Attachment 2 - Schedule of Items.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Needle Rock Pavement Parking Repairs
Solicitation number
127EAX24Q0036
Issued by

About this file

This document is a Schedule of Items for a federal contract opportunity to repair the Needle Rock pavement parking area on the Tonto National Forest. The Contractor will be responsible for repairing damaged asphalt pavement, concrete curbing, embankment failure, and undercutting of pavement in accordance with the Statement of Objectives, Maps, and Pictures. The Solicitation Number is 127EAX24Q0036, and the Contractor must provide a Technical Proposal in the form of a Performance Work Statement or Statement of Work that outlines their technical approach, including considerations for stormwater management. The Contractor will also be responsible for mobilization, erosion and sediment control, and temporary traffic control. The contract has an estimated quantity of 1 for the Parking Area and Embankment Repair and Construction. The contracting agency is the Department of Agriculture Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT (NO OPTIONS)

SCHEDULE OF ITEMS

TONTO NATIONAL FOREST

PROJECT TITLE: NEEDLE ROCK PAVEMENT PARKING REPAIRS SOLICITATION NO: 127EAX24Q0036

SCHEDULE OF ITEMS
ITEM
NUMBERDESCRIPTIONMETHOD OF MEAS.PAY UNITEST QTYAmount
0001Parking Area and Embankment

Repair and Construction IAW Attachment Statement of Objectives, Maps and Pictures

- Mobilization

- Erosion and Sediment Control

- Temporary Traffic Control CSQ LS 1