Attachment 6 - 50 Division Construction Cost Estimate Worksheet.xlsx

XLSX spreadsheet 229 KB Posted

Attached to
ADD/Alter Space Deficiencies, 8 SOS, Bldg 90145
Solicitation number
FA441723R0002
Issued by

About this file

This document contains a construction cost estimate worksheet for the federal contract opportunity FA441723R0002 to ADD/Alter Space Deficiencies at Building 90145, 8 SOS, Hurlburt Field. The cost estimate provides labor and material costs by construction division for the project, including site work, concrete, masonry, metals, wood and plastics, thermal and moisture protection, openings, finishes, specialties, special construction, fire suppression, HVAC, electrical, communications, electronic safety and security, exterior improvements, and utilities. The total estimated hard construction cost is $1,395,024.41. With general contractor fees of 15% for overhead and 10% for profit, sales tax of 7%, and builder's risk/performance bonds of 2%, the total estimated contract cost is $1,800,000.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Use the information from the provided prefilled division sheets to fill in the 50 Divisions Cost Estimate CSI Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab.
The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs.

Summary

CONSTRUCTION COST ESTIMATEDate:
19-May-23
COMPANY
IGE
PROJECT
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145
LOCATIONPROJECT NO.CP1033732
HURLBURT FIELD, FLORIDA
DIVISIONDESCRIPTION% by
DivisionDivision Total
DIVISION 02EXISTING CONDITIONS3.1%42,758.20
DIVISION 03CONCRETE WORK10.4%145,370.38FILL IN AS REQUIRED (this will link to the entire document)

davisjam: davisjam:

Percentages listed are place fillers. Please complete as required

DIVISION 04MASONRY11.7%163,804.05
DIVISION 05METALS1.7%24,406.91
DIVISION 06WOOD, PLASTICS AND COMPOSITES0.5%6,500.00GC Overhead15.00%
DIVISION 07THERMAL AND MOISTURE PROTECTION11.6%162,457.68GC Protit10.00%
DIVISION 08OPENINGS1.6%22,122.80Sub Overhead0.00%
DIVISION 09FINISHES1.6%22,962.07Sub Profit0.00%
DIVISION 10SPECIALTIES0.0%277.90Sales Tax7.00%
DIVISION 13SPECIAL CONSTRUCTION35.5%494,869.00This spreadsheet contains many formulas, please save a copy prior to editting in case you make a mistake. All shaded areas are either linked or contain formulas
DIVISION 21FIRE SUPRESSION1.2%16,403.89
DIVISION 22PLUMBING0.0%- 0
DIVISION 23HEATING, VENTILATING AND A/C4.1%57,404.39
DIVISION 26ELECTRICAL5.8%80,567.00
DIVISION 27COMMUNICATIONS0.2%2,645.75
DIVISION 28ELECTRONIC SAFETY AND SECURITY2.0%27,888.70
DIVISION 32EXTERIOR IMPROVEMENTS6.6%92,448.95
DIVISION 33UTILITIES2.3%32,136.75

HARD COST TOTAL 100% 1,395,024.41

GENERAL CONTRACT OFFICE OVERHEAD (Fill in%)15%209,253.66
SUBTOTAL1,604,278.08
GENERAL CONTRACTOR'S PROFIT(Fill in%)10%160,427.81
SUBTOTAL1,764,705.88
BUILDER'S RISK / PERFORMANCE BONDS (Fill in%)2%35,294.12
CONTRACT TOTAL$ 1,800,000.00

&"Arial"&8&B SHEET &P OF &N

Div1

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
ERROR:#REF!
- 0- 0- 0
Superintendent8MO4,800.0038,400.00- 0- 038,400.00
Site Clean-Up/Dumpster8MO200.001,600.001,250.0010,000.0011,600.00
Portable Toilet8MO- 0250.002,000.002,000.00
Temp. Office8MO- 01,000.008,000.008,000.00
Site Phone8MO- 0100.00800.00800.00
Safety Measures8MO- 01,500.0012,000.0012,000.00
Superintendent Truck8MO- 0950.007,600.007,600.00
Material Handling/Forklift8MO- 02,500.0020,000.0020,000.00
Project Sign1EA250.00250.00250.00250.00500.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS40,250.0060,650.00
SUBTOTAL100,900.00
Sub-Contractor's Overhead0.00%1.01
Sub-Contractor's Profit0.00%1.01
FL State Sales Tax7.00%4,245.50
TOTAL$ 105,147.52

Div2

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
EXISTING CONDITIONS
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
Construction Layout1EA4,500.004,500.00- 04,500.00
Erosion Control/Inlet Protection1LS5,000.005,000.00- 05,000.00
Remove Magnolia Tree1EA500.00500.00- 0500.00
Remove Curb and Gutter217LF5.351,160.95- 01,160.95
Remove Water Line92LF10.00920.00- 0920.00
Remove Concrete Island and Walks328SY25.008,200.00- 08,200.00
Remove Gravel110SY8.00880.00- 0880.00
Remove Asphalt332SY20.006,640.00- 06,640.00
Partial Demolition at Connection2EA1,500.003,000.00- 03,000.00
Remove Canopy System and Concrete1EA3,000.003,000.00- 03,000.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS33,800.95- 0
SUBTOTAL33,800.95
Sub-Contractor's Overhead15.00%5,070.14
Sub-Contractor's Profit10.00%3,887.11
FL State Sales Tax7.00%- 0
TOTAL$ 42,758.20

Div3

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
CONCRETE WORK
- 0- 0- 0
Excavate Footings1500CF5.508,250.001.502,250.0010,500.00
Reinforcing Steel6.2Ton1,850.0011,470.002,000.0012,400.0023,870.00
Concrete Footings70CY190.0013,300.00165.0011,550.0024,850.00
6" Slab Concrete68CY285.0019,380.00165.0011,220.0030,600.00
Finish Slab Concrete3670SF0.953,486.500.25917.504,404.00
Cure & Seal Concrete3670SF0.25917.500.451,651.502,569.00
Exterior Concrete Slab1700SF2.504,250.006.5011,050.0015,300.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS61,054.0051,039.00
SUBTOTAL112,093.00
Sub-Contractor's Overhead15.00%16,813.95
Sub-Contractor's Profit10.00%12,890.70
FL State Sales Tax7.00%3,572.73
TOTAL$ 145,370.38

Div4

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
MASONRY
- 0- 0- 0
8" Split Faced Fluted CMU700SF16.0011,200.009.506,650.0017,850.00
12" Regular CMU2030SF14.7529,942.508.0016,240.0046,182.50
4" Split Faced Fluted CMU2320SF15.0034,800.008.0018,560.0053,360.00
Grout Fill5CY185.00925.00165.00825.001,750.00
Cell Reinforcing0.5Ton975.00487.501,875.00937.501,425.00
Mortar - Type N60CF2.50150.006.50390.00540.00
Sand - Builders190CF- 0- 09.001,710.001,710.00
Masonry Ties15C80.001,200.0060.00900.002,100.00
Thru-Wall Flashing185SF2.40444.004.00730.001,174.00
Weeps1LS700.00700.0095.0095.00795.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS79,849.0047,037.50
SUBTOTAL$ 126,886.50
Sub-Contractor's Overhead15.00%19,032.98
Sub-Contractor's Profit10.00%14,591.95
FL State Sales Tax7.00%3,292.63
TOTAL$ 163,804.05

Div5

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
METALS
- 0- 0- 0
Structural Steel System (Canopy)2.5Ton4,500.0011,250.002,500.006,250.0017,500.00
Steel Decking (Canopy)330SF1.75577.502.50825.001,402.50
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS11,827.507,075.00
SUBTOTAL$ 18,902.50
Sub-Contractor's Overhead15.00%2,835.38
Sub-Contractor's Profit10.00%2,173.79
FL State Sales Tax7.00%495.25
TOTAL$ 24,406.91

Div6

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
WOOD, PLASTICS AND COMPOSITES
- 0- 0- 0
Rough Blocking1LS2,500.002,500.002,500.002,500.005,000.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS2,500.002,500.00
SUBTOTAL5,000.00
Sub-Contractor's Overhead15.00%750.00
Sub-Contractor's Profit10.00%575.00
FL State Sales Tax7.00%175.00
TOTAL$ 6,500.00

Div7

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
THERMAL AND MOISTURE PROTECTION
- 0- 0- 0
- 0- 0- 0
Simple Saver Insulation System4500SF5.2523,625.003.7516,875.0040,500.00
Rigid Insulation - End Walls2466SF0.902,219.401.503,699.005,918.40
Air/Moisture Barrier - Roof4901SF0.904,410.900.854,165.858,576.75
Air/Moisture Barrier - Wall4682SF0.241,123.680.0146.821,170.50
Prefinished Fascia Panels516SF3.751,935.005.252,709.004,644.00
Prefinished Metal Canopy @ Coiling Door50SF5.00250.007.00350.00600.00
Downspout Boots10EA7.0070.0020.00200.00270.00
Joint Sealants1LS550.00550.00150.00150.00700.00
2" Prefinished Metal Wall Panels2580SF3.488,978.4013.2034,056.0043,034.40
Prefinished Soffit433SF3.751,623.754.852,100.053,723.80
Flashing at End Walls91LF2.65241.151.25113.75354.90
Foam Fill Insulation - Low CMU Walls916SF2.001,832.001.501,374.003,206.00
Roof Fall Protection System300LF35.0010,500.005.001,500.0012,000.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS57,359.2867,339.47
SUBTOTAL124,698.75
Sub-Contractor's Overhead15.00%18,704.81
Sub-Contractor's Profit10.00%14,340.36
FL State Sales Tax7.00%4,713.76
TOTAL$ 162,457.68

Div8

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
OPENINGS
- 0- 0- 0
Galv. Insul. Steel Doors, 3'-0" W x 7'-0"6EA53.00318.00610.003,660.003,978.00
Steel Frames, 3'-0" W x 7'-0"4EA216.00864.0056.00224.001,088.00
Steel Frames, 6'-0" W x 7'-0"1EA244.00244.0062.0062.00306.00
Exterior Hardware Sets5EA400.002,000.001,200.006,000.008,000.00
Overhead Insulated Coiling Doors 12'x12'1EA400.00400.003,000.003,000.003,400.00
- 0- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS3,826.0012,946.00
SUBTOTAL16,772.00
Sub-Contractor's Overhead15.00%2,515.80
Sub-Contractor's Profit10.00%1,928.78
FL State Sales Tax7.00%906.22
TOTAL$ 22,122.80

Div9

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
FINISHES
- 0- 0- 0
- 0- 0- 0
Interior Paint - Steel440SF1.85814.000.96422.401,236.40
Interior Paint - CMU2102SF1.092,291.180.33693.662,984.84
Finish Doors6EA25.00150.0015.0090.00240.00
Metal Studs700SF0.86602.000.55385.00987.00
Gypsum Board1300SF1.001,300.001.501,950.003,250.00
Paint Gypsum Board1300SF0.851,105.000.65845.001,950.00
Accoustical lay-in Ceiling System1236SF3.504,326.002.252,781.007,107.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS10,588.187,167.06
SUBTOTAL$ 17,755.24
Sub-Contractor's Overhead15.00%2,663.29
Sub-Contractor's Profit10.00%2,041.85
FL State Sales Tax7.00%501.69
TOTAL$ 22,962.07

Div10

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
SPECIALTIES
- 0- 0- 0
Signage5EA7.0035.0035.00175.00210.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS35.00175.00
SUBTOTAL$ 210.00
Sub-Contractor's Overhead15.00%31.50
Sub-Contractor's Profit10.00%24.15
FL State Sales Tax7.00%12.25
TOTAL$ 277.90

Div13

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
SPECIAL CONSTRUCTION
- 0- 0- 0
PEMB-Main4000SF32.00128,000.0062.35249,400.00377,400.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS128,000.00249,400.00
SUBTOTAL377,400.00
Sub-Contractor's Overhead15.00%56,610.00
Sub-Contractor's Profit10.00%43,401.00
FL State Sales Tax7.00%17,458.00
TOTAL$ 494,869.00

Div21

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
FIRE SUPRESSION
- 0- 0- 0
Wet pipe Fire Suppression3950SF2.6510,467.50- 010,467.50
Test1EA2,500.002,500.00- 02,500.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS12,967.50- 0
SUBTOTAL12,967.50
Sub-Contractor's Overhead15.00%1,945.13
Sub-Contractor's Profit10.00%1,491.26
FL State Sales Tax7.00%- 0
TOTAL$ 16,403.89

Div22

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGE
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
PLUMBING
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS- 0- 0
SUBTOTAL$ - 0
Sub-Contractor's Overhead0.00%- 0
Sub-Contractor's Profit0.00%- 0
FL State Sales Tax7.00%- 0
TOTAL$ - 0

Div23

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGE
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
HEATING, VENTILATING AND A/C
- 0- 0- 0
CHW AHU1EA2,200.002,200.0015,000.0015,000.0017,200.00
Commissioning1LOT3,500.003,500.00- 0- 03,500.00
Controls1LOT3,500.003,500.002,500.002,500.006,000.00
Ductwork180LF15.002,700.008.651,557.004,257.00
Grilles15EA35.00525.0060.00900.001,425.00
CHW Piping220LF12.252,695.005.401,188.003,883.00
CHW Pump1EA750.21750.213,500.003,500.004,250.21
Test and Balance1LOT3,500.003,500.00- 0- 03,500.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS19,370.2124,645.00
SUBTOTAL$ 44,015.21
Sub-Contractor's Overhead15.00%6,602.28
Sub-Contractor's Profit10.00%5,061.75
FL State Sales Tax7.00%1,725.15
TOTAL$ 57,404.39

Div26

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
ELECTRICAL
- 0- 0- 0
Elec. Demolition1LS700.00700.00500.00500.001,200.00
- 0- 0- 0
NEW WORK- 0- 0- 0
Lighting Fixtures1LS6,000.006,000.0012,000.0012,000.0018,000.00
Emergency Lighting System1LS- 0- 02,750.002,750.002,750.00
Lighting Controls (includes plug load)1LS550.00550.001,200.001,200.001,750.00
Exterior Lighting1LS2,200.002,200.002,200.002,200.004,400.00
Receptacles1LS2,750.002,750.001,200.001,200.003,950.00
HVAC Equipment Connections1LS1,800.001,800.001,700.001,700.003,500.00
125 Amp Breaker1EA700.00700.001,700.001,700.002,400.00
45KVA Transformer1EA1,800.001,800.002,500.002,500.004,300.00
Panel Feeder1LS5,500.005,500.005,000.005,000.0010,500.00
New Panelboard2EA1,000.002,000.002,000.004,000.006,000.00
Branch Circuits1LS1,750.001,750.001,200.001,200.002,950.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS25,750.0035,950.00
SUBTOTAL61,700.00
Sub-Contractor's Overhead15.00%9,255.00
Sub-Contractor's Profit10.00%7,095.50
FL State Sales Tax7.00%2,516.50
TOTAL$ 80,567.00

Div27

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
COMMUNICATIONS
- 0- 0- 0
NIPR/TELE Outlets1EA300.00300.00250.00250.00550.00
1" Conduit1LS1,000.001,000.00500.00500.001,500.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS1,300.00750.00
SUBTOTAL2,050.00
Sub-Contractor's Overhead15.00%307.50
Sub-Contractor's Profit10.00%235.75
FL State Sales Tax7.00%52.50
TOTAL$ 2,645.75

Div28

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
ELECTRONIC SAFETY AND SECURITY
- 0- 0- 0
Wall Speakers/Stobes5EA120.00600.00220.001,100.001,700.00
Ceiling Strobes2EA100.00200.00160.00320.00520.00
Pull Stations5EA60.00300.00100.00500.00800.00
Replace Existing System1LS4,000.004,000.005,400.005,400.009,400.00
System Wiring and Conduit1LS3,000.003,000.003,500.003,500.006,500.00
Testing1LS2,000.002,000.00500.00500.002,500.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS10,100.0011,320.00
SUBTOTAL21,420.00
Sub-Contractor's Overhead15.00%3,213.00
Sub-Contractor's Profit10.00%2,463.30
FL State Sales Tax7.00%792.40
TOTAL$ 27,888.70

Div32

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
EXTERIOR IMPROVEMENTS
- 0- 0- 0
Fill Material/Compaction/Grading250CY22.005,500.0022.005,500.0011,000.00
Concrete222SY8.001,776.0025.005,550.007,326.00
FDOT SP 12.5 Asphalt116SY6.00696.0022.002,552.003,248.00
6" Graded Aggregate Base116SY5.00580.0018.502,146.002,726.00
12" Compacted Subgrade116SY3.00348.00- 0- 0348.00
FDOT Type F Curb143LF6.00858.0022.003,146.004,004.00
8" PVC Roof Collection System142LF32.504,615.0025.003,550.008,165.00
- 0- 0- 0
12" PVC Roof Collection System62LF35.002,170.0028.001,736.003,906.00
18" HDPE Stormwater Piping75LF42.003,150.0032.002,400.005,550.00
18" Nyloplast Inlet2EA1,300.002,600.002,400.004,800.007,400.00
Doghouse Stormwater Manhole1EA4,500.004,500.004,800.004,800.009,300.00
Stormwater Cleanout4EA450.001,800.001,200.004,800.006,600.00
Place/Water Sod150SY3.00450.005.00750.001,200.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS29,043.0041,730.00
SUBTOTAL70,773.00
Sub-Contractor's Overhead15.00%10,615.95
Sub-Contractor's Profit10.00%8,138.90
FL State Sales Tax7.00%2,921.10
TOTAL$ 92,448.95

Div33

CONSTRUCTION COST ESTIMATEDATE
45,065.00
PROJECTBASIS FOR ESTIMATE
CP1033732 ADD/ALTER SPACE DEFADD/ALTER SPACE DEFIECIENCES 8 SOS BUILDING 90145CODE A (No design completed)
LOCATIONCODE B (Preliminary design)
HURLBURT FIELD, FLORIDACODE C (Final design)
COMPANYPROJECT NO.OTHER (Specify)
IGECP1033732
DRAWING NO.ESTIMATORCHECKED BY
QUANTITYLABORMATERIAL
ITEM DESCRIPTIONNO. UNITSUNIT MEAS.PER UNITTOTALPER UNITTOTALTOTAL COST
UTILITIES
- 0- 0- 0
10" Water line-fittings included86LF65.005,590.0080.006,880.0012,470.00
4" Sewer Lateral1LS1,000.001,000.003,000.003,000.004,000.00
2" Water service1LS2,000.002,000.003,000.003,000.005,000.00
Bollards8EA160.001,280.00230.001,840.003,120.00
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
- 0- 0- 0
TOTAL LABOR/MATERIALS9,870.0014,720.00
SUBTOTAL24,590.00
Sub-Contractor's Overhead15.00%3,688.50
Sub-Contractor's Profit10.00%2,827.85
FL State Sales Tax7.00%1,030.40
TOTAL$ 32,136.75