This document outlines the evaluation criteria for a federal contract solicitation to replace chillers at Building 530 for the Department of the Air Force Air Education and Training Command. Contractors must propose removing one existing 250 ton chiller and repairing one existing 275 ton chiller, and installing two new comparably sized Trane air cooled chillers with full Trane lead/lag control capabilities in accordance with the statement of work. Bidders must also propose removing two existing variable frequency drives controlling chiller water pumps and installing two new Danfoss or equivalent VFDs with manual bypass switches. The contractor will further need to install two 600 Amp and one 400 Amp 3-pole transfer switches on the north outside wall of the mechanical room. This opportunity is set aside for women-owned small businesses.

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Evaluation Criteria

The Contractor shall demonstrate that their quote meets all of the criteria listed below to be considered technically acceptable.

Requirement Yes/No Contractor proposed removal of 250 ton and 275 ton existing chillers?

Contractor proposed 2 comparably sized replacement air cooled Trane chillers in accordance with the Statement of Work and justification and approval?

Contractor proposed chillers with complete Trane® lead/lag control capabilities to ensure all compressors and circuits run equally to maximize chiller efficiency?

Contractor proposed removal of two (2) VFD’s controlling chill water pumps?

Contractor proposed to provide and install two (2) new, appropriately sized, “Danfoss” VFD’s or equivalent, with matching manual bypass switches?

Contractor proposed to install two (2)

600 Amp 3‐pole transfer switches on the North outside wall of the mechanical room?

Contractor proposed to install one (1)

400 Amp 3‐pole transfer switch on the

North outside wall of the mechanical room?