This document provides details for a federal solicitation for trail paving and roadway micro-surfacing work. The solicitation number is 140F0920B0003 and is being issued by the Department of the Interior Fish and Wildlife Service Region 2. The solicitation seeks contractors to perform trail paving and roadway micro-surfacing at the National Conservation Training Center in West Virginia. Responses are due by the date listed on the Federal Business Opportunities website. The selected contractor will be responsible for paving existing gravel trails and applying a micro-surfacing treatment to existing roadways per the attached statement of work and drawings. The period of performance and pricing terms will be negotiated with the awarded contractor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT “A”
SPECIFICATIONS AND DRAWINGS
Trail Paving & Select Asphalt Surfacing Maintenance
NATIONAL CONSERVATION TRAINING CENTER (NCTC)
SHEPHERDSTOWN, WV
JUNE 2020
TABLE OF CONTENTS
Description Section Pages
Construction Specifications
Summary of Work 01 11 00 2 Work Restrictions 01 14 00 4 Administrative Requirements 01 30 00 3 Submittals 01 33 00 10
01 33 00 Insert: ENG Form 4025 2 01 33 00 Insert: Submittal Register 1
Demolition 02 41 00 4
Technical Project Requirements (Based on 2017 WV DOH Standard Specifications for Roads & Bridges)
Earthwork, Aggregate Base & Bituminous Paving 5
Site Specific Scopes of Work
Trail Paving 2 Overlay – Baird Drive (Bid Opt. 1) 2 Surface Treatments – Conservation Way & Roosevelt Rd.
Contract Drawings/Sketches 14
NIC
NIC - Not In Contract
NCTC
TRAIL PAVING 2020
Section 01 11 00 Summary of Work Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Facility Description
The National Conservation Training Center (NCTC) is an active training facility for the U.S. Fish and Wildlife Service. The NCTC site is a campus setting with multiple buildings, which include lodges, offices, training rooms, a large auditorium, a laboratory, dining facilities, gymnasium, operations support, a central plant and self contained water and wastewater treatment facilities. The majority of the buildings on campus were constructed between 1994 and 1997.
1.1.2 Project Description
This is a construction contract for which the contractor shall provide all supervision, labor, and materials necessary to remove and replace aged bituminous pavements on trails, re construct subbase where specified, provide a seal coat to existing paved roadways where specified, provide new shoulders where specified, correct specified drainage deficiencies and restore work areas
Perform all work as described in these documents, including all attachments.
The project consists of four distinct groupings of the work, per Contract Line Items (CLIN) in the bid schedule:
BASE BID
CLIN 010: Re pave Existing Trails CLIN 020: Conservation Way – Microsurfacing and Striping CLIN 030: Roosevelt Road – Microsurfacing and Striping
BID OPT 1
CLIN 040: Baird Drive – Overlay and Striping
1.1.3 Location
The work is located on the campus of the National Conservation Training Center, 698 Conservation Way, Shepherdstown, WV, as indicated.
1.2 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Section 01 11 00 Summary of Work Page 2
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. See Section 01 14 00 Work Restrictions, for more information on coordination requirements.
1.3 EXISTING WORK
In addition to "FAR 52.236 9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
A. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which will remain.
B. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
End of Section
Section 01 14 00 Work Restrictions Page 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD 01 Preconstruction Submittals
Sequence of Work; G
Personnel List (Access Roster); G
1.2 GENERAL FACILITY HOURS, ACCESS AND COORDINATION
1.2.1 Business Hours: NCTC is an active training campus. Normal facility business hours are between 8:00 am and 5:00 pm, Monday through Friday, excluding Government holidays.
1.2.2 Access: The Contractor, subcontractor, and all employees shall stop and check in with the guard on duty at the Guard Station every time they enter the campus.
1.2.3 The schedule and sequencing of all work shall be closely coordinated with the Contracting Officer.
1.2.4 Closed Weekend: A Closed Weekend is when no guests are scheduled to be on site and there are no events planned through a weekend. Closed weekends typically mean that the Contractor will have full use of the work site from 5:00 pm on a Friday until 11 a.m. on the following Sunday in housing units and until 6:30 a.m. on the following Monday in educational buildings and offices. Closed weekends can be confirmed generally two weeks prior to when they occur.
1.2.5 Preparation: Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
1.2.6 Unless noted otherwise, buildings will remain in operation during the entire construction period.
The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
Work Restrictions Page 2
1.2.7 Any work that involves loud or continuous noise shall be scheduled so as to create the least disturbance to guests, i.e. work creating loud noises near or within the educational buildings shall be performed outside of normal business hours as defined above; work creating loud noises near or within the lodges will not be permitted to be performed while guests will most likely be in their rooms, including nonclosed weekends. This could include activities such as excavation, saw cutting, compaction, demolition hammers, mortar mixers close to the work areas, etc. Work of this type is to be coordinated with the Contracting Officer
1.3 SPECIAL SCHEDULING REQUIREMENTS & COORDINATION OF WORK
1.3.1 Sequence of Work:
The Contractor shall submit for review and approval, a Sequence of Work that breaks down the work of this project into the proposed sequence of work and associated duration, at a minimum per trail and per roadway. The sequence shall take into account the schedule restrictions noted below and elsewhere in the specifications. The Sequence of Work shall be coordinated with the Traffic Control Plan and the Construction Schedule.
1.3.2 Trail Paving: Trail work shall be closely coordinated with the CO
Trail 08: Only a portion of the inner loop trails will be able to be closed at any one time so as to not block pedestrian traffic between the lodges and the Classrooms (Entry Auditorium, Instructional East and Instructional West) or the dining hall (Commons) while guests are on campus. The inner trails may be fully closed on weekends when there are no guests.
All other trails: See restrictions as noted in the pavement schedule.
1.3.3 Road Work:
One paved traffic lane shall be kept open from 0600 to 1700 hours on weekdays and approved, closed weekends; two lanes shall be placed in service at all other times.
Conservation Way, one way loop at Entry Auditorium: This is the arrival and departure point for guests and cannot be closed. Work to re seal Conservation Way around this loop shall be completed during a closed weekend when no guests are on site.
No more than one entrance to a parking area can be worked on or obstructed due to construction activities at any given time. Work shall be completed through final pavement before moving to the next entrance.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Work Restrictions Page 3
Ensure that Contractor personnel employed on the project become familiar with and obey NCTC regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
Access Roster: Submit a personnel list (access roster). Access will be granted based on the access roster and an official photo identification via a state issued driver's license or other means of identification as approved by the Contracting Officer. The Contractor shall provide the Contracting Officer with an updated access roster as necessary.
Vehicle Identification: The Contractor and subcontractor(s) shall have signage (magnetic ok) on each side of vehicles, clearly identifying the associated company.
No Smoking Policy: Smoking is prohibited within and outside of all buildings at NCTC, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. The Contracting Officer will identify designated smoking areas.
1.4.2 Contractor Work Outside of Normal Business Hours
Any work to be completed outside of normal business hours shall be closely coordinated with the Contracting Officer.
1.4.3 Special Requirements
Facility Events: From time to time there are various public events held at the facility. The Contractor shall adjust his work schedule and work areas as directed by the Government.
The dining facility and other amenities are not available for Contractor use.
No parking in fire lanes. Fire lanes can be used for access into the building for the delivery of material only. Vehicles shall be removed immediately after the delivery is complete.
Drive and park only on paved roads and pathways.
Parking: Employees shall park at the Support Services parking lot. Generally, only one (1) vehicle, such as a foreman's vehicle, shall be permitted to park near the worksite.
1.4.4 Storage and Staging Areas:
There is a contractor staging area that is adjacent to Support Services. Storage trailer(s) can be parked here, in area(s) designated by the Contracting Officer.
Overnight storage for pavers, rollers and similar equipment will be in areas designated by the
COR.
There shall be no driving or parking on the grass shoulders.
Work Restrictions Page 4
1.5 JOB CONDITIONS
1.5.1 Water for paving operations will be made available for the contractor’s use. Coordinate with the COR.
1.5.2 No facility amenities are available to the contractor. The contractor shall provide and maintain restroom facilities for their employee’s use.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Section 01 30 00 Administrative Requirements Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 SUPERVISION
1.1.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job site at all times during the performance of contract work. The Superintendent shall have the authority to act on behalf of the Contractor in all areas, to include schedule and price.
1.1.2 Superintendent Qualifications
The project superintendent shall have a minimum of 5 years experience in construction with at least 2 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.1.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day to day production and schedule adherence on the project. The superintendent or qualified alternative must be on site at all times during the performance of this contract until the work is completed and accepted.
1.1.3 Non Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.2 PRECONSTRUCTION
Once the contract has been awarded, but prior to the start of work at the site, the Contractor shall attend a pre work meeting to discuss the schedule and details of the construction. As a minimum, Section 01 30 00 Administrative Requirements Page 2 attendance shall be the contractor’s project manager, and designated site superintendent, the testing company, a technical representative from the asphalt pavement supplier and the Contracting Officer’s Representative (COR). The agenda shall include:
Review of the schedule & sequence of construction Traffic control Testing Plan Coordination Issues & after hours work
1.3 PROGRESS & COORDINATION MEETINGS
Coordination meetings shall be held as requested by either the Government or the Contractor. The intent of the meeting shall be to discuss the progress of work, schedule, work hours, potential changes, etc.
The Government may choose to schedule recurring progress/coordination meetings on a weekly or biweekly basis.
1.4 HOUSEKEEPING
1. The General Contractor and all subcontractors are to remove dust, debris and other waste from the job site on a daily basis.
2. Waste is to be properly bagged and stored for removal in a timely manner.
3. A wetting agent is to be used to suppress dust where possible.
4. All interior absorptive materials are to be protected from moisture and inspected for signs of moisture damage prior to installation.
1.5 VEGETATION RESTORATION
General: It is not expected that the Contractor will need to restore any vegetated areas during this contract, but if damage to vegetation occurs, the Contractor shall proceed with restoration at their own expense.
1. The Contractor shall provide screened topsoil that has been properly amended for growing turf grass. The Contractor shall have the topsoil tested to determine the quantity and type of amendment required for lawn type grasses.
2. All areas to be seeded shall be fine graded. The finished grade shall be uniform and free of irregularities or waterpockets. The finished grade shall be free of weed and plant growth, stones over 1 inch in diameter, or other debris. Immediately prior to seeding, all areas shall be cultivated to provide a reasonably firm but friable seedbed. The depth of tillage shall be 3 inches. Limestone as required and fertilizer as specified shall be worked into the upper 3 inches of the seedbed before seeding.
Section 01 30 00 Administrative Requirements Page 3
3. Seed Mixture:
Kentucky 31 Fescue: 45 lbs per acre RedFescue (Pennlawn): 20 lbs per acre Kentucky Bluegrass: 25 lbs per acre
4. Damaged trees shall be addressed on a case by case basis.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Section 01 33 00 Submittal Procedures Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
The Contractor shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications;
warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions
Submittal requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD 01 Preconstruction Submittals (PS)
Submittals which are required prior to the start of construction.
SD 02 Shop Drawings (SD)
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Section 01 33 00 Submittal Procedures Page 2
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD 03 Product Data (PD)
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD 04 Samples (SM)
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD 05 Design Data (DD)
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD 06 Test Reports (TR)
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Section 01 33 00 Submittal Procedures Page 3
SD 07 Certificates (CT)
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Text of posted operation instructions.SD 08 Manufacturer's Instructions (MI)
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD 09 Manufacturer's Field Reports (MF)
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.SD 10 Operation and Maintenance Data (OM)
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD 11 Closeout Submittals (CS)
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi phase contract.
Section 01 33 00 Submittal Procedures Page 4
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD 01 Preconstruction Submittals
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved Submittals (G)
Within the terms of the Contract Clause 52.236 21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, these are considered to be "shop drawings."
1.4.2 For Information Only Submittals (FIO)
These are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 PREPARATION
1.5.1 Transmittal Form
Use the sample transmittal form, (ENG Form 4025 R), at the end of this specification section, for submitting both Government approved and for information only submittals.
1.5.2 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD 04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described above. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Section 01 33 00 Submittal Procedures Page 5
Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through a secure electronic file sharing system.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Samples SD 04 Samples
1. Submit one sample, or one set of samples showing range of variation, of each required item. The sample or set of samples will be retained by approving authority.
2. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
3. Submit one sample installation, where directed.
4. Submit one sample of non solid materials.
1.6.2 Number of Copies of SD 10 Operation and Maintenance Data
Submit four copies of O&M Data to the Contracting Officer for review and approval.
1.7 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 SUBMITTAL REGISTER
Attached at the end of this specification section is a submittal register showing items of equipment and materials for which submittals are required by the specifications. Prepare and maintain the submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. This list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Section 01 33 00 Submittal Procedures Page 6
Column (d): Lists each submittal description (SD No. and type, e.g. SD 02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.8.1 Use of Submittal Register
Submit submittal register. Submit project schedule. Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.8.2 Contractor Use of Submittal Register
Update the following fields with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.8.3 Approving Authority Use of Submittal Register
Update the following fields in the program utilized by Contractor.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Section 01 33 00 Submittal Procedures Page 7
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.8.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.9 VARIATIONS
Variations from contract requirements require Government approval pursuant to contract Clause FAR
52.236 21 and will be considered where advantageous to Government.
1.9.1 Considering Variations
Discussion with Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP), see clause 52.248 3..
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.9.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 (transmittal form) for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.9.3 Warranting that Variations are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record (DOR), warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.9.4 Review Schedule Extension
Section 01 33 00 Submittal Procedures Page 8
In addition to normal submittal review period, a period of 14 calendar days will be allowed for consideration by the Government of submittals with variations.
1.10 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
1. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
2. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
3. Re submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re submittal is required.
4. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.11 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
1. Note date on which submittal was received.
2. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
3. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date submittals.
Two copies of the submittal will be retained by the Contracting Officer and zero copies of the hard copy submittals will be returned to the Contractor, unless additonal hard copies have been provided for this purpose.
1.11.1 Review Notations
Contracting Officer review will be completed no later than 30 calendar days after receipt by the Government. Submittals will be returned to the Contractor with the following notations:
Section 01 33 00 Submittal Procedures Page 9
1. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
2. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
3. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
4. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.12 DISAPPROVED OR REJECTED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications;
notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer.
Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.13 APPROVED/ACCEPTED SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the project quality control.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.14 APPROVED SAMPLES
Section 01 33 00 Submittal Procedures Page 10
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. Contractor to replace such materials or equipment to meet contract requirements.
Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.
1.15 STAMPS
The Contractor shall use a standard stamp on the submittal data to certify that the submittal has been reviewed by the prime contractor and that it meets contract requirements.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Section 02 41 00 Demolition Page 1
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385 1 1 (2014) Safety and Health Requirements Manual
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of wrecking or taking out any load supporting structural member of a facility together with any related handling and disposal operations.
1.2.1.2 Deconstruction
Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials.
1.2.1.3 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.2 Demolition Plan
Prepare a Demolition Plan and submit proposed demolition and removal procedures for approval before work is started. The Demolition plan shall be coordinated with the scheduling requirements noted in Section 01 14 00, and the associated Sequence of Work.
1.2.3 General Requirements
Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. Remove rubbish and debris from Government property daily, unless otherwise directed.
Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the
Demolition Page 2 interest of occupational safety and health, perform the work in accordance with EM 385 1 1, Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer. Coordinate the work of this section with all other work indicated.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
1.3.2 Trees
Protect trees within the project site which might be damaged during demolition or deconstruction. It is anticipated that no trees will need to be removed in the work of this project. Replace any tree designated to remain that is damaged during the work under this contract with like kind or as approved by the Contracting Officer.
1.3.3 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations.
1.3.4 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD 01 Preconstruction Submittals
Demolition Plan; G
Demolition Page 3
SD 11 Closeout Submittals
Receipts
1.6 QUALITY ASSURANCE
Comply with federal, state, and local hauling and disposal regulations.
1.7 PROTECTION
1.7.1 Traffic Control Signs
A. Where pedestrian safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the Contracting Officer prior to beginning such work.
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 DISPOSITION OF MATERIAL
3.1.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.1.2 Reuse of Materials and Equipment
Remove and store materials and equipment indicated to be reused or relocated to prevent damage, and reinstall as the work progresses.
3.2 CLEANUP
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas.
Apply local regulations regarding hauling and disposal.
3.3 RECYCLE AND DISPOSAL OF REMOVED MATERIALS
Demolition Page 4
3.3.1 Removed Materials
Unless demolished asphalt pavements have unsuitable material properties, asphalt removed from the site shall be recycled as RAP (recycled asphalt pavement) and either incorporated within this project or stockpiled at the asphalt plant to be used in other, future projects. Recycle Receipts (by weight), will be submitted to the Government. The Demolition Plan shall indicate the intended recycle method for demolished asphalt.
For materials not being recycled, dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations.
3.3.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
U.S. Fish & Wildlife Service, NCTC, Shepherdstown, WV – Trail Paving – Technical Project Requirements
Technical Project Requirements
EARTHWORK, AGGREGATE BASE, AND BITUMINOUS PAVING
PART 1 GENERAL
1.1 APPLICABLE PUBLICATION
All work shall conform to the requirements of the 2017 West Virginia Standard Specifications – Roads and Bridges (including the 2018, 2019 and 2020 Supplemental Specifications as applicable) unless otherwise indicated herein. Measurement and Payment sections of the WV specifications do not apply and all work shall be covered under the contracting line items of the lump sum bid and associated line items.
1.2 SUBMITTALS
Submit the following for Government review and approval:
Bituminous (Asphalt) Mix Design Aggregate Base Material (gradation and quality) data Rip rap Geotextile Tack Coat product data Microsurfacing product data Paint Striping product data Asphalt Density Test Results HDPE Pipe Culvert product data Traffic Control Plan
1.3 TESTING
All testing shall be done by an independent commercial testing laboratory at the Contractor's expense and responsibility.
PART 2 MATERIALS
2.1 AGGREGATE BASE COURSE
Aggregate base course shall conform to the requirements of section 704.6 of the WV specification Aggregate Class 1 or 3 of Table 704.6.2A and 704.6.2B.
2.3 RIP RAP
Rip rap for lined channel shall conform to the requirements of section 704.2, 704.4 and
704.6 of the WV specification, Aggregate Class 7 of Table 704.6.2A and 704.6.2B.
U.S. Fish & Wildlife Service, NCTC, Shepherdstown, WV – Trail Paving – Technical Project Requirements
2.4 ENGINEERING FABRIC (GEOTEXTILE)
Engineering fabric shall conform to the requirements of section 715.11 of the WV specification as an Engineering Fabric for Separation (715.11.7).
2.5 PIPE CULVERTS
Pipe culvert material shall be HDPE, type N-12, soil tight.
2.6 TACK COAT
Tack coat materials shall be emulsified asphalt (RS-1 or SS-1) conforming to Section 705.
2.7 ASPHALT MIX DESIGN
The job mix formulas shall be hot mix asphalt (HMA) or warm mix asphalt (WMA) WV DOH approved Superpave design mix. The mix shall utilize a PG 64-22 binder and a Design ESAL frequency of 0.3 million to 3 million.
The surface mix for the trail paving shall have an aggregate meeting the requirements of Mix Type 9.5 of Table 401.4.2B.
The surface mix for overlay paving shall have an aggregate meeting the requirements of Mix Type 12.5 of Table 401.4.2B.
The base mix shall have an aggregate meeting the requirements of Mix Type 25 of Table 401.4.2B.
Mix materials shall conform to the requirements of the subsections listed in Section 401.2 Materials of the WV specifications.
As an alternative, and per the Contractor’s preference, the existing asphalt trail material can be milled the full depth, and recycled into the new trail pavement if the Contractor has the appropriate equipment for the operation without causing disturbance outside the existing 6’ trail width. If this method is chosen, the Contractor is responsible for sampling and testing the existing pavement to develop the appropriate job mix formula for the trail, maintaining the trail paving binder and aggregate requirements above.
2.8 SURFACE TREATMENT
The surface treatment material shall comply with Section 420.2 (WVDOH 2019 Supplemental Specifications) for microsurfacing, 2FA.
U.S. Fish & Wildlife Service, NCTC, Shepherdstown, WV – Trail Paving – Technical Project Requirements
2.8 PAINT FOR PAVEMENT MARKINGS
Paint shall be in conformance with WV DOH 663, Pavement Markings, for permanent applications. Pavement markings shall not be reflective.
PART 3 EXECUTION
All work shall be performed in accordance with the applicable WV DOH spec.
3.1 TRAFFIC CONTROL
The Contractor shall submit a traffic control plan (TCP) prior to the start of any work onsite. The TCP shall incorporate pedestrian and vehicular traffic controls for the proposed work on roadways and trails. TCP plan shall comply with FHWA MUTCD and shall be coordinated with the Sequence of Work, Section 01 14 00, Work Restrictions.
The TCP shall be submitted at the same time as the Sequence of Work.
3.2 EARTHWORK
The contractor shall be responsible for obtaining all utility clearances prior to earthwork operations. Subgrades below aggregate base shall be thoroughly compacted to provide a stable platform for overlying construction. Any existing soft subgrades encountered below the existing pavement section during pavement repairs shall be brought to the attention of the Contracting Officer who will direct required measures to stabilize the subgrade. Soft subgrades resulting from inadequate protection of the subgrade from precipitation during the work shall be repaired at the contractor’s expense and responsibility. Fill and backfill shall be placed in loose lifts not exceeding 6 inches in thickness and thoroughly compacted until stable.
3.3 CLEARING & GRUBBING
WV DOH Specifications section 201. Clearing and grubbing activity shall be minimized to only those areas needed for placement of new paved areas (i.e. parking area behind the Lab building).
3.4 EXCAVATION
WV DOH Specification section 207. Topsoil shall be stockpiled on the NCTC campus.
Exact location will be determined in the field. Haul distance for topsoil is one mile or less.
3.5 AGGREGATE BASE COURSE
U.S. Fish & Wildlife Service, NCTC, Shepherdstown, WV – Trail Paving – Technical Project Requirements
Aggregate base course shall be placed and compacted in loose lifts not exceeding 6 inches in thickness. The material shall be thoroughly compacted until stable with a minimum of 4 passes of a vibratory steel drum roller or vibratory plate tamper.
3.6 TACK COAT
A tack coat shall be applied to all areas indicated in the drawings and scope per WV DOH 408. Materials shall be as indicated in PART 2 of this specification. Surfaces to receive a tack coat shall be free of excess dust and other loose material. The tack coat application rate shall be determined using a test strip(s), with the starting application rate Table 408.11 of WVDOH 408. Sand shall be used to blot up excess bituminous material when directed by the Contracting Officer.
3.7 BITUMINOUS PAVEMENT PLACEMENT
The bituminous paving shall be constructed in accordance with the WV DOH 401specifications. The material shall be compacted to 92% to 96% of the maximum density of the approved mix design. Density shall be checked with a nuclear density gauge. Density tests shall be taken for every 300 feet of lane construction with a minimum of 3 tests for each day’s placement.
3.8 PIPE CULVERTS
Pipe culverts shall be constructed in accordance with the WV DOH Section 604, class B bedding.
3.9 RIPRAP LINED CHANNEL
Riprap lined channel shall be construction in accordance with the WV DOH Section 633, dumped rock gutter.
3.10 SURFACE TREATMENT – MICRO SURFACING
The surface treatment application shall be in accordance with WV DOH Section 420, Single/Multiple Course Micro Surfacing. The pavements to receive a surface treatment shall be prepared in accordance with section 420.4.6, after which a single course micro surface shall be applied.
Removal all wheelstops prior to surface treatment application. Re-install once seal coat and pavement markings are complete.
U.S. Fish & Wildlife Service, NCTC, Shepherdstown, WV – Trail Paving – Technical Project Requirements
3.11 PAVEMENT MARKINGS
Pavement markings shall be applied in accordance with WV DOH Section 663. .
Prior to applying surface treatments,…