Attachment 2 SOW EGF Replace Roof 06172020.pdf
PDF 195 KB Posted
- Attached to
- Replace Roof Federal contract opportunity
- Solicitation number
- 12805B20R0014
About this file
This scope of work document outlines the requirements for replacing the roof on a USDA research building in East Grand Forks, Minnesota. The contractor will be required to remove the existing single-ply vinyl roof system and spray foam insulation, install new polyiso insulation to achieve an R-value of 35 or greater, and install a new low-profile metal standing seam roof. Additional requirements include working around existing roof-mounted equipment, providing flashing, gutters and drain spouts, submitting a safety plan, and providing 20-year manufacturer and 2-year contractor warranties. The project deliverable is to replace and overlay the new roof within 120 days.
The related federal contract opportunity is solicitation number 12805B20R0014 to replace the roof. Contractors must register to attend an optional site visit by July 24, 2020 by emailing the point of contact with company information. The soliciting agency is the USDA Agricultural Research Service Field Research Implementation and Information Delivery Plains Area.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Amendment 0001.pdf | ||
| Attachment 2 SOW Rev 1 EGF Replace Roof 06172020.pdf | ||
| Industry Question and Answers.pdf | ||
| Attachment Existing Roof Photographs.pdf | ||
| Attachment 1 Wage Determination MN20200124.pdf | ||
| Solicitation 12805B20R0014.pdf | ||
| Attachment 3 ARS-371.pdf | ||
| Attachment 4 ARS-372.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work (SOW) Project: Replace Roof on USDA Potato Research Building, East Grand Forks MN
GENERAL INFORMATION
1.0 Scope of Work: Prepare existing roof to receive Poly ISO insulation to achieve an
R-Value of 35 or greater. Provide and install a Low Profile Metal Over Metal (LPMOM) standing seam roof on existing 116’ X 160’ facility.
2.0 Background: This roof at this facility is approximately 18,600 square feet and was built in 1966. The building has a combination of single ply membrane (5,850 square feet) and metal (12,750 square feet) roofs. The membrane is showing blister and ponding and the metal roof is showing corrosion.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks:
A. Remove existing vinyl roof system which includes a single layer of membrane and spray foam insulation.
B. Install PolyIso Insulation in a minimum of 2 layers to achieve a minimum R-value of 35. Small amount of tapering required.
C. Install new low profile metal over metal (LPMOM) standing seam roof.
D. Work around existing roof mounted equipment.
1. Allow 8 hours of work by a plumber and electrician to raise the air handler unit curb approximately 1’.
E. Properly seal all openings.
F. Provide new flashing at ridge, eaves and gable ends of building.
G. Replace gutters and drain spouts.
H. Provide a safety plan addressing the safety methods used while on the roof of the building. Plan must be submitted and approved by the COR and/or CO prior to construction.
I. Provide 20 year warranty from Roofing Manufacturer on installation and materials.
J. Provide a 2 year Contractor’s warranty on installation.
4.0 Government Furnished: Photographs of roof areas are shown in attachment 1, Existing Roof Photographs. Original roof blueprints are available on site for review.
Prior appointment required.
5.0 Deliverables / Schedule:
Item No.
Deliverable
Objective
Due
1 Replace / overlay new roof on ARS, East Grand Forks, MN
Provide Weather Protection for Building Contents
120 days.
6.0 Travel: Not applicable.
7.0 Contractor’s Key Personnel:
A. On site Superintendent’s name required.
B. Operator’s certification or license on equipment that operates over buildings or personnel.
8.0 Security Requirements: All personnel shall have a U.S. photo ID, such as U.S.
Driver’s License, or U.S. passport.
9.0 Data Rights: Not applicable.
10.0 Section 508 – Electronic and Information Technology Standards: All electronic documentation to be submitted in Adobe Acrobat PDF format.
Attachment: Photographs of existing conditions are available in attachment 1.
| CONTRACTOR REQUIREMENTS |
| 3.0 Technical Requirements/Tasks: |
| A. Remove existing vinyl roof system which includes a single layer of membrane and spray foam insulation. |
| 6.0 Travel: Not applicable. |