ATTACHMENT 4 - Brand Name Justification - St. Cloud Parking.pdf

PDF 252 KB Posted

Attached to
Y1LZ--Construct Parking Structure for Patient Access (Minor) - St Cloud VAMC Federal contract opportunity
Solicitation number
36E77620B0006
Issued by
Department of Veterans Affairs Headquarters

About this file

This document contains a justification for other than full and open competition for a federal construction contract. The justification is for the Construct Parking for Patient Access Construction project at the St. Cloud VA Medical Center, which will be awarded as a firm-fixed price contract valued between $10 million and $20 million.

The justification seeks approval for two brand name items - Best lock cores and Johnson Controls HVAC controls. These items have been standardized throughout the St. Cloud VAMC and installing different systems would create duplication of costs and potential incompatibility issues. The overall procurement will be competed as a Service-Disabled Veteran-Owned Small Business set-aside, with the justification posted to the solicitation on Contracting Opportunities. The solicitation number is 36E77620B0006 and is expected to be issued in late July or early August 2020, with a period of performance of approximately 487 calendar days from notice to proceed.

View the file

Other files for this federal contract opportunity

Other files attached to Y1LZ--Construct Parking Structure for Patient Access (Minor) - St Cloud VAMC, newest first.
File Type Posted
36E77620B0006 0003.docx DOCX document
Technical Questions - FINAL No. 2 - St. Cloud Parking 8-28-2020.pdf PDF
Pavement Sections.pdf PDF
079200 JointSealants ADDENDUM.pdf PDF
Addendum Cover Sheet.pdf PDF
36E77620B0006 0002.docx DOCX document
071800 Traffic Coatings ADDENDUM.pdf PDF
Technical Questions - FINAL - St. Cloud Parking 8-26-2020.pdf PDF
071916 Silane Water Repellent Sealer ADDENDUM.pdf PDF
36E77620B0006 0001.pdf PDF
Sign In Sheet Site Visit.pdf PDF
36E77620B0006_1.docx DOCX document
ATTACHMENT 7 - Campus Map - COVID Security Information.pdf PDF
ATTACHMENT 1 - Specifications.pdf PDF
ATTACHMENT 3 - Drawings 2 of 2.pdf PDF
ATTACHMENT 2 - Drawings 1 of 2.pdf PDF
ATTACHMENT 5 - Construction Wage Rates - Stearns County - 7-10-20.pdf PDF
ATTACHMENT 6 - Contractor Safety - Environmental Record Evaluation Form.docx DOCX document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERANS AFFAIRS

Justification and Approval

For Other Than Full and Open Competition

1. Contracting Activity:

Veterans Health Administration (VHA), Program Contracting Activity Central (PCAC)

The proposed procurement, Invitation for Bid (IFB) 36E77620B0006 is for the Construct Parking for Patient Access Construction project at the St. Cloud VA Medical Center (VAMC).

2. Nature and/or Description of the Action Being Processed:

This justification is to support the Construct Parking for Patient Access Construction project at the St. Cloud VAMC, that will be awarded as a firm-fixed price contract. This justification is for other than full and open competition for the procurement of certain construction materials. The use of a particular brand name for the items listed below accommodates standardization of these items throughout the facility.

a. Lock Cores

i. Best TE Series Interchangeable Core

b. HVAC Controls

i. Johnson Controls Direct-Digital Control

3. Description of Supplies/Services Required to Meet the Agency’s Needs:

This procurement is for the Construct Parking for Patient Access Construction project at the St.

Cloud VAMC. The scope includes everything necessary to construct a new parking structure that meets the requirements of the Department of Veterans Affairs. There are two (2) brand name items listed for which the VA is not able to accept equal or alternate items. The value of these items is listed below and the VAAR Construction magnitude for the entire project is between $10,000,000 and $20,000,000.

a. Lock Cores

i. Best TE Series

ii. Value: $1,200.00

iii. Description: interchangeable core keying system door locksets.

b. HVAC Controls

i. Johnson Controls Direct-Digital Control System

ii. Value: $85,000.00

iii. Description: HVAC control system for Heating, Ventilation, and Air Conditioning, which will be incorporated into the new parking structure.

4. Statutory Authority Permitting Other than Full and Open Competition:

(X) (1) Only One Responsible Source and No Other Supplies or Services Will Satisfy

Agency Requirements per FAR 6.302-1; 41 U.S.C. § 3304(a)(1) ( ) (2) Unusual and Compelling Urgency per FAR 6.302-2;

( ) (3) Industrial Mobilization, Engineering, Developmental or Research Capability or Expert Services per FAR 6.302-3;

( ) (4) International Agreement per FAR 6.302-4 ( ) (5) Authorized or Required by Statute FAR 6.302-5;

( ) (6) National Security per FAR 6.302-6;

( ) (7) Public Interest per FAR 6.302-7;

5. Demonstration that the Contractor’s Unique Qualifications or Nature of the Acquisition Requires the Use of the Authority Cited Above (applicability of authority):

These items have been standardized throughout the St. Cloud VAMC. Installing a different manufacturers’ system will create significant duplication in cost for the facility, and in most cases the equipment will not function properly. The specific impact for not using the brand name items is listed below:

a. Lock Cores

i. Best TE Series

ii. Impact: This product is the only key core used throughout the St. Cloud VA campus.

The medical center locksmith is trained to service these locksets and maintain them in working condition. It is necessary that all lockset hardware components added onto the existing system match the brand to facilitate proper interchangeability.

Supportability of the added lock cores in the new parking structure will be accomplished with minimal additional investment in the existing system’s single standardized parts inventory.

b. HVAC Controls

i. Johnson Controls Direct-Digital Control System

ii. Impact: The patient occupied buildings, as well as the entire facility, employs the Johnson Controls system to regulate the buildings HVAC systems. The controls must be identical to the existing controls in every building to communicate with our centrally monitored Metasys System that our facility has in place. Expansion of the existing system to cover new construction will ensure compatibility and provide for seamless interface of the equipment while enhancing operability since personnel are already trained in maintenance and system operation. Supportability of the added system in the new parking structure will be accomplished with minimal additional investment in the existing system’s single standardized parts inventory.

6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable:

In accordance with the Competition in Contracting Act (CICA), the components listed above are identified as brand name; however, the overall procurement will be competed as a Service-Disabled Veteran-Owned Small-Business (SDVOSB) Set-Aside. This Justification for Other Than Full and Open Competition will be posted to Contracting Opportunities (FBO) with the solicitation.

7. Determination by the Contracting Officer (CO) that the Anticipated Cost to the Government will be Fair and Reasonable:

Government estimate was prepared and provided by the AE Firm Apogee/CEMS Joint Venture and confirmed by the Contracting Officer’s Representative (COR). The anticipated price to the Government for the items requested to be brand name is approximately $86,200.00.

The items for which brand name approval is being requested are subsequent components to the overall construction project. This procurement will be competed and based on competition; the CO will make a determination of fair and reasonable pricing prior to award.

8. Description of the Market Research Conducted and the Results, or a Statement of the Reasons Market Research Was Not Conducted:

The market research for the equipment was conducted and prepared by the COR and shared with the CO for further review. The CO was in concurrence with information provided in the estimate that supported the brand name items. Approval of the items as brand name only is critical for the overall efficiency of the completed project and the entire St. Cloud VAMC facility.

9. Any Other Facts Supporting the Use of Other than Full and Open Competition:

New components must be able to tie into an existing and operational system including the use of software. At this time, there are no competing vendors whose products are fully compatible with the existing systems being used at the St. Cloud VAMC.

10. Listing of Sources that Expressed, in Writing, an Interest in the Acquisition:

Not applicable. It is the responsibility of the offerors and the general contractor awarded the project to locate suppliers and obtain pricing for all materials and components, including the items listed in this justification.

11. A Statement of the Actions, if any, the Agency May Take to Remove or Overcome any Barriers to

Competition before Making subsequent acquisitions for the supplies or services required:

There will be competition for the overall procurement. It will be the responsibility of the offerors to obtain pricing from the suppliers of the items and to submit a competitive proposal for the project.

12. Requirements Certification: I certify that the requirement outlined in this justification is a Bona

Fide Need of the Department of Veterans Affairs and that the supporting data under my cognizance, which are included in the justification, are accurate and complete to the best of my knowledge and belief.

Robert Klein Date General Engineer St. Cloud VAMC

13. Approvals in accordance with FAR 6.304

a. Contracting Officer's Certification (required): I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.

Donald A. Marsh III Date Contracting Officer VHA Program Contracting Activity Central (PCAC)

b. One Level Above the Contracting Officer (Required over$150K but not exceeding $700K): I certify the justification meets requirements for other than full and open competition.

John Yallech, Jr. Date Supervisory Contracting Officer VHA Program Contracting Activity Central (PCAC)

6-24-2020

ROBERT G

KLEIN

646902

Digitally signed by

ROBERT G KLEIN

646902 Date: 2020.06.24 11:42:16 -05'00'

Donald A. Marsh 1489406

Digitally signed by Donald A.

Marsh 1489406 Date: 2020.06.24 14:50:48 -04'00'

John Yallech 189260

Digitally signed by John Yallech 189260 Date: 2020.06.25 08:36:48 -04'00'

File details come from the government source that posted it. Updated .