1. OLD CITY HALL WILL REMAIN OPEN TO THE PUBLIC FOR THE DURATION OF THE CONTRACT. THE PUBLIC WILL ENTER AND EXIT THROUGH THE NORTH FIRST FLOOR DOOR. IF CLOSURE OF THE BUILDING ENTRY IS REQUIRED, THE CONTRACTOR SHALL NOTIFY CONTRACTING OFFICER 48 HOURS PRIOR TO ENTRY CLOSURE. NO BUILDING ENTRY SHALL BE CLOSED
WITHOUT PRIOR APPROVAL BY CONTRACTING OFFICER.
2. CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER OF THE PROPOSED WORK SCHEDULE, I.E. TYPICAL WORKDAY, PRIOR TO MOBILIZATION ON SITE.
3. CONTRACTOR WILL BE PERMITTED TO WORK MONDAY THROUGH FRIDAY BETWEEN 7:30AM AND 5:00PM. WORK PERFORMED AT ANY OTHER TIME OR ON FEDERAL HOLIDAYS MAY BE DONE ONLY WITH PRIOR WRITTEN APPROVAL OF THE
CONTRACTING OFFICER.
3.1. NO WORK WILL BE PERMITTED THE WEEK OF JULY 4th.
4. SMOKING IS PROHIBITED WITHIN THE WORK AREA.
5. WELDING OR ANY OPEN FLAME IS PROHIBITED WITHIN BUILDING, IN TEMPORARY STORAGE SHEDS, OR IN THE WORK AREAS.
WORK AREAS INCLUDE THE AREA ENCLOSED BY THE JOB FENCE, LAY DOWN AREAS, AND ANY OTHER AREAS ON THE SITE
DESIGNATED FOR THE CONTRACTOR'S USE.
6. NO FOOD OR BEVERAGE OTHER THAN WATER IS PERMITTED IN THE WORK AREAS.
7. THE CONTRACTOR IS NOT PERMITTED TO USE THE INTERIOR OF OLD CITY HALL OR ANY OF THE ENTRANCES. THE INTERIOR
SPACES ARE NOT TO BE USED FOR MATERIAL STORAGE OR FABRICATION. THE CONTRACTOR IS NOT ALLOWED IN THE
BUILDING OTHER THAN FOR REQUIRED WORK.
8. CONSTRUCTION PERSONNEL ARE NOT PERMITTED OUTSIDE THE IDENTIFIED AREA OF CONTRACT WORK EXCEPT FOR SPECIFIC WORK ITEMS SUCH AS LOADING/UNLOADING, AND CIRCULATION TO PROJECT WORK AREA.
9. CONTRACTOR SHALL ARRANGE HIS SITE FENCING SO AS TO NOT BLOCK ACCESS TO THE GATE IN THE WOOD FENCE USED
FOR REMOVAL OF TRASH FROM INDEPENDENCE SQUARE.
10. IF OPTION # 1 IS ACCEPTED THE CONTRACTOR SHALL MAINTAIN THE MAXIMUM WIDTH CLEAR PASSAGE TO ALLOW FOR PARK VISITOR ACCESS TO THE SECURITY CHECKPOINT FOR INDEPENDENCE SQUARE BUT IN NO CASE LESS SHALL THE
CLEARANCE BE LESS THAN 48".
SECURITY
1. ALL CONTRACTOR STAFF THAT WILL REQUIRE ACCESS TO THE INDEPENDENCE SQUARE AND OLD CITY HALL WORK SITE
WILL NEED TO HAVE A SECURITY CHECK PERFORMED. CONTRACTOR WILL NEED TO PROVIDE THE FOLLOWING INFORMATION OF EACH STAFF MEMBER AND ALL SUB-CONTRACTORS: FULL NAME, SOCIAL SECURITY NUMBER, AND ADDRESS. THE CONTRACTING OFFICER RESERVES THE RIGHT TO DENY ACCESS TO ALL OR ANY INDIVIDUALS.
2. ALL CONTRACTOR STAFF AND SUB-CONTRACTORS WILL BE ISSUED A BADGE THAT WILL SERVE AS IDENTIFICATION FOR THE DURATION OF THE PROJECT. BADGES WILL BE ISSUED BY INDEPENDENCE NATIONAL HISTORICAL PARK, OFFICE OF RESOURCE AND VISITOR PROTECTION, 143 S. THIRD STREET, PHILADELPHIA, PA. CONTACT THE CONTRACTING OFFICER TO ACCOMPANY YOU TO THIS OFFICE TO OBTAIN ALL BADGES. NO STAFF MEMBER WITHOUT A BADGE WILL BE PERMITTED ACCESS OR WILL BE UNESCORTED IN INDEPENDENCE SQUARE AND CONGRESS HALL. ALL BADGES SHALL BE ACCOUNTED FOR AND RETURNED TO INDEPENDENCE NATIONAL HISTORICAL PARK WHEN AN INDIVIDUAL IS NO LONGER ASSIGNED TO
THE WORK OR AT THE CONCLUSION OF THE WORK .
3. N.P.S. PROTECTION STAFF SHALL HAVE ACCESS TO THE WORK SITE AND WILL CONDUCT PERIODIC SECURITY CHECKS.
VEHICULAR ACCESS TO THE SITE
1. VEHICULAR ACCESS TO INDEPENDENCE SQUARE IS STRICTLY CONTROLLED AND MONITORED. ALL VEHICLES AND
PERSONNEL WILL BE THOROUGHLY SEARCHED PRIOR TO ACCESS BEING PERMITTED. DELIVERIES ARE PERMITTED PRIOR TO 9 AM. DELIVERIES AT ANY OTHER TIMES REQUIRE 48 HOUR NOTICE TO THE CONTRACTING OFFICER. ACCESS IS VIA A RAMP OFF OF SIXTH STREET. IT IS IMPORTANT THAT THE HISTORIC SCENE IN THE PARK BE PRESERVED FOR THE ENJOYMENT OF THE PARK'S VISITORS. FOR THAT REASON, THERE IS NO ON SITE PARKING. FOR A POSSIBLE STREET PARKING PERMIT, WHICH ALLOWS FREE PARKING AT LEGAL METERED SPACES, CONTACT DEBORAH SUMMERS AT THE
PHILADELPHIA PARKING AUTHORITY (215) 683-9745.
2. UNLOADING AND LOADING OF MATERIAL, TOOLS, AND EQUIPMENT MUST BE ARRANGED BY PERMIT FROM THE INDEPENDENCE NATIONAL HISTORICAL PARK, OFFICE OF RESOURCE AND VISITOR PROTECTION, 143 S. THIRD STREET FOR EACH DELIVERY. CONTACT THE CONTRACTING OFFICER TO ACCOMPANY YOU TO THIS OFFICE TO OBTAIN PERMIT.
3. ALL VEHICLES ON INDEPENDENCE SQUARE MUST ADHERE TO THE FOLLOWING:
3.1. ALL VEHICLES ARE REQUIRED TO USE PNEUMATIC TIRES.
3.2. THE CONTRACTOR WILL BE HELD RESPONSIBLE FOR THE PROTECTION OF THE BLUESTONE PAVERS AND BRICK
SIDEWALKS, AND WILL BE HELD ACCOUNTABLE FOR ANY DAMAGE THAT OCCURS AS A DIRECT RESULT OF THE WORK.
ALL VEHICLES THAT EXCEED A GROSS WEIGHT OF 10,000 POUNDS MUST USE THE PROTECTION DESCRIBED BELOW.
USING THIS METHOD DOES NOT RELIEVE THE CONTRACTOR OF RESPONSIBILITY TO PROTECT THE WALKWAYS FROM
DAMAGE.
3.2.1. TWO LAYERS OF 3/4" PLYWOOD, WITH A LAYER OF 1/2" EXTRUDED POLYSTYRENE (EPS) PANELING IN BETWEEN, LAID IN SUCH A MANNER THAT THE SURFACE OF THE PAVED AREA IS COVERED TO ALL EXTENDS OF ITS
SURFACE.
3.2.2. WHEN THE EPS IS COMPRESSED TO A HEIGHT THAT IS LESS THAN HALF ITS ORIGINAL THICKNESS, OR TO AN EXTENT THAT THE EPS IS NOT PROTECTING THE PAVING, IT IS TO BE REPLACED AS DESCRIBED ABOVE.
PROTECTION
1. PROVIDE PROTECTION AROUND EACH BOLLARD WITHIN THE WORK AREA. THIS IS TO CONSIST OF PLYWOOD ENCLOSURES
TO PROTECT BOLLARDS FROM DAMAGE BY VEHICLES.
2. PROVIDE PROTECTION AT GRASS AREAS. NO PENETRATION OF GROUND PLANE IS ALLOWED AT AREAS WITH
ARCHAEOLOGICAL FEATURES.
3. PROTECT PAVING FROM CONSTRUCTION ACTIVITY. PROVIDE PLYWOOD AT AREAS WITHIN CONSTRUCTION FENCE. NO
DRILLING INTO PAVING IS ALLOWED FOR FENCE OF WORK OR STAGING AREAS.
SITE/ BUILDING ACCESS
SITE PLAN AND CONSTRUCTION LIMITS
SCALE: N.T.S.
G2
LEGEND
SECURED ZONE FOR ALL VISITORS
INDEPENDENCE HALL
EAST WING
OLD
CITY
HALL
OLD CITY HALL
ENTRANCE
WORK AREA
CONTRACTOR IS TO
DISASSEMBLE THE
TEMPORARY ACCESS
PROTECTION AT THE
DOUBLE DOORS TO OPEN
THE DOORS FOR HIS
ACCESS TO THE LIBRARY.
PROVIDE TEMPORARY DUST
BARRIER PROTECTION AT
DOORWAY AND RE-ERECT
THE TEMPORARY ACCESS
PROTECTION.
ACCESSIBLE DOOR
OUTLINE OF EXISTING
PROTECTIVE WALKWAY
ACCESSIBLE DOOR
ENLARGED CEILING SECTION
NOT TO SCALE
WOOD
FRAMING /
CEILING
JOIST
WOOD LATH;
SECURE AS
REQUIRED. TYP
GENERAL NOTES:
1. THE PRIMARY GOAL OF CONSERVATION WORK IS TO MITIGATE DETERIORATION AND STABILIZE THE
EXISTING PLASTER ASSEMBLY WITH MINIMAL LOSS OF HISTORIC PLASTER.
2. RETAIN AS MUCH EXISTING MATERIAL AS POSSIBLE; REPAIR AND CONSOLIDATE RATHER THAN REPLACE.
3. USE SPECIFIED MATERIAL TO REINFORCE, STRENGTHEN, PROP, TIE, AND SUPPORT EXISTING MATERIAL OR STRUCTURE. MATERIALS MUST BE AS SPECIFIED OR APPROVED BY THE COR PRIOR TO STABILIZATION
AND REPAIR WORK.
4. USE REVERSIBLE AND/OR RE-TREATABLE PROCESSES UNLESS APPROVED IN WRITING BY THE COR.
5. USE TRADITIONAL REPLACEMENT MATERIALS AND TECHNIQUES UNLESS APPROVED IN WRITING BY THE
COR.
PLAN OF WORK:
PREP:
1. DOCUMENT PRIOR TO ANY CUTTING, MODIFICATION, OR DISASSEMBLY OF THE CEILING OR ATTIC FRAMING.
RECORD THE EXISTING CONDITIONS AND ASSEMBLY TO NOTE THE APPEARANCE, DIMENSIONS,
PLACEMENT, AND CONFIGURATION OF MODULAR ELEMENTS.
2. REMOVE BATT INSULATION ABOVE WORK AREA IN ITS ENTIRETY. AFTER REPAIR WORK IS COMPLETE AND
NEW PLASTER HAS CURED INSTALL NEW BATT INSULATION AS SPECIFIED.
3. CLEAN PLASTER AS SPECIFIED, PLACE DEBRIS IN NEW BOXES WITH LIDS. MINIMUM OF ONE BOX PER JOIST
SPACE MARKED FOR LOCATION USING APPROVED LABELING SYSTEM.
4. AFTER REMOVAL AND BOXING OF LARGER DEBRIS, USING A HEPA VACUUM, CLEAN THE REVERSE SIDE OF
THE CEILING, INCLUDING PLASTER, LATH, AND FRAMING.
5. INSPECT CEILING REVERSE AND FRAMING TO VERIFY AREAS REQUIRING TREATMENT. REPORT FINDINGS IN WRITING TO THE COR, PROVIDE A DIAGRAM OF LOCATIONS AND INCLUDE ESTIMATES OF WORK I N
EXCESS OF BASIS OF BID QUANTITIES.
CEILING PLASTER STABILIZATION:
6. SECURE LOOSE WOOD LATH AS SHOWN.
7. CAREFULLY RAISE DISTORTED PLASTER USING TEMPORARY SUPPORTS THAT HOLD PLASTER IN ORIGINAL POSITION AGAINST WOOD LATH. REMOVE SUPPORTS AFTER PLASTER IS RE-ADHERED AND TREATMENTS
ARE CURED.
8. TEMPORARILY SECURE LOOSE HISTORIC PLASTER AS APPROVED IN MOCKUP. CONNECT DETACHED
AREAS TO UNDAMAGED AREAS USING ADHESIVE LENS TISSUE.
9. UNDERCUT THE EDGES OF SOUND PLASTER ADJACENT TO REPAIRS TO PROVIDE KEYS FOR THE NEW WORK. BRUSH AND VACUUM CLEAN DUST AND DEBRIS FROM THE REPAIR AREA. REBUILD BROKEN OR MISSING PLASTER KEYS. USE BULKED ADHESIVE GROUT OR PRE-MIXED ADHESIVE TO RE-ESTABLISH
MECHANICAL KEYS BETWEEN PLASTER AND LATH.
10. ADHERE LOOSE PLASTER USING LIME PLASTER REPAIR FORMULATION AS SPECIFIED. INJECT ADHESIVE IN WIDE CRACKS AND EDGE OF LOSSES PRIOR TO CARRYING OUT OTHER REPAIRS. FILL OTHER CRACKS
WIDER THAN 1
32 INCH WITH LIME PLASTER FORMULATION AS SPECIFIED. DAMPEN PLASTER WITHIN AND
ADJACENT BEFORE APPLICATION TO REDUCE SUCTION AND PREVENT PREMATURE DRYING. CLEAN
EXCESS ADHESIVE FROM PLASTER SURFACES BEFORE IT DRIES.
11. FINISH CEILING SURFACES LEVEL AND TRUE WITH THE SURFACE OF SURROUNDING PLASTER. AFTER
PLASTER HAS CURED PREP AND PAINT CEILING TO MATCH EXISTING COLOR.
12. INSTALL NEW R 34 INSULATION ABOVE WORK AREA.
13. REMOVE TEMPORARY SUPPORTS AND PROTECTION, ADDED ATTIC WALK BOARDS AND PLYWOOD WORK
AREAS AND PERFORM FINAL CLEANING.
PLASTER KEYS,
REPLACE MISSING
& REPAIR BROKEN,
TYP.
EXISTING
PLASTER
A1
A1
ATTIC PLAN
SCALE: 18" = 1'-0"
A1
REFLECTED CEILING PLAN 4
A1
TEMPORARY ACCESS
PROTECTION. INSTALL
DUST PROTECTION TO
ISOLATE THE NPS
STAFF ACCESS PATH
AND BOOKS FROM THE
WORK. ACCESS AND
DUST PROTECTION TO
BE REMOVED BY
CONTRACTOR AT THE
END OF WORK OR BY
DIRECTION OF COR.
REMOVE BATT
INSULATION ABOVE
WORK AREA, TYP.
REPLACE WITH NEW
INSULATION AT END
OF WORK.
CLEAN & INSPECT
REVERSE SIDE OF
CEILING AS SPECIFIED
TO CONFIRM AREAS
REQUIRING
TREATMENT. REPORT
FINDINGS TO THE COR.
SCALE: 18" = 1'-0"
CARRY OUT PLASTER
CONSERVATION
AND REPAIRS AS
SPECIFIED. SEE
BASIS OF BID FOR
QUANTITIES
REQUIRED.
PROTECT/SUPPORT
DECORATIVE
PLASTER AS
REQUIRED.
CARRY OUT PLASTER
CONSERVATION AND
REPAIRS AS
SPECIFIED. TYPICAL
FOR THE ENTIRE
CEILING AREA. SEE
BASIS OF BID FOR
QUANTITIES REQUIRED.
54"+/-
APPROXIMATE
AREA OF
GYPSUM
PLASTER TO
BE REMOVED.
AFTER PLASTER REPAIRS
AND CONSERVATION
ARE COMPLETE AND
NEW PLASTER FULLY
CURED, CLEAN AND
PREP ENTIRE
PLASTER CEILING
AND PAINT TO
MATCH THE EXISTING
CEILING COLOR.
SS SCREWS
LENGTH TO FIT
CONDITION
DRILL PLASTER AT
JOIST TO SET SCREWS,
FILL HOLES WITH
FINISH PLASTER.
AT LOOSE OR UNATTACHED PLASTER
LATH CAREFULLY PUSH PLASTER
AND LATH BACK INTO PLACE TO THE
EXTENT POSSIBLE AGAINST THE
CEILING JOIST TAKING CARE NOT TO
BREAK PLASTER. DRILL 38" HOLE
THROUGH PLASTER TO LATH THEN
DRILL PILOT HOLE THROUGH THE
LATH INTO THE JOIST. SET A
STAINLESS STEEL SCREW TO HOLD
LATH INTO PLACE AND FILL HOLE
WITH FINISH PLASTER.
PATH OF TRAVEL.
PROVIDE TEMPORARY
PROTECTION FOR
FLOOR, WALLS, DOORS,
AND FRAMES AS
SPECIFIED, REQUIRED,
OR DIRECTED.
SCALE: 18" = 1'-0"
PROVIDE WALK BOARDS
AND PLYWOOD WORK
SURFACES TO LAY ON
TOP OF THE CEILING
JOISTS AS NEEDED TO
PROVIDE ACCESS TO
WORK AREAS TO
CARRY OUT THE WORK.
PROVIDE
SUPPLEMENTAL
LIGHTING IF REQUIRED.
SEE DETAIL 1/A1 FOR
REATTACHMENT OF
PLASTER LATH
WHERE REQUIRED.