Attachment A4- Proposed Project Schedule.pdf

PDF 656 KB Posted

Attached to
RFP-48-27 CM/GC KSU Health Sciences Center
Solicitation number
RFP 785 2700000052 1
Issued by
Elliott County, Kentucky

About this file

This is a Proposed Project Schedule document for the KSU Health Science Center Construction Manager/General Contractor (CM/GC) project in Kentucky. The schedule outlines a comprehensive design and construction timeline beginning with predesign in September 2025 and extending through final project completion and building operations in 2030. Key project phases include predesign (54 days), schematic design Phase A (104 days), design development Phase B (90 days), construction documents Phase C (120 days), bidding (30 days), and construction from December 2029 through June 2032, with substantial completion targeted for June 2027 and final completion by February 2030. The schedule integrates KSU's academic calendar, incorporating fall, spring, and summer terms with identified holiday and spring break periods to coordinate project activities with institutional operations. Milestones are distributed across 2025 through 2030, with critical review periods scheduled after each design phase.

The document specifies durations for supporting activities including CM selection (prior to construction), FF&E installation and move-in (60 days), equipment pre-purchase (45 days), and RTA document preparation (7 days). The overall construction duration is estimated at 900 days (30 months) from start of construction to substantial completion. The project schedule demonstrates a phased approach aligned with standard architectural and construction industry practices, with defined start and end dates for each deliverable and review checkpoint to ensure coordinated project advancement through design and construction phases.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACADEMIC CALENDAR

JA S O N D

FALL TERM

MILESTONES DURATION

(DAYS)

START

DATE

END

DATE

FALL /

SPRING /

SUMMER

KSU HEALTH SCIENCE CENTER PROJECT SCHEDULE

J F M A M J J A S O N D

SPRING TERM FALL TERM

RUN DATE: 06/08/26

J F M A M J J A S O N D

SPRING TERM FALL TERM

PREDESIGN

SCHEMATIC DESIGN (PHASE A)

DESIGN DEVELOPMENT (PHASE B)

PHASE C REVIEW

BIDDING

FF&E INSTALLATION / MOVE-IN

CM SELECTION

(3+ mo.)

(3 mo.)

(4 mo.)

(2 wks)

(3 mo.)

(1 mo.)

(2 mo.)

PREDESIGN REVIEW

(7+ wks)

PHASE A REVIEW 14

(2 wks)

PHASE B REVIEW

(2 wks)

09/23/25 01/05/26

01/06/26 03/01/26

03/02/26 05/31/26

06/01/26 06/15/26

06/16/26 10/14/26

10/15/26 10/29/26

02/28/27 03/14/27

03/23/27 06/21/27

01/09/30 02/08/30

RTA DOCUMENTS 7

(1 wk)

SPRING TERM

J F M A M

03/22/2703/15/27

KSU Spring Break

A M J J A S O N D

FALL TERM

(4 mo.)

10/30/26 02/27/27CONSTRUCTION DOCUMENTS - PHASE C

KSU Holiday Break

BIDDING

(1 mo.) 12/09/29 01/08/30

START OF CONSTRUCTION TO SUBSTANTIAL COMPLETION

SUBSTANTIAL COMPLETION TO FINAL COMPLETION

EQUIPMENT PRE-PURCHASE

(6+ wks)

12/08/2906/22/27

(30 mo.)

KSU Holiday Break

KSU Spring Break

KSU Spring Break

KSU Holiday Break

12/29/26

J F M A MA M J J A S O N D

06/16/26 07/31/26

10/30/26

KSU 2025 BUSINESS PLAN

START OF CONSTRUCTION BUILDING IN OPERATION

SUMMER TERM SUMMER TERM SUMMER TERM SPRING TERM FALL TERMSUMMER TERM

KSU Holiday Break

KSU Spring Break

J F

SPRING TERM

KSU Holiday Break

Drafting Views (Detail)
Schedule_26 06 08

File details come from the government source that posted it. Updated .