Industry Question and Answers.pdf

PDF 40 KB Posted

Attached to
Replace Roof Federal contract opportunity
Solicitation number
12805B20R0014
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area

About this file

This document contains questions and answers regarding a federal contract solicitation to replace a roof. The solicitation seeks bids to replace an existing roof with 24 gauge steel roofing and membrane. Bidders are responsible for allowing up to 8 hours of work by subcontractors to raise an air handler unit curb by approximately 1 foot. The solicitation number is 12805B20R0014 issued by the Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area to replace the roof. Bidders must register by July 24, 2020 to attend an optional site visit by emailing the point of contact.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Roof, newest first.
File Type Posted
Amendment 0001.pdf PDF
Attachment 2 SOW Rev 1 EGF Replace Roof 06172020.pdf PDF
Questions and Answers.pdf PDF
Attachment Existing Roof Photographs.pdf PDF
Solicitation 12805B20R0014.pdf PDF
Attachment 3 ARS-371.pdf PDF
Attachment 4 ARS-372.pdf PDF
Attachment 2 SOW EGF Replace Roof 06172020.pdf PDF
Attachment 1 Wage Determination MN20200124.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question 1: I don’t see any information on what gauge steel roofing is acceptable? What type and thickness of membrane are you wanting?

Answer 1: 24 Gauge

Question 2: Work around existing roof mounted equipment. 1. Allow 8 hours of work by a plumber and electrician to raise the air handler unit curb approximately 1’. Who’s responsibility is this task?

Answer 2: It’s the bidder’s responsibility. For reference, the government’s estimate is for a subcontractor to take up to 8 hours to complete the task.