Attachment (A) SOW_Calibration_plate.pdf

PDF 245 KB Posted

Attached to
NSLSII Calibration Plate for Fizeau Interferometer
Solicitation number
PB457974
Issued by

About this file

This Statement of Work (SOW) specifies requirements for a calibration plate for a Fizeau interferometer required by the Photon Science organization at Brookhaven National Laboratory. The calibration plate must be manufactured to precise specifications of 170x170x30mm using glass with chromium coating.

The technical requirements include a non-transparent/non-translucent specular reflective surface with a flatness of PV < λ/4, chamfering on all edges, and a specific pattern design featuring repeating dots with 2mm spacing and 4mm intervals. The deliverable must be provided within 12-14 weeks after receipt of order (ARO). The plate includes precise measurements for the pattern layout, with middle and center lines clearly defined, and 100nm measurement markings. The document includes detailed technical drawings showing both the physical dimensions and the required pattern layout for the calibration plate.

View the file

Other files

File Type Posted
Enclosure (2) Pricing Sheet 457974.pdf PDF
457974 RFQ Letter.pdf PDF
Draft PO457794.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW for Calibration plate for Fizeau interferometer

Name: Mourad Idir – Optical Metrology Group Leader 12/10/2024 Organization: Photon Science

SOW for Calibration plate for Fizeau interferometer

Project Objective This SOW is for a Calibration plate for Fizeau interferometer Project Scope The scope of this project is the delivery of a Calibration plate for Fizeau interferometer See below Drawings

LxWxH(mm) 170x170x30 Material Glass and Chromium coating

Deliverables

Deliverable Description Due Date (in # of days or weeks after contract award) Do not put a specific date in here.

Deliverables:

Calibration plate for Fizeau interferometer

12-14 weeks ARO (after receipt of order)

Signature: _____ ____________Of Requestor or Technical Rep