 21 05 23 - General-Duty Valves for Water-Based Fire-Suppression Piping 21 05 48 - Vibration and Seismic Controls for Fire Suppression Piping and Equipment 21 05 53 - Identification for Fire Suppression Piping and Equipment 21 11 00 - Facility Fire-Suppression Water-Service Piping 21 13 00 - Fire-Suppression Sprinkler Systems

DIVISION 22 -- PLUMBING

22 05 00 - Common Work Results for Plumbing 22 05 18 - Plumbing Expansion Compensation 22 05 19 - Meters and Gauges for Plumbing 22 05 23 - General-Duty Valves and Specialties for Plumbing 22 05 29 - Hangers, Supports, and Anchors Plumbing 22 05 48 - Vibration and Seismic Controls for Plumbing Piping and Equipment 22 05 53 - Identification for Plumbing Piping and Equipment 22 05 90 - Pressure Testing for Plumbing Systems 22 05 93 - Testing, Adjusting, and Balancing for Plumbing 22 07 00 - Insulation for Plumbing 22 08 00 - Commissioning for Plumbing 22 21 13 - Pipe and Pipe Fittings for Plumbing 22 21 23 - Pumps for Plumbing 22 25 00 - Plumbing Water Treatment 22 30 00 - Plumbing Equipment

OYA - Tillamook Living Units 00 01 10 - 4 08/20/2024

Permit Set

22 40 00 - Plumbing Fixtures

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 00 - Common Work Results for HVAC 23 05 13 - Common Motor Requirements for HVAC Equipment 23 05 16 - Expansion Fittings and Loops for HVAC Piping 23 05 17 - Sleeves and Sleeve Seals for HVAC Piping 23 05 19 - Meters and Gauges for HVAC Piping 23 05 23 - General-Duty Valves for HVAC Piping 23 05 29 - Hangers and Supports for HVAC Piping and Equipment 23 05 33 - Heat Tracing for HVAC Piping 23 05 48 - Vibration and Seismic Controls for HVAC 23 05 53 - Identification for HVAC Piping and Equipment 23 05 90 - Pressure Testing for HVAC Systems 23 05 93 - Testing, Adjusting, and Balancing for HVAC 23 07 13 - Duct Insulation 23 07 16 - HVAC Equipment Insulation 23 07 19 - HVAC Piping Insulation 23 08 00 - Commissioning of HVAC 23 09 13 - Instrumentation and Control Devices for HVAC 23 09 23 - Direct-Digital Control System for HVAC 23 09 34 - Variable-Frequency Motor Controllers for HVAC 23 21 13 - Hydronic Piping 23 21 14 - Hydronic Specialties 23 21 23 - Hydronic Pumps 23 23 00 - Refrigerant Piping 23 25 00 - HVAC Water Treatment 23 31 00 - HVAC Ducts and Casings 23 33 00 - Air Duct Accessories (Revised 02/25/2025) 23 33 19 - Duct Silencers 23 34 13 - Axial HVAC Fans 23 34 16 - Centrifugal HVAC Fans 23 34 23 - HVAC Power Ventilators 23 37 00 - Air Outlets and Inlets 23 40 00 - HVAC Air Cleaning Devices 23 51 00 - Breechings, Chimneys, and Stacks 23 52 16 - Condensing Boilers 23 65 33 - Liquid Coolers 23 81 26.13 - Small-Capacity Split-System Air Conditioners 23 81 49 - Ground-Source Unitary Heat Pumps 23 82 00 - Convection Heating and Cooling Units

OYA - Tillamook Living Units 00 01 10 - 5 08/20/2024

Permit Set

DIVISION 26 -- ELECTRICAL

26 05 00 - Common Work Results for Electrical 26 05 05 - Selective Demolition for Electrical 26 05 19 - Low-Voltage Electrical Power Conductors and Cables 26 05 26 - Grounding and Bonding for Electrical Systems 26 05 29 - Hangers and Supports for Electrical Systems 26 05 33.13 - Conduit for Electrical Systems 26 05 33.16 - Boxes for Electrical Systems 26 05 43 - Underground Ducts and Raceways for Electrical Systems 26 05 48 - Vibration and Seismic Controls for Electrical Systems 26 05 53 - Identification for Electrical Systems 26 05 73 - Power System Studies 26 05 83 - Wiring Connections 26 09 23 - Lighting Control Devices 26 09 43 - Network Lighting Controls 26 09 93 - Sequence of Operations for Lighting Controls 26 21 00 - Low-Voltage Electrical Service Entrance 26 24 13 - Switchboards 26 24 16 - Panelboards 26 27 13 - Electricity Metering 26 27 26 - Wiring Devices 26 28 13 - Fuses 26 28 16.13 - Enclosed Circuit Breakers 26 28 16.16 - Enclosed Switches 26 31 00 - Photovoltaic Collectors 26 32 13 - Engine Generators 26 33 53 - Static Uninterruptible Power Supply 26 36 00 - Transfer Switches 26 43 00 - Surge Protective Devices 26 50 00 - Lighting

DIVISION 27 -- COMMUNICATIONS

27 05 00 - Common Work Results for Communications 27 05 26 - Grounding and Bonding for Communications Systems 27 05 28 - Pathways for Communications Systems 27 08 00 - Commissioning of Communications 27 11 00 - Communications Equipment Room Fittings 27 11 19 - Communications Termination Blocks and Patch Panels 27 13 00 - Communications Backbone Cabling 27 15 00 - Communications Horizontal Cabling

DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

28 05 00 - Common Work Results for Electronic Security

OYA - Tillamook Living Units 00 01 10 - 6 08/20/2024

Permit Set

28 05 26 - Grounding and Bonding for Electronics Security 28 05 27 - Racks and Cabinets for Electronic Security 28 05 53 - Identification for Electronic Security 28 18 20 - Detention Intercom and Paging System 28 23 30 - Detention Video Surveillance Recording System 28 46 00 - Fire Detection and Alarm 28 46 13 - GUI HMI System 28 46 19 - PLC Electronic Detention Monitoring and Control System 28 50 00 - Electric Adjustable Workstations 28 80 00 - Commissioning for Electronic Security

DIVISION 31 -- EARTHWORK

31 23 00 - Excavation, Fills and Subgrade Preparation 31 23 33 - Trench Excavation and Backfill

DIVISION 32 -- EXTERIOR IMPROVEMENTS

32 10 00 - Trench Surface Restoration 32 12 16 - Hot Mixed Asphalt Concrete (HMAC) Pavements 32 16 00 - Concrete Curbs and Sidewalks 32 31 13 - Chain Link Fences and Gates 32 92 13 - Seeding and Mulching

DIVISION 33 -- UTILITIES

33 05 13 - Concrete Manholes 33 11 00 - Clearing and Grubbing 33 11 16 - Water Distribution System 33 31 00 - Sanitary Sewer System 33 40 00 - Storm Sewer System 33 44 13.13 - Catch Basins, Inlets and Junction Structures

APPENDIX A

Archaeologicial and Human Remains Inadvertent Discovery Plan (IDP) - June 9, 2024

APPENDIX B

Security Technology Responsiblity Matrix - August 20, 2024

APPENDIX C

Geotechnical Engineering Report - October 21, 2022

END OF SECTION

OYA - Tillamook Living Units 01 10 00 - 1 08/20/2024

Permit Set

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: Tillamook Living Units.

B. Owner's Name: Oregon Youth Authority.

C. The Project consists of the construction of new dormitories and clinic facility at the Tillamook

Youth Correctional Facility, plus renovation of selected portions of the existing building. The project will be performed in phases. The existing dormitories are to remain occupied during construction and be demolished once the new construction is complete.

1.02 PERMITS AND FEES

A. The Owner will be responsible for filing and paying for building permits and all fees associated with the building permit and system development charges.

B. The Contractor will be responsible for picking up all Project permits and will have full responsibility for requirements of and payments for all trade permits (i.e. electrical, plumbing, mechanical) and all costs associated with deferred submittals. Contractor shall be responsible for coordinating installation of serving utilities and is responsible for paying for all charges associated with installation of utilities.

1.03 DESCRIPTION OF ALTERATIONS WORK

A. Scope of demolition and removal work is indicated on drawings and specified in Section 02 41

00.

B. Scope of alterations work is indicated on drawings.

C. The Work shall include all supplies, tools, equipment, scaffolding, transportation, utilities, service, superintendence, labor, and the furnishing of all materials, items, and accessories needed for the Project.

1. All on-site work, including demolition, installation, and final cleaning is required to be completed during the regularly scheduled hours. Contractor is to coordinate work to accommodate the continuous operation of the adjacent streets and utilities, without interruption or hindrance.

2. The Contractor shall provide for all scheduling, coordination, cutting and patching and all other items required by the Contract Documents to complete the Work.

D. Renovate the following rooms and spaces, complete including operational mechanical and electrical work and finishes:

1. Existing Break Room.

2. Existing Laundry.

3. Existing Clinic and Clinic Office.

4. Portions of existing Indoor Recreation.

E. Plumbing: Alter existing system and add new construction, keeping existing in operation.

F. HVAC: Alter existing system and add new construction, keeping existing in operation.

G. Electrical Power and Lighting: Alter existing system and add new construction, keeping existing in operation. Add new photovoltaic (PV) array.

H. Fire Suppression Sprinklers: Alter existing system and add new construction, keeping existing in operation.

I. Fire Alarm: Alter existing system and add new construction, keeping existing in operation.

J. Security System: Alter existing system and add new construction, keeping existing in operation.

K. Owner will remove the following items before start of work:

1. All non-fixed furniture.

01 10 00 - Summary

OYA - Tillamook Living Units 01 10 00 - 2 08/20/2024

Permit Set

1.04 WORK BY OWNER

A. Items noted NIC (Not in Contract) will be supplied and installed by Owner before Date of

Substantial Completion.

B. Items noted OFOI (Owner Furnished, Owner Installed) will be supplied and installed by Owner before Substantial Completion, unless noted otherwise. Items include, but are not limited to:

1. Clinic furniture, medical equipment, and electronics.

2. Soap dispensers at youth toilet and shower rooms.

3. Paper towel dispensers at youth toilet and shower rooms.

4. Cameras.

5. Security Technology:

a. See Appendix B for a schdule of items and coordination responsibilty.

C. Contractor Responsibilties for NIC and OFOI Items:

1. Designate delivery date for each portion of the Work in the Progress Schedule (if appropriate).

2. Storage of products if requested.

3. Coordination of installation with Project Schedule.

4. Provide all preparatory work necessary for proper installation including but not limited to:

blocking, backing, and finish work including sealing, grouting, furring, preparing subfloors for finish flooring materials, and painting adjacent surfaces as required for NIC and/or OFOI products.

D. Items noted OFCI (Owner Furnished, Contractor Installed) will be supplied by the Owner and installed by the Contractor before Substantial Completion, unless noted otherwise.

1. ________.

1.05 OWNER OCCUPANCY

A. Owner intends to continue to occupy adjacent portions of the existing building during the entire construction period.

B. Owner intends to occupy the Project upon Substantial Completion.

C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

D. Schedule the Work to accommodate Owner occupancy.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

1. Locate and conduct construction activities in ways that will limit disturbance to site.

2. Review Archaeological and Human Remains Inadvertant Discovery Plan (IDP) prior to any site excavation. See Appendix A.

B. Arrange use of site and premises to allow:

1. Owner occupancy.

2. Work by Owner.

C. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

D. Time Restrictions:

1. Limit conduct of especially noisy exterior work to the hours of 9 am to 4 pm, Monday - Thursday.

2. Limit conduct of the hours of 7 am - 5 pm, Monday - Thursday.

E. Utility Outages and Shutdown:

1. Keep all existing systems in service and operating until new service is online.

OYA - Tillamook Living Units 01 10 00 - 3 08/20/2024

Permit Set

2. Utility service outages must be preapproved by OYA and scheduled at least a week in advance or longer depending on the duration of the outage and the systems affected. All efforts to minimize the outage duration must be utilized. Contractor to provide temporary power for critcal systems during outage (security, life safety systems, door controls, heating/cooling).

3. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.

4. Limit shutdown of utility services to 4 hours at a time, arranged at least 24 hours in advance with Owner.

5. Prevent accidental disruption of utility services to other facilities.

F. Limtations On Use:

1. Complete and exclusive use of the construction area except as outlined above will be permitted from Notice to Proceed until Substantial Completion of the Project. Coordinate areas available for early occupancy (if any) with Owner.

2. Smoking or open fires will not be permitted within the building enclosure or on the premises.

3. Do not encumber the site with materials or equipment. Confine stockpiling of materials and location of storage sheds to the areas indicated or coordinated with Owner.

4. Move any stored products under Contractor's control which interfere with operations of Owner or separate contractors.

G. Contractor's Site Conduct:

1. Follow Owner's policies and posted signage regarding entry and secured portions of the building.

2. Follow Owner's restrictions on mobile phone use and possession on site.

3. Identifying name tags will be worn at all times.

4. Site is tobacco- and cannabis-free. No smoking or chewing is allowed on any school property.

5. Beyond courtesy, interaction with staff is prohibited unless directed otherwise by Owner's representative.

6. Interaction with youth is prohibited.

7. Review with the Owner the scheduling of any work that is excessively noisy or has the potential to disrupt activities of Owner or neighbors.

8. Profanity is not acceptable.

9. The wearing of clothing with logos displaying alcohol, tobacco, illegal or restricted substances or suggestive themes is not acceptable attire.

10. Do not prop open doors or disable locks or latches.

1.07 SAFETY AND SITE CONTROL

A. The locations are all within youth correctional facilities. Contractor is responsible for the safety and security of the work site and any material and equipment staging areas. The Contractor shall comply with all facility access requirements for personnel and vehicles. The Contractor will provide as part of the work a temporary sally port entry around the work area to serve as a barrier to youth accessing the work area. The Contractor will ensure the area is secure at all times. Personnel doors will be kept closed when not in use.

B. All Contractor and subcontractor personnel shall wear OSHA approved, high visibility vests at all times. This is to ensure not only the normal safety protocol and procedure but also to allow OYA staff to quickly differentiate Contractor staff from residents and other visitors.

C. Gates and Building Doors are to be locked and monitored by Contractor. Gates and Building Doors are to be posted with signage stating the following at a minimum (verify exact wording with Owner):

CONSTRUCTION AREA: AUTHORIZED PERSONNEL ONLY; HARD HATS AND

PROTECTION GEAR REQUIRED; WATCH FOR FALLING MATERIAL; WATCH FOR

MOVING EQUIPMENT; WATCH FOR UNEVEN SURFACES.”

OYA - Tillamook Living Units 01 10 00 - 4 08/20/2024

Permit Set

D. Contractor shall have personnel monitoring all material movements through site or building secure perimeter.

E. Contractor shall have personnel provide end of work period jobsite sweeps.

F. Contractor shall confirm that all construction personnel have exited the site at end of work period.

G. Contractor shall provide sweeps and monitoring to ensure construction materials, tools and supplies are 100% accounted for and secured to ensure youth do not take possession.

H. Contractor will comply with all security and safety requirements and requests from Owner to ensure the security and safety of staff and youth.

I. Contractor shall immediately correct all security and safety matters the Owner identifies.

J. Contractor shall monitor and enforce clean-up, tool control activities, unlocking and locking vehicles and storage facilities inside the secure perimeter, and end of work period jobsite sweeps.

K. Gather and collect all tools and vehicle and equipment keys at day’s end as per requirements of the Oregon Youth Authority.

L. Secure all ladders and other materials or equipment that are not in use that could be used to aid youth escapes.

1.08 ASBESTOS FREE CERTIFICATION

A. Absolutely no materials containing asbestos are to be furnished or installed as part of this

Project. Ensure that no subcontractor or any of the Contractor's own forces installs any materials containing asbestos. At final closeout of the Project, provide to the Owner certification that no materials containing asbestos have been installed in the Project, and that the Project is asbestos-free as required by the State of Oregon.

1.09 OWNER-PROVIDED ASBESTOS SURVEY AND ABATEMENT

A. The Owner has furnished, at its expense, all information, requirements, reports, data, surveys and instructions required for performance of the Work of this Article. Contractor may use such information, requirements, reports, data, surveys and instructions in performing its services and is entitled to rely upon the accuracy and completeness thereof. The Architect shall not be held responsible for any errors or omissions that may arise as a result of erroneous or incomplete information provided by the Owner and/or the Owner's consultants and contractors.

1. Documents pertaining to Asbestos Survey and Abatement are available upon Contractor request.

2. If Contractor encounters a suspected asbestos-containing material, do not disturb material. Notify Architect and Owner.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION

01 20 00 - 1 08/20/2024 Permit Set

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Procedures for preparation and submittal of application for final payment.

1.02 RELATED REQUIREMENTS

A. Section 01 78 00 - Closeout Submittals: Project record documents.

1.03 SCHEDULE OF VALUES

A. Use Schedule of Values Form: AIA G703, edition stipulated in the Agreement.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Architect for approval.

C. Forms filled out by hand will not be accepted.

D. Submit Schedule of Values in duplicate within 10 days after date of Owner-Contractor

Agreement.

E. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization and bonds and insurance.

1.04 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Use Form AIA G702 and Form AIA G703, edition stipulated in the Agreement.

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval.

D. Forms filled out by hand will not be accepted.

E. Execute certification by signature of authorized officer.

F. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

G. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

H. Submit one electronic and three hard-copies of each Application for Payment.

1.05 MODIFICATION PROCEDURES

A. Submit name of the individual authorized to receive change documents and who will be responsible for informing others in Contractor's employ or subcontractors of changes to Contract Documents.

B. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect will issue instructions directly to Contractor.

C. For other required changes, Architect will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

D. For changes for which advance pricing is desired, Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any

01 20 00 - PRICE AND PAYMENT PROCEDURES

OYA - Tillamook Living Units

01 20 00 - 2 08/20/2024 Permit Set overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 5 days.

E. Contractor may propose a change by submitting a request for change to Architect, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

Document any requested substitutions in accordance with Section 01 60 00.

F. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

1. For change requested by Architect for work falling under a fixed price contract, the amount will be based on Contractor's price quotation.

2. For change requested by Contractor, the amount will be based on the Contractor's request for a Change Order as approved by Architect.

3. For pre-determined unit prices and quantities, the amount will be based on the fixed unit prices.

4. For change ordered by Architect without a quotation from Contractor, the amount will be determined by Architect based on the Contractor's substantiation of costs as specified for Time and Material work.

G. Substantiation of Costs: Provide full information required for evaluation.

1. On request, provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

2. Support each claim for additional costs with additional information:

a. Origin and date of claim.

b. Dates and times work was performed, and by whom.

c. Time records and wage rates paid.

d. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

3. For Time and Material work, submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

H. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

I. After execution of Change Order, promptly revise Schedule of Values and Application for

Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

J. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

K. Promptly enter changes in Project Record Documents.

1.06 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 70 00.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION 01 20 00

OYA - Tillamook Living Units 01 22 00 - 1 08/20/2024

Permit Set

SECTION 01 22 00

UNIT PRICES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. List of unit prices, for use in preparing Bids for quantities unknown prior to construction, applicable only to items indicated in 1.07 below.

B. Measurement and payment criteria applicable to Work performed under a unit price payment method.

1.02 RELATED REQUIREMENTS

A. Section 01 20 00 - Price and Payment Procedures: Additional payment and modification procedures.

1.03 COSTS INCLUDED

A. Provide unit prices for Unit Prices 1 through 3 listed in 1.07 of this section under Base Bid on Form A-2 Pricing Form of the Invitation to Bid (ITB).

B. Unit Prices included on Form A-2 shall include full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit; and other markups as permitted in the Owner-Contractor Agreement.

1.04 UNIT QUANTITIES SPECIFIED

A. Unit prices cover Work for which quantities are unknown prior to construction.

B. Quantities and measurements of actual Work will determine the payment amount.

1.05 MEASUREMENT OF QUANTITIES

A. Take all measurements and compute quantities. Measurements and quantities will be verified by Architect and Owner.

B. Assist by providing necessary equipment, workers, and survey personnel as required.

C. Measurement by Area: Measured by square dimension using mean length and width or radius.

D. Linear Measurement: Measured by linear dimension, at the item centerline or mean chord.

E. Capacity Measurement: Measured by equipment capacity as indicated in unit cost description.

1.06 PAYMENT

A. Payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities of Work that is incorporated in or made necessary by the Work, or removed from the Work, and accepted by the Architect and Owner, multiplied by the unit price, with no additional markups. Cost increases or reductions for Work based on unit prices will be incorporated into the project through a Change Order.

B. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from the transporting vehicle.

4. Products placed beyond the lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected Products.

1.07 SCHEDULE OF UNIT PRICES

A. The base bid includes the photovoltaic (PV) array as described and documented in the drawings and specifications, including the PV array itself (with associated mounting system, conductors, and conduits), a gravel pad, and a fenced enclosure

01 22 00 - Unit Prices

OYA - Tillamook Living Units 01 22 00 - 2 08/20/2024

Permit Set

B. The unit prices described below are intended to facilitate expanding or reducing the final size of the photovoltaic (PV) array as necessary to meet the State of Oregon 1.5% Green Energy Technology (GET) requirement (ORS 279C.527-528).

C. Unit Price 1: Expansion or reduction of photovoltaic array scope, including PV modules and associated mounting system, conductors, and conduit (price per Watt). Reference specification section 26 31 00, Photovoltaic Collectors.

D. Unit Price 2: Expansion or reduction of gravel pad at photovoltaic array location, including 8-inch minimum thickness 1"-0" compacted crushed rock over compacted subgrade (price per square foot). Reference Sheet C-121, Surfacing Plan.

E. Unit Price 3: Expansion or reduction of 7-foot chain link fence enclosure for photovoltaic collectors (price per lineal foot). Reference sheet G-103, Enlarged Site Plan - Complete.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION

01 23 00 - 1 08/20/2024 Permit Set

SECTION 01 23 00

ALTERNATES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Description of Alternates.

1.02 ACCEPTANCE OF ALTERNATES

A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner's option.

Accepted Alternates will be identified in the Owner-Contractor Agreement.

B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.

1.03 SCHEDULE OF ALTERNATES

A. Alternate No. 1 - Generator:

1. Base Bid Item: Existing generator to remain. Connect new emergency lighting to existing generator. Provide underground conduit for future generator connection to Electrical Room 1007.

2. Add Alternate Item: Provide new 300kW generator, including manufacturer's weatherproof enclosure and base diesel tank, new concrete pad, new fenced enclosure, new conductors, and two (2) new automatic transfer switches (ATS). New equipment to be located in Electrical Room 1007 and on site where indicated. Demolish existing generator, ATS, and feeder, and refeed existing emergency panel from new generator.

3. Relevant drawings include, but are not limited to, the following:

a. G-103, Enlarged Site Plan - Complete

b. S-502, Concrete Details

c. E-011, Enlarged Site Plan - Electrical

d. E-601, Details - Electrical

e. E-702, Diagrams - Electrical - Alternate Scope

4. Relevant specification sections include, but are not limited to, the following:

a. 26 05 48 - Vibration and Seismic Controls for Electrical Systems

b. 26 32 13 - Engine Generators

c. 26 36 00 - Transfer Switches

B. Alternate No. 2 - New Electrical Service for PV Array:

1. Base Bid Item: Provide complete 28 kW PV array system, including gravel pad, fenced enclosure, PV collectors, switchgear, and associated equipment, trenching, and connections to building.

2. Add Alternate Item: Provide partial infrastructure for new electrical service for 28 kW PV array system, as required to meet Tillamook People's Utility District (TPUD) requirements.

Scope includes primary conduits, secondary conduits and conductors, electrical distribution panel, and vault with lid. Coordinate work required with TPUD's installation of equipment.

3. Relevant drawings include, but are not limited to, the following:

a. E-010, Overall Site Plan - Electrical

b. E-011, Enlarged Site Plan - Electrical

c. E-703, Diagrams - Electrical - Alternate Scope

4. Relevant specification sections include, but are not limited to, the following:

a. 26 31 00 - Photovoltaic Collectors

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION 01 23 00

OYA - Tillamook Living Units 01 25 00 - 1 08/20/2024

Permit Set

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.02 RELATED REQUIREMENTS

A. Section 01 30 00 - Administrative Requirements: Submittal procedures, coordination.

B. Section 01 60 00 - Product Requirements: Fundamental product requirements, product options, delivery, storage, and handling.

1.03 REFERENCE STANDARDS

A. CSI/CSC Form 1.5C - Substitution Request (During the Bidding/Negotiating Stage); Current Edition.

B. CSI/CSC Form 13.1A - Substitution Request (After the Bidding/Negotiating Phase); Current Edition.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response. Submit using desginated forms designed below.

1. Forms included in the Project Manual are adequate for this purpose.

2. CSI/CSC Form 1.5C may be used during the bidding/negotiating stage.

3. CSI/CSC Form 13.1A may be used after the bidding/negotiating stage.

4. No other forms will be accepted.

D. Limit each request to a single proposed substitution item.

3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT

A. Submittal Time Restrictions:

1. For deadline for Bidders to submit request for substitution, see Section A.3 Solicitation

Schedule of the Instructions to Bidders (ITB). See ITB Section C.4 for instructions on request for approval of equivalents, clarification, or change for submitting substitution requests during the bidding period.

B. Submittal Form (before award of contract):

1. Submit substitution requests by completing the form attached to this section. See this form for additional information and instructions OR

2. Submit substitution requests by completing CSI/CSC Form 1.5C - Substitution Request.

See this form for additional information and instructions.

01 25 00 - Substitution Procedures

OYA - Tillamook Living Units 01 25 00 - 2 08/20/2024

Permit Set

3. Enter ITB #S-DASOBO-00015981 under Substitution Request Number or next to Owner’s name on submittal form. Submit the completed form to Single Point of Contact (SPC) identified in ITB.

3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Submittal Form (after award of contract):

1. Submit substitution requests by completing the form attached to this section. See this form for additional information and instructions OR

2. Submit substitution requests by completing CSI/CSC Form 13.1A - Substitution Request (After Bidding/Negotiating). See this form for additional information and instructions.

B. Architect will consider requests for substitutions only within 15 days after date of Agreement.

C. Submit request for Substitution for Cause within 14 days of discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

D. Submit request for Substitution for Convenience within 14 days of discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

a. Owner's compensation to the Architect for any required redesign, time spent processing and evaluating the request.

3.04 RESOLUTION

A. Architect may request additional information and documentation prior to rendering a decision.

Provide this data in an expeditious manner.

B. Architect will notify Contractor in writing of decision to accept or reject request.

3.05 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.06 CLOSEOUT ACTIVITIES

A. See Section 01 78 00 - Closeout Submittals, for closeout submittals.

END OF SECTION

© Copyright 2017 Building Systems Design Page 1 of 1

Substitution Request Form (During Procurement)

IDENTIFICATION:

Owner:

Design Professional:

Project Name:

Project Number: Date:

REFERENCE:

Specification Title:

Specification No.: Page: Article/ Paragraph:

DESCRIPTION:

Manufacturer’s Name: Model No:

Trade Name:

Proposed Substitution General Description:

CERTIFICATION:

The Undersigned certifies:

• Proposed substitution has been investigated and determined that it meets or exceeds the quality level of the specified product.

• Same warranty will be furnished for proposed substitution as for specified product.

• Same maintenance service and source of replacement parts, as applicable, is available.

• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

• Proposed substitution does not affect dimensions and functional clearances.

• Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.

Submitted and Signed by:

Name Title

Firm:

Address:

Telephone:

ATTACHED SUPPORTING DATA:

☐ Drawings ☐ Product Data ☐ Samples ☐ Tests ☐ Reports ☐ _________

A/E’s REVIEW AND ACTION:

☐ Substitution approved - Make submittals in accordance with Specification Section 01 2500.

☐ Substitution approved as noted - Make submittals in accordance with Specification Section 01 2500.

☐ Substitution rejected - Use specified materials.

☐ Substitution Request received too late - Use specified materials.

Signed by:

Name Title Date

Section 01 60 00.01Section 01 25 00.01

© Copyright 2017 Building Systems Design Page 1 of 2

Substitution Request Form (During Construction)

IDENTIFICATION:

Owner:

Contractor:

Design Professional:

Project Name:

Project Number:

Substitution Reason: ☐ For Cause ☐ For Convenience Date:

REFERENCE:

Substitution Request Title:

Substitution Request No.:

Specification Title:

Specification No.: Page: Article/ Paragraph:

DESCRIPTION:

Manufacturer’s Name: Model No:

Trade Name: Installer:

Proposed Substitution General Description:

EXPLANATION:

Reason for not providing specified item:

Differences between proposed substitution and specified item:

Proposed substitution affects other parts of work as follows:

Savings to Owner for accepting substitution:

Change to Contract Time due to accepting substitution:

Section 01 60 00.02Section 01 25 00.02

© Copyright 2017 Building Systems Design Page 2 of 2

CERTIFICATION:

The Undersigned certifies:

• Proposed substitution has been investigated and determined that it meets or exceeds the quality level of the specified product.

• Same warranty will be furnished for proposed substitution as for specified product.

• Same maintenance service and source of replacement parts, as applicable, is available.

• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

• Cost data as stated above is complete. Claims for additional costs related to accepted substitution which may subsequently become apparent are to be waived.

• Proposed substitution does not affect dimensions and functional clearances.

• Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.

• Coordination, installation, and changes in the Work as necessary for accepted substitution will be complete in all respects.

Submitted and Signed by:

Firm:

Address:

Telephone:

ATTACHED SUPPORTING DATA:

☐ Drawings ☐ Product Data ☐ Samples ☐ Tests ☐ Reports ☐ _________

A/E’s REVIEW AND ACTION:

☐ Substitution approved - Make submittals in accordance with Specification Section 01 2500.

☐ Substitution approved as noted - Make submittals in accordance with Specification Section 01 2500.

☐ Substitution rejected - Use specified materials.

☐ Substitution Request received too late - Use specified materials.

Signed by: __________________________ Date:

ADDITIONAL COMMENTS:

☐ Owner ☐ Design Professional ☐ Contractor ☐ Installer ☐ Manufacturer ☐ ________

01 30 00 - 1 08/20/2024 Permit Set

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. General administrative requirements.

B. Electronic document submittal procedures.

C. Preconstruction meeting.

D. Progress meetings.

E. Construction progress schedule.

F. Contractor's daily reports.

G. Progress photographs.

H. Coordination drawings.

I. Submittals for review, information, and project closeout.

J. Submittal format.

K. Requests for Information (RFI) procedures.

L. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Section 01 60 00 - Product Requirements: General product requirements.

B. Section 01 70 00 - Execution and Closeout Requirements: Additional coordination requirements.

C. Section 01 78 00 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

1.03 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 01 70 00 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

B. Make the following types of submittals to Architect:

1. Requests for Information (RFI).

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 ELECTRONIC DOCUMENT SUBMITTAL PROCEDURES

A. All documents transmitted for purposes of administration…