INDEPENDENCE NATIONAL HISTORICAL

PARK PHILADELPHIA, PA

PMIS XXXXXX: Repair Old City Hall Library Plaster Ceiling

SPECIFICATIONS

February 25, 2022

INDE XXXXXX Old City Hall Repair Library Plaster Ceiling

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

Section 01 11 00 Summary of Work Section 01 31 00 Project Management and Coordination… Section 01 32 0 0 Construction Progress Documentation Section 01 33 00 Submittal Procedures Section 01 35 2 0 Safety Requirements Section 01 35 91 Historic Treatment Procedures. …………… Section 01 42 0 0 References Section 01 50 0 0 Temporary Facilities and Controls Section 01 73 00 Execution……………………………………………………………. 4 Section 01 74 19 Construction Waste Management and Disposal Section 01 77 00 Closeout Procedures

DIVISION 02 — EXISTING CONDITIONS

Section 02 41 16 Selective Demolition..… … … Section 02 83 30 Lead Waste Management ………………………………………… 15

DIVISION 03 — CONCRETE

NOT USED

DIVISION 04 — MASONRY

DIVISION 05 — METALS

NOT USED

DIVISION 06 — WOOD, PLASTICS AND COMPOSITES

DIVISION 07 — THERMAL AND MOISTURE PROTECTION

Section 07 XX 00 Thermal Insulaton

DIVISION 08 — DOORS, WINDOWS, AND GLAZING

DIVISION 09 — FINISHES

Section 09 90 00 Plaster and Lath………………………………………….……………. 6 Section 09 91 13 Interior Painting

APPENDICES

Appendix CM-16 Transmittal Form T 017419_WasteMgmt_Appx A_3-14-14 T 017419_WasteMgmt_Appx B_3-14-14

INDE XXXXXX Section 01 01 00

SECTION 01 11 00 SUMMARY OF WORK

PART 1- GENERAL

1.1 SUMMARY:

A. Basis of Bid: The work for PMIS XXXXXX, Repair and Conservation of the Old City Hall Library Plaster Ceiling, is to be bid as a single bid under one contract and shall include all work specified and required to repair the plaster ceiling of the second-floor library in the Old City Hall of Independence National Historical Park, and shall include, but is not limited to, all labor, equipment and materials required to accomplish the following work:

1. The installation of protective coverings, padding or other protective measures of the interior surfaces, grills and registers, windows and doors, woodwork, carpet, furnishing and/or objects remaining in the library or the work area should the work area be contained at the beginning of the work and the maintenance of the same during the course of the work.

2. The removal and proper disposal of the fiberglass batt insulation above the ceiling of the library and the cleaning of the top side of the plaster ceiling thus exposed. The cleaning of the top side of the ceiling shall include the removal by hand of larger pieces of debris and the vacuuming of the surface with a HEPA vacuum. Prior to disposal all debris removed by hand shall be made available for inspection by the COR to determine if any is to be retained by the NPS. Additional cleaning may be required under the plaster repair/conservation specifications.

3. Removal of approximately 225 SF+/- of a three-coat plaster system from the ceiling of the Old City Hall library including the associated metal lath. The work includes the erection and maintenance of a negative pressure dust containment system to prevent the dust from the demolition from spreading beyond the immediate work area.

4. Removal of approximately 50 SF +/-of a three-coat plaster system on wood lath from the ceiling of the Old City Hall library if deemed necessary, wood lath to remain in place and be reattached to the ceiling joist as required. The work includes the erection and maintenance of a negative pressure dust containment system to prevent the dust from the demolition from spreading beyond the immediate work area.

5. The consolidation and stabilization of 560 SF+/- of the existing plaster ceiling as specified or required. This work may be noncontiguous with a minimum area of consolidation and stabilization of 5 SF +/-. The work will be performed from the attic and will include the use of temporary supports as required to hold the plaster in place while it is stabilized.

6. The reattachment of 50 SF of loose or detached wood lath as specified or required by drilling holes through the plaster as specified and then drilling pilot holes in the lath and ceiling joist to set a SS screw of sufficient length to securely reattach the lath to the joist. The work includes providing supports for the plaster ceiling to enable the ceiling assembly to be carefully pushed back into position as tight or close as possible to the joist without damage to the plaster. This work may be noncontiguous with a minimum area of attachment and stabilization of 1 SF +/-.

7. The replacement of the 225 SF+/- of removed plaster and its supporting metal lath as specified or required.

8. The replacement of the 50 SF+/- of removed plaster on existing wood lath as specified or required. The work includes the erection and maintenance of a negative pressure dust containment system to prevent the dust from the plaster preparation from spreading beyond the immediate work area.

9. The removal and replacement as specified or required of 15 SF of delaminated plaster finish coat. The work includes the erection and maintenance of a negative pressure dust containment system to prevent the dust from the plaster preparation from spreading beyond the immediate work area.

10. The painting of the entire plaster ceiling of the library as specified, including the prepping of the existing plaster finishes and the sealing and priming of the new plaster finishes after curing.

11. The inspection of the exposed electrical wiring and devices in the attic including junction boxes and the miscellaneous repair to ensure code compliance and safety of the electrical wires and devices prior to covering with new insulation. This work is to be covered under an allowance, see C. Allowances below.

12. The installation of new R 26 faced batt insulation to lay on the ceiling between the joists and building structure in the attic above the library as specified.

13. Removal of all temporary protective measures including the existing protective walkway and the cleaning of the walls, windows and doors, woodwork, floor/carpet, and contents of the library and the path of travel used by the contractor and his subs and personnel to access the work area.

B. Unit prices, where included, will be used to modify the contract bid price for the addition of additional quantities of the specified work and shall include all Labor, equipment and materials. Unit prices may be used to reduce the contract price if the quantity of work covered by the unit price is ≥ 15% less than the quantity stipulated in the A. Basis of Bid above. Required Unit Prices for the work are as follows:

1. $________/SF for the removal and replacement of a three-coat plaster system on wood lath from the ceiling of the Old City Hall library, wood lath to remain in place and be reattached to the ceiling joists as required. The work includes the erection and maintenance of a negative pressure dust containment system to prevent the dust from the demolition from spreading beyond the immediate work area.

2. $________/ 5 SF for the consolidation and stabilization of the existing plaster ceiling as specified or required. This work may be noncontiguous with a minimum area of consolidation and stabilization of 5 SF +/-. The work will be performed from the attic and will include the use of temporary supports as required to hold the plaster in place while it is stabilized.

3. $________/SF for the removal and replacement as specified or required of a delaminated plaster finish coat. The work includes the erection and maintenance of a negative pressure dust containment system to prevent the dust from the plaster preparation from spreading beyond the immediate work area.

4. $________/SF for the reattachment of loose or detached wood lath as specified or required by drilling holes through the plaster as specified and then drilling pilot holes in the lath and ceiling joist to set a SS screw of sufficient length to securely reattach the lath to the joist. The work includes providing supports for the plaster ceiling to enable the ceiling assembly to be carefully pushed back into position as tight or close as possible to the joist without damage to the plaster.

C. Allowances, where included, are to be included in the contractor’s bid price total and will be applied to the defined allowance work on a time and materials basis up to the full amount of the allowance. The contractor must not perform any work that would require payment beyond the amount stipulated in the allowance without authorization of the CO and a modification to the contract to include such additional work. The work under this contract includes the following allowance:

1. The contractor shall include in the contract bid price where indicated the amount of ($8,500.00) eight thousand five hundred dollars to cover the cost of an inspection of the Old City Hall electrical wiring and devices associated with and/or attached to the ceiling and the ceiling structural system in the attic above the second-floor library for code deficiencies by a qualified, licensed electrician and the correction of minor deficiencies so identified. Minor deficiencies are defined for the purpose of this work as missing cover plates on junction boxes, unsupported or insufficiently supported wiring, loose or non-code compliant electrical connections and terminals, and similar deficiencies. Wiring size, outdated wiring, overloaded circuits and non-functioning light fixtures, devices or circuits are specifically excluded from the repairs but should be noted and reported as part of the inspection. Only those portions of the building electrical system above the library ceiling are included in the work with particular focus on those parts of the electrical system that are exposed or potentially affected by the removal and reinstallation of the attic insulation.

1.2 DURATION OF THE CONTRACT

A. Work shall be completed within 90 days from the Notice to Proceed for this given normal weather conditions. Fair and reasonable extensions may be granted for unforeseen circumstances at the desecration of the Contracting Officer. Note that newly installed plaster finishes shall be allowed a minimum of 30 days to cure prior to sealing, priming and painting and must meet the painting manufacturer’s recommendations for maximum moisture content before painting work may begin.

1.3 LOCATION: The location of the project is at Old City Hall, Independence Square at the corner of Fifth and Chestnut Streets, Philadelphia, Pennsylvania: Independence National Historical Park Building #0103.

1.4 CONTRACTOR'S USE OF PREMISES:

A. Old City Hall will remain open to the public during construction. Contractor will maintain access to the north and west elevation entrances throughout the construction phase to permit public access. A handicap ramp shall be maintained at the west entrance throughout the construction phase, as shown on the drawings.

1. The Contractor’s construction activities shall not interfere with building access including access to the second floor for public and employee use throughout the construction phase. The NPS reserves the right to reschedule work that causes excess fumes or noise which interrupts normal work.

2. The National Park Service (NPS) will not tolerate any deviation from the specifications noted for the safety of the park's staff or visitors at all times.

3. Access to the library may be restricted for portions of the work, but the contractor shall endeavor to limit the closure of the library to the minimum time required and to allow the greatest amount of access to park staff as possible.

B. The Contractor shall notify the Contracting Officer of the proposed work schedule, i.e.

typical workday, prior to mobilization on site. This is to aid NPS Protection staff in monitoring the site. The Contractor shall notify the Contracting Officer whenever work will take place on the site so that the work can be monitored and to allow for coordination with Park operations.

1. The Contractor shall at all times conduct his operations to ensure the least inconvenience to the occupants and disruption to visiting public.

a. No loud radios or other forms of music shall be permitted.

b. Loud noise shall be kept to a minimum.

c. No loud, inappropriate language toward or around any park staff or visitors.

C. The contractor will not be permitted access to other portions of the interior of Old City Hall or other Park structures unless accompanied by the Contracting Officer or their designated representative.

1. Contractor access to the building shall be restricted to the west entrance door and from there along a designated path of travel to the work site. The contractor shall endeavor to limit his construction foot traffic through the building to the greatest extent possible and shall provide protection to the existing finishes and historic building fabric if determined to be necessary by the CO.

D. Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to areas indicated on the Drawings.

E. Nonsmoking Facility: Smoking is not permitted on NPS Property at any time.

F. Work and storage of materials shall take place in the work area as prescribed by the Contracting Officer.

1.5 WORK RESTRICTIONS

A. Delivery of material: Vehicular Restrictions: It is important that the historic scene in the Park be preserved for the enjoyment of the Park’s visitors. For that reason, there is no onsite parking except to load and unload Contractor’s vehicle. For a possible street parking permit, which allows free parking at legal metered spaces, contact Philadelphia Parking Authority. Permit is good for 6 months.

1. No vehicular parking shall be permitted on brick sidewalks adjacent to Independence Square.

B. The Contractor will be permitted to work Monday through Friday between 7:30 a.m. and 5:00 p.m. Work performed at any other time or on Federal Holidays may be done only with prior approval of the Contracting Officer and the Park.

1. No work will be permitted on Flag Day.

2. No work will be permitted during the week of Independence Day

3. No access will be permitted to the Contractor during these designated time periods. No Contractor activity is permitted on site during this time period. The Contractor will secure the site against vandalism, theft and damage.

4. The Contracting Officer may, with at least 2 weeks written notice, designate additional “no work days” due to other special events.

1.6 SPECIAL CONSTRUCTION REQUIREMENTS:

A. Historic Status and Review Notice:

1. Old City Hall is a contributing structure to the Independence Hall World Heritage Site and on the List of Classified Structures. The Contractor is advised of the following:

a. The work to be performed on this building will meet the highest standards of preservation/conservation and building craftsmanship.

b. The Contractor will be intimately familiar with the Secretary of the Interior’s

Standards for the Treatment of Historic, specifically standards for preservation and rehabilitation.

c. Proper attention shall be given during construction to ensure that there is no unnecessary loss of or damage to significant or historic fabric during construction activities.

d. Maintain existing building in a weather-tight condition throughout construction period. Repair damage caused by construction operations.

Protect building and its occupants during construction period.

e. Install dust barriers as required to prevent the escape of dust and debris from the immediate work area(s) within the library.

B. Preservation of Natural Features: Confine all operations to work limits of the project.

Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the NPS.

1. Provide temporary barriers to protect existing trees and plants and root zones.

2. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with the Contracting Officer and remove agreed-on roots and branches that interfere with construction (only after written approval).

3. Do not fasten ropes, cables, or guys to trees.

C. Prior to start of work, the Contractor shall examine work site with Contracting Officer or his designated representative to determine exact limits of work and the conditions under which this work will be performed.

D. All vehicles operating on paved areas shall comply with the following requirements:

1. All vehicles are required to use pneumatic tires.

2. The Contractor will be held responsible for the protection of the brick sidewalks and will be held accountable for any damage that occurs as a direct result of the work. Any vehicles that exceed a gross weight of 10,000 pounds must use the protection described below. Using this method does not relieve the Contractor of responsibility to protect the walkways from damage.

a. Two layers of ¾” plywood, with a layer of 2” Styrofoam paneling in between, laid in such a manner that the surface of the paved area is covered to all extents of its surface.

b. When the Styrofoam has compressed to a height that is less than half its original thickness, or to an extent that the Styrofoam is not protecting the paving, it is to be replaced as described above.

3. Post signage to route pedestrians around construction as recommended by the Contracting Officer.

4. Protect pedestrian traffic by guardrails or fences.

5. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.

6. Removal: Completely remove barriers no longer needed and when approved by Contracting Officer.

E. Temporary Controls:

1. Housekeeping:

a. Keep project work site neat, orderly, and in a safe condition at all times.

b. Provide enough refuse containers for collecting construction debris and have them removed from the site or emptied daily.

c. Keep volatile wastes in covered containers, do not store within the building when not in use.

2. Proposed dumpster and/or refuse container location shall be submitted to Contractor Officer for review and approval prior to dumpster/refuse containers being brought to the site.

F. Air and Water Pollution Control:

1. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.

2. Do not dispose of volatile wastes or oils in storm or sanitary drains.

G. Provide constant protection against rain, wind, storms, frost, and heat so as to keep work and materials free from damage. At the end of each day's work, cover work likely to be damaged. During cold weather, protect work from damage by freezing.

1.7 FIELD VERIFICATION: Field verify all new and existing dimensions affecting the work of this contract before fabricating work.

1.8 QUALITY CONTROL:

A. The Contractor’s designated quality control supervisor shall be employed full time at the project site whenever contract work is in progress.

B. Methods of monitoring and controlling environmental pollution and contamination shall be used as required by regulations and laws.

1.9 CONSTRUCTION CAMP/STAGING-STORAGE AREA

A. The establishment of a construction camp area will be not permitted.

B. Establishment of a Contractor Staging Area will be permitted at a location determined by Contracting Officer adjacent to work area. Keep Contractor Staging Area neat and clean during construction work. Completely remove evidence of Contractor use and return to original condition at completion of work.

PART 2- PRODUCTS Not used.

PART 3- EXECUTION Not used.

PART 4- MEASUREMENT AND PAYMENT Not used.

END OF SECTION 01 01 00

INDE XXXXXX Section 01 31 00

SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

PART 1: GENERAL

1.1 SUMMARY

A. Contractor shall attend and participate in project meetings as defined below:

1.2 FREQUENCIES:

A. Weekly Progress Meetings: The Contracting Officer will schedule on-site meetings with the Contractor, subcontractors, as required, as well as Park Staff and the Contracting Officer’s Representative (COR). These meetings shall be held approximately once a week, and at the request of the Contracting Officer or Contractor.

B. Project Observation and Review: Coordinate with COR.

D. Final Inspection: This meeting shall be held when the work has been substantially completed, and upon request of the Contractor, as indicated in Section 01 77 00, Closeout Procedures.

E. Section Inspection: These meetings will be held on-site at the Contractor's request to inspect work prior to beginning subsequent procedures that will obscure completed work, or is contingent upon approval of completed work.

1.3 LOCATION: Meetings shall be held at Park Headquarters, 143 S. 3rd Street Philadelphia, PA, unless otherwise determined by the Contracting Officer.

PART 2: PRODUCTS Not used.

PART 3: EXECUTION Not used.

PART 4: MEASUREMENT AND PAYMENT Not used.

END OF SECTION 01 31 00

INDE XXXXXX Section 01 32 00

SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

PART 1: GENERAL

1.1 SUMMARY

A. The Contractor shall execute work according to a Construction Schedule prepared by the Contractor and submitted for review and approval to the Contracting Officer and in coordination with the Park. The purpose of the Schedule is to facilitate ongoing management of project, thorough inspection of work, and assignment of values for progress payments.

1.2 SUBMITTALS

A. The Contractor shall submit the Construction Schedule within 7 calendar days from date of Notice to Proceed.

1.3 SCHEDULE CHANGES

A. The progress of work will be monitored according to the approved schedule. The Contractor shall anticipate required changes and submit all changes for review to Contracting Officer.

1.4 FORM OF SCHEDULE: The Construction Schedule shall be a horizontal bar chart (ie

Gantt or MS Project). Provide separate bars for each trade or operation and identify each bar by proposed activity.

1.5 CONTENT OF SCHEDULE: The Construction Schedule shall show complete sequence of construction activities including, but not limited to, the following information:

A. Submittal dates, and date that approval of submittal is needed.

B. Project mobilization activities.

C. Material and equipment procurement and delivery dates.

D. Dates for beginning and ending specific construction activities.

E. Percentage of completion for each aspect of the Work at the first day of each month during Contract time.

PART 2: PRODUCTS Not used.

PART 3: EXECUTION Not used.

PART 4: MEASUREMENT AND PAYMENT Not used.

END OF SECTION 01 32 00

INDE XXXXXX Section 01 33 00

SECTION 01 33 00 SUBMITTAL PROCEDURES

PART 1 - GENERAL

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals as specified in each of specification section.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Government’s responsive action.

B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

1.3 GENERAL SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with contract documents.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Action submittals

a. Initial Review: Allow 15 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

b. Re-submittal Review: Allow 15 calendar days for review of each re-submittal.

2. Informational submittals

a. Review: Allow 10 days for review of each submittal.

D. Approved Equals:

1. For each item proposed as an "approved equal," submit supporting data, including:

a. Drawings and samples as appropriate.

b. Comparison of the characteristics of the proposed item with that specified.

c. Changes required in other elements of the work because of the substitution.

d. Name, address, and telephone number of vendor.

e. Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

2. A request for approval constitutes a representation that Contractor:

a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

b. Will provide the same warranties for the proposed item as for the item specified.

c. Has determined that the proposed item is compatible with interfacing items.

d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

e. Waives all claims for additional expenses that may be incurred as a result of the substitution

E. Additional Copies: Unless additional copies are required for final submittal, and unless Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

F. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form.

Contracting Officer will return submittals, without review, received from sources other than Contractor.

1. Transmittal Form: All material submittals shall be transmitted using National Park Service form CM-16. (A copy of the form is included in the Appendix). No action will be taken on a material submittal item unless accompanied by the transmittal form.

2. Documents required in Division 1 are to be delivered under separate cover letter. Do not use the CM-16 Transmittal form for these documents.

G. Identification: Properly label submittal for identification with the following:

1. Project name, Park, PMIS number (INDE XXXXXX), Contract number.

2. Date.

3. Submittal number or other unique identifier, including revision identifier.

a. Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).

H. Re-submittals: Make re-submittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Re-submit submittals until they are marked “Approved” or “Approved with notations.”

I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

J. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations.”

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections. If the Contractor intends on supplying materials that differ from the salient characteristics specified in the individual sections, than a submittal will be required.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable. Failure to mark selections shall be grounds for rejection.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. When compliance is required with manufacturer's printed installation instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.

d. Manufacturer's catalog cuts: Submit only pertinent pages; identify specific products proposed for use.

e. Compliance with specified referenced standards.

f. Testing by recognized testing agency.

4. Number of Copies: Submit four copies of Product Data, unless otherwise indicated. Contracting officer will return one copy. Retain copy as a Project Record Document.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents.

Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Shop work manufacturing instructions.

g. Templates and patterns.

h. Schedules.

i. Notation of coordination requirements.

j. Notation of dimensions established by field measurement.

k. Relationship to adjoining construction clearly indicated.

l. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches.

3. Number of Copies: Submit four opaque (bond) copies of each submittal. Contracting Officer will return one copy.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes generic description of sample, product name and name of manufacturer, and sample source along with submittal number and title of appropriate Specification Section.

3. Disposition: Maintain sets of approved Samples at Project site for quality control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

4. Samples for Initial Selection: Submit two manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. Contracting Officer will return submittal with options selected.

5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components;

small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets;

and components used for independent testing and inspection.

a. Number of Samples: Submit four sets of Samples. Contracting Officer will retain three Sample sets; remainder will be returned.

b. Retain Sample set as a Project Record Sample.

E. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.

F. Subcontractor List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. List must include, at a minimum, t h e Subcontractors shown in your original proposal.

1. Number of Copies: Submit three copies of subcontractor list, unless otherwise indicated.

2.2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. Contracting Officer will not return copies.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification and authorized to sign documents on behalf of that entity.

3. Informational submittals that do not comply with the requirements specified in the contract documents will be rejected and one copy will be returned.

B. Contractor's Construction Schedule: Comply with requirements specified in Division 01 Section "Construction Schedule."

C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and contact information for owners.

D. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

E. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the

Contract Documents. Include evidence of manufacturing experience where required.

F. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

G. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

H. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

I. Research/Evaluation Reports: Prepare w r i t t e n evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

J. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

K. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

L. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

M. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in Division 01 Section "Closeout Operation & Maintenance Requirements."

N. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for i n s t a l l i ng or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

O. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include as applicable statement on condition of substrates and their acceptability for installation of product and summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

P. Results of operational and other tests and a statement of whether observed performance complies with requirements.

Q. Insurance Certificates and Bonds: Prepare written information indicating current status of insurance or bonding coverage. Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of the coverage.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW

A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.

3.2 CONTRACTING OFFICER’S ACTION

A. General: Submittals will be returned disapproved without technical review if:

identification information is missing or placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or if submittals do not show evidence of Contractor's approval.

1. Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.

B. Action Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return one copy.

Contracting Officer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

1. The returned submittal will be marked in one of three ways as defined below:

a. APPROVED: Acceptable with no corrections.

b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.

c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications.

The Contracting Officer will identify the reasons for disapproval.

The Contractor shall revise and resubmit with changes clearly identified.

C. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will reject and return one copy if it does not comply with requirements. Contracting Officer will forward each submittal to appropriate party.

D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

PART 4: MEASUREMENT AND PAYMENT Not Used

END OF SECTION 01 33 00

INDE XXXXXX Section 01 35 20

SECTION 01 35 20 SAFETY REQUIREMENTS

A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2 SUBMITTALS

A. Accident Prevention Plan: After contract award and before the Pre-Construction conference, submit for review an Accident Prevention Plan. The Contracting Officer and the Park Safety Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within 10 days. No progress payments will be made until the Plan is accepted.

1.3 QUALITY ASSURANCE

A. Comply with contract clauses entitled "Accident Prevention" and "Permits and Responsibilities." In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees:

1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.

2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for a l l equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

4. Key Contractor’s personnel including the Site Superintendent and Safety Officer must be fluent in English.

1.4 ACCIDENT REPORTING

A. Reportable Accidents: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of $100. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22).

Form may be obtained from the Contracting Officer.

PART 2 - PRODUCTS

2.1 ACCIDENT PREVENTION PLAN

A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name of responsible supervisor to carry out the program.

2. Weekly and monthly safety meetings.

3. First aid procedures.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase.

5. Training, both initial and continuing.

6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

2.2 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.

2.3 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of applicable ANSI standards.

PART 3 - EXECUTION

3.1 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.2 FIRE AND LIFE SAFETY

A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).

B. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain readily available, on site, MSDS/SDS for each chemical.

1. Immediately report all spills of hazardous materials to the park.

2. Maintain a spill emergency response kit.

3.3 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition.

Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.4 SAFETY MEETINGS

A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite.

B. Review safety issues and concerns at the weekly construction meeting with follow-up as need by the Contracting Officer.

3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. A hard hat area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment at all times. As a minimum, provide three hard hats for use by visitors.

3.6 TRAINING

A. First Aid: Provide adequate training to an adequate number of personnel to ensure prompt and efficient first aid.

B. Hazardous Material: Train and instruct each employee exposed to hazardous materials in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

PART 4 MEASUREMENT AND PAYMENT

4.1 SAFETY REQUIREMENTS

A. Payment will be included in the bid item to which this work relates.

END OF SECTION 01 35 20

INDE XXXXXX Section 01 35 91

SECTION 01 35 91 HISTORIC TREATMENT PROCEDURES

A. This Section includes special procedures for historic treatment on the Project including, but not limited to, the following:

1. Storage and protection of existing historic materials.

2. Temporary protection of historic materials during construction.

3. Protection during application of chemicals.

4. Protection during use of heat-generating equipment.

5. Historic preservation treatment procedures.

1.2 DEFINITIONS

A. "Preservation": To apply measures n eces s a ry t o sustain the existing form, integrity, and materials of a historic property. Work may include preliminary measures to protect and stabilize the property.

B. "Rehabilitation": To make possible a compatible use for a property through repair, alterations, and additions while preserving those portions or features that convey its historical, cultural, or architectural values.

C. "Restoration": To accurately return the form, features, and character of a property to its appearance at a particular period of time by means of the removal of features from other periods in its history and the repair and reconstruction of missing and deteriorated features from the restoration period.

D. "Reconstruction": To reproduce in the exact form and detail a building, structure, or artifact as it appeared at a specific period in time. Reconstructed elements do not possess historic integrity in their own right since it is not original fabric.

E. "Stabilize": To apply measures designed to reestablish a weather-resistant enclosure and the structural reinforcement of an item or portion of the building while maintaining the essential form as it exists at present. This level of intervention is aimed at retarding or arresting adverse impacts to structures.

F. "Protect and Maintain": To remove deteriorating corrosion, reapply protective coatings, and install protective measures such as temporary guards; to provide the least degree of intervention.

G. "Repair": To stabilize, consolidate, or conserve; to retain existing materials and features while employing as little new material as possible. Repair includes

INDE XXXXXX Section 01 35 91 patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials. Within restoration, repair also includes limited replacement in kind, rehabilitation, and reconstruction, with compatible substitute materials for deteriorated or missing parts of features when there are surviving prototypes.

H. "Replace": To duplicate in its entirety a historic element or feature by matching its historic pattern, detail and appearance. Replacement is justified when original or historic elements are damaged beyond repair or are missing.

Replacement methods include the following conditions:

1. Replacement with Original or Historic Fabric: Includes fabric salvaged from other locations or projects having identical architectural qualities.

It means duplication of appearance using identical material possessing historical significance.

2. Replacement with New Materials: Includes replacement with new material of like kind (custom fabricated of manufactured) that is currently in production. It means duplication of appearance using like material.

3. Replacement with Substitute Materials: Includes replacement with a compatible substitute that is frequently contemporary and unlike the historic fabric. It means duplication o f appearance u s i n g modern ( non-traditional) m a t e r i a l . Use of substitute materials is not approved unless matching materials are not available.

I. "Remove": To demolish or detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

J. "Remove and Salvage": To detach items from existing construction and deliver them to the NPS ready for reuse.

K. "Remove and Reinstall": To detach items from existing construction, repair and prepare them for reuse, and reinstall them where indicated.

L. "Existing to Remain" or "Retain": Existing items of construction that are not to be removed and that are not otherwise indicated to be removed and salvaged, or removed and reinstalled.

M. "Material in Kind": Material that closely matches existing materials, through comparison of architectural qualities and salient characteristic such as species, cut, color, grain, dimension, profile, thickness, and finish.

N. “Hot Work”: Any work that involves burning, welding, using fire- or spark-producing tools, or that produces a source of ignition.

1.3 SUBMITTALS

INDE XXXXXX Section 01 35 91

A. Alternative Methods and Materials: If alternative methods and materials to those indicated are proposed for any phase of work, provide a written description including evidence of successful use on other,…