Attachment 2 - Project Drawings.pdf
PDF 2 MB Posted
- Attached to
- INSTALL DOOR IG OFFICES, BLDG 10480 Federal contract opportunity
- Solicitation number
- FA500022R0024
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Install IG Door Offices Questions.pdf | ||
| Solicitation Amendment - FA500022R0024000.pdf | ||
| Solicitation - FA500022R0024.pdf | ||
| Attachment 5 - Supplemental Specs FXSB211098.pdf | ||
| Attachment 8 - Wage Determinations.pdf | ||
| Attachment 9 - FXSB211098 AF 66.pdf | ||
| Attachment 1 - Statement of Work.pdf | ||
| Attachment 4 - Contractors Fire Safety Guide (2017 ed).pdf | ||
| Attachment 6 - Environmental Protection Specifications on JBER (28 Oct 2020 Rev 3).pdf | ||
| Attachment 3 - JBER Lock Standards.pdf | ||
| Attachment 7 - Open Market General Specifications_10 Feb 2021.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INSTALL DOOR IG OFFICES, BLDG 10480 – COVER SHEET
A-1
INSTALL DOOR IG OFFICES, BLDG 10480 - DEMOLITION
NOTES
1 REMOVE DOUBLE DOOR
3 REMOVE CARPET TO TILE TRANSITION
REMOVE DRYWALL FLUSH TO CORRIDOR WALLS
REMOVE DISPLAY CASE4 2
REMOVE FIRE ALARM MANUAL PULL STATION
A-2
NOTES
INSTALL DOOR IG OFFICES, BLDG 10480 – NEW WORK
INSTALL NEW FIRE ALARM MANUAL PULL STATION2
INSTALL NEW 60 MINUTE FIRE RATED GLASS DOOR (SEE SHEET A-3)
REPAIR DRYWALL WHERE DISPLAY CASE WAS REMOVED,
MATCH EXISTING
TRANSITION SUSPENDED CEILING AT OLD DOOR LOCATION4
4REPAIR DRYWALL, MATCH EXISTING5
6 INSTALL NEW CARPET TO TILE TRANSITION
A-3
INSTALL DOOR IG OFFICES, BLDG 10480 – EXAMPLE PRODUCTS